WEBpage is NOT an official record of either the Building Committee or
the School Building Committee...official records and
actual minutes plus documentation for actions may be found in Town Hall
or in the offices of the Owner's Representative at the Jarvis Military
Academy (Norfield Road and Weston Road southeast corner) office on 2nd
floor...until close out time.
Building
Committee/School
Building
Committee:
Older reports here.
Are they busy, or what? I'm glad they are getting involved in the
long range development of the central part of Weston!


























FRONT BURNER (NO PUN INTENDED)
ISSUES...INDENTED, MORE RECENT BUSINESS; TO GET
THE BUILDING COMMITTEE HISTORY CLICK HERE:
- BOOSTER
BARN
IN THE
FORUM;
- AN
UNOFFICIAL REPORT: At Board of Selectmen June 4, 2009, discussion
of Booster Barn - would be handled by the Selectmen; application for Clean Energy Fund $$ for
fuel cell at WMS-WHS/Sustainibility Committee named in application -
"About Town" questioned whether the Building Committee should not be in
charge - was assured that they would be - of the construction - until
then, it is the "Sustainibility Committee (aka Global Warming) up
front.
- ALTERNATIVE
ENERGY SUBCOMMITTEE merges back into Building Committee;
Legislature going to
kill this business,
too?
- Please
be
advised...this (top, left) is the Plan for @$80 million. So what is the story about how
we
got to where we are? Click here
for review.
- Next, logo
for
Town's arts partner - SPECIAL
TOWN MEETING ON JUNE 11, 2008 APPROVED AUDITORIUM REDO!
- Town Hall Roof project gets
the go ahead from the Selectmen August 7, 2008;
- BOOSTER BARN REDO - stands for this Fall/Winter;
building for teams to be located next to home stands and facing School
Road - for the Spring. The construction project finishing off in
a spectacular performance by Weston parents: sports families rise
to the challenge again for Booster Barn;
- "ROOFING MATTERS" PAGE - click here;
- And guess what?
Someone replaced
the burned out light bulbs in the Commission Room (both sides of the
room);
- Cartbridge designer to
oversee Auditorium project; one computer-generated view of new
version of Cartbridge.
- REVSON FIELD latest.
- Building Committee to lead
the way on photovoltaic
cell project!
- "SPEAK
UP 2008"
featured lots of questions to and answers from Building
Committee!!! (By "SPEAK UP 2009" the issue of taxes dominated.)
- TOWN HALL ROOF
REPLACEMENTS STALLS (it went ahead after all - see item above) - read earlier report here.
- One
of the most
expensive continuing tasks for local government if replacing roof
structure for municipal facilities;
- KAESTLE BOOS (link to their response, in part, to
RFQ), checked out other facilities' roof
repair needs- draft in October '07, final report in November...it was
presented to the Building Committee in December and then Jan.9,
'08; KAESTLE BOOS' FINAL
NUMBERS PART
OF REPORT HERE.
This is the report that, in 2008 dollars, lays out K-B's opinion of the
physical conditions of schools and some Town buildings.
- New
subcommittee on alternative energy...its new webpage
location (and read unofficial minutes)! Changes
proposed to the State Building Code this Session...
- Update from the Town Administrator...SPECIAL TOWN MEETING
JAN. 17, 2008 to rearranged amounts among the three parts of the
Referendum of Nov. 15, 2001.
- Revson
repair project crisis in March; it was on the Selectmen's agenda
October 4, 2007 (was sent back to Building
Committee); read FORUM story on initial
introduction to Selectmen; unofficial
history from our meeting notes;
- HS
ROOF: done! ATBM OK's funds
in Capital Budget for $36,000 worth of school repair projects.
- Town Hall Roof story - what else do you think
is
needed? Town Hall condition photos;
- Building Committee idea for seeking grant for
photovoltaic cells for high school roof - Selectmen give green
light
and small $$ to get it started;
- Project not completely
losed
out yet; Special
Town Meeting Thursday, March 22 at 8pm in the Weston High School
Cafeteria; money from Question #3 of Referendum of Nov. 15, 2001
moved to new roof on
old section of high school plus $$ for auditorium - no new money;
read the call here.
JMO - WESTON MIDDLE SCHOOL LOOKING COOL!


Shooting
into the sun Sunday on School Road on Bike-Ped Day
WMS Windows and Doors Project winding down - glad they didn't have to
use red colored surrounds, as EPA may have been threatening; matte
black look best!




Building Committee meets
before school starts to inform public of status of WMS window and doors
project. WHS next...
Contractor has creative idea (bottom, center). Committee checks
progress on green sheet (r), green light for WMS opening the result.
BUILDING COMMITTEE: PROGRESS ON WMS PROJECT - NO RED PAINT THE
RESULT IN THE END!
Wednesday, August 22, 2012
Still some parts of the WMS Windows and Doors project still to be
completed
(pool area). Also, more testing - but school can open on schedule
next week! Collection of contractors, architects,
environmental consultants and Owner's Rep explain to the five sitting
members of the Building Committee (with two prospective new members in
the audience).what's gone wrong and what's gone right in this
compressed construction schedule over the summer...looking at the green
sheet, it is clear that WMS is built in two parts - the original in
1960, in the middle, and in 1972, additions including the pool area,
were added, wrapping around much of the original structure. Which
explain to About Town why some spots are inaccesssible - design oops
factor in 1972 (not picked up by anybody at the time)?


Bull heads directly for WMS.
Weston Middle
School's project has a very tight time frame
Weston FORUM
Written by Kimberly Donnelly
Wednesday, 18 July 2012 16:03
A $2-million windows and doors replacement project at Weston Middle
School is progressing on time and on budget.
"I'm really pleased with the contractors. They understand what they are
up against. They've been very responsive," said Town Administrator Tom
Landry earlier this week.
What Secondino and Sons contractors are up against is an extremely
compressed deadline. Because the work they are doing is not only
disruptive, but also includes hazardous material abatement, no one is
allowed in the building until they are done. That means they have
until Sunday, Aug. 26, just about five more weeks. School starts
Monday, Aug. 27.
"They have a very, very tight schedule. Timing will be an issue," Mr.
Landry said. But, so far so good.
Bill Knight, the town's owner's representative on the project, is on
site every day and he said the work is on schedule thus far and things
are going well overall. The weather — hot, making it
uncomfortable at times, but not impossible to work — has not been an
issue, he said. Also, all of the windows and doors have been
assembled and delivered. Mr. Landry said no change orders have
been submitted, which means there are no unforeseen costs of which he
is aware.
Mr. Knight said prep work began on June 18, and then construction
started full tilt not long after school ended on June 21. There
are about 25 to 30 workers on site, working a 10-hour shift, followed
by a crew of mostly abatement workers from Eagle Environmental at night
— including a full-time environmental monitor — taking samples and
doing material and air quality testing.
Hazardous PCBs were discovered in the window caulking and there is a
small amount of asbestos, which turned the project into one that must
be monitored by the federal Environmental Protection Agency (EPA). Mr.
Knight said the samples have to be sent off site for testing, which
takes some time, but the contractor is able to work in clear areas
while other parts of the building are contained during testing.
Once the windows are replaced, Eagle will do more air testing to make
sure the building is clear, Mr. Knight said. Because federal
regulations for PCBs are more vague than for other materials like
asbestos, Mr. Knight said they are using the "most restrictive"
standards they can just to be safe. He expects that by the end of
next week, the abatement process will be mostly complete and a full
second shift of construction workers can come on site.
Many of the windows have been installed on the north side of the middle
school. They are large-paned and slide open sideways to give maximum
light and air flow in the classrooms, most of which are not air
conditioned. Mr. Knight said after all the windows and outside
doors are replaced (concrete pads outside the doors will need to be
redone in several entrances), then soil remediation needs to be done.
Workers will remove and replace about four inches of soil four feet out
from the building to ensure no PCBs are in the ground.
Mr. Landry said the only snafu the project has experienced so far is
the encapsulation paint that was used on the outside of the building
when the windows were removed (meant to catch and contain the PCBs) is
bright red.
"It's ugly but we are working with it because we have to," Mr. Landry
said.
He explained the encapsulation paint they initially intended to use is
clear. The EPA approved the plan back in February or March, but then
just before work began, the agency said it was not familiar with the
clear encapsulation material the town wanted to use.
"They gave us two choices," Mr. Landry said. The town could either
resubmit the project for EPA approval using the clear material — which
would mean the project would not take place this year — or it could use
the red material preapproved by the EPA.
Mr. Knight said after the windows are replaced and the testing is done,
the encapsulation material will be covered with a primer of sorts, and
then another paint that will more closely match the brick on the
outside of the building.
There are already about five different finishes on the middle school,
Mr. Landry said. "It's pretty busy already. A basic design principle is
when you have a lot going on like that, the last thing you want to do
is add more."
WINDOWS AND DOORS PROJECT...THE
BUILDING COMMITTEE
GETS DOWN TO CASES, OR WAS THAT CASEMENTS?
WARNING: Special
Board of Selectmen's meeting Friday March 23, 2012 at 1PM, TOWN HALL
MEETING ROOM - Selectmen OK'd the project
with conditions that review from Town Attorney and confirmation of PCB
number be supplied.
WMS windows and doors project
described in FORUM article here.




THIS IN NOT AN
OFFICIAL REPORT: TWO
HOUR PLUS JOINT MEETING OF BUILDING COMMITTEE AND BOARD OF SELECTMEN
WED., MAR. 21, 2012 AT 7:30PM, COMMISSION ROOM
Chair. of the Building Committee consults with Construction
Manager. First Selectperson calls other Selectman;
Committee member who is architect and in construction business
questions bids. This was a very long meeting and nothing was
decided altho' the Building Committee was still not in favor of moving
forward (2 in favor, 2 opposed and one on the fence - oh, not THE fence
related to the Revson Field controversy). The time factor related
to being able to guarantee window delivery is very much an issue.
KB's architect pointed out the delays initially in getting the project
started forced this tight schedule, then the need for back tracking for
the asbestos and PCB abatement evaluation work...left a short window
for decision-making. That door (or window) may have shut...tune
in to further adventures in Weston school construction projects!


SPECIAL
BOARD OF
SELECTMEN MEETING BALKS AT QUICK APPROVAL OF
WMS WINDOWS/DOORS PROJECT
Special meeting next week to resolves
this after Selectmen have the chance to read contracts - order for
doors has to go in at the end of next week. Any date yet for
Special Meeting?
------------------------


PHOTO FROM APRIL 13, 2011 BUILDING COMMITTEE MEETING; TOWN
WEBSITE BID DOCUMENTS
An example of the window to be used at Weston High School project
(silver one). Really, this time, out to bid!
----------
BIDS COME IN HIGH BUT DO-ABLE - SUMMER
2012 NOW IN PROGRESS ON THE W.M.S. PROJECT...Extra $250,000 to be taken
from General Fund to complete WHS part...or so it seems to us.







BIG MEETING: Looks at WMS,
WHS
windows and doors bottom line, now higher because of EPA reviews;
wetlands remediation work for 2012.
Consultants questioned by Building Committee; new Superintendent
reminds of "Columbine" reqirement for one openable window;
Building Committee Vice-Chair. expresses hope that the windows/doors
project will actually come in for less once design is finalized.
IT'S
A GO ON THE WINDOWS AND DOORS PROJECT - OUT TO BID
SOON! WILL THIS INTERFERE WITH THE WETLANDS REMEDIATION?
The consensus was to go ahead with a modified version of a project
description - no air conditioning but the the "short sighted" option -
cost is higher than originally estimated because of remediation that
has never before been mandated. After bids come back, the
decision will be made whether to go for extra appropriation or just
stretch it out over more years. (NOTE: About Town thinks
that is the reasoning.)
Now it "next summer" and WMS work started...
Wetlands remediation work at Weston
schools postponed until next summer
Weston FORUM
Written by Kimberly Donnelly
Wednesday, 24 August 2011 11:20
The town has been given permission to delay wetlands remediation at the
school campus until next summer when school is not in session.
Tom Landry, town administrator, heard from the Army Corps of Engineers
last Thursday, Aug. 18, that the town’s request to hold off on the
required work had been granted.
The corps had told the town earlier this month that the first phase of
construction had to begin immediately in order for the second phase —
installation of the necessary plantings — to take place in October.
That would have meant the middle and high school campuses would have
been an active construction zone during the first weeks of school, as
well as in October.
However, Colleen Palmer, superintendent of schools, sent a letter to
the town administrator to forward to the Army Corps of Engineers
outlining the reasons why construction would be so disruptive if it
took place while school was in session.
“While no project is painless, the scope of work required in Phase I of
this project would severely impact our ability to educate our students
while school is in session,” Dr. Palmer’s letter read in part.
The superintendent cited health and safety issues, spelled out the
educational impact on students, and raised management issues. Some of
her objections included:
--Diesel fumes, dirt, and dust in classrooms that
have open windows during the warm first weeks of schools might
necessitate a rearrangement of classrooms to accommodate students and
staff with asthma and other respiratory needs.
--Heavy equipment needed for the project would
create a traffic problem, especially during drop-off and dismissal
times. “All four schools of the district are located on one continuous
‘mile of safety’ in our town, whereby the disruption ot the flow of
traffic at one school creates traffic issues throughout the entire
district property housing all of its schools,” Dr. Palmer wrote.
--Noise would not only be a distraction, but might
necessitate moving classrooms, thus disrupting the district’s goal of
“establishing routines and to focus on laying the foundation for
learning for the year.”
--The middle school fields are used for physical
education classes, and having to walk to farther fields would take away
from state mandated instructional time. Recess at the middle school
would also be restricted, and some high school athletic teams’
practices and games would need to be relocated.
--Proximity of the work area and staging of
construction vehicles would impact student and staff parking. “Parking
is already inadequate for the school and any lost parking spaces would
add stress to the system,” Dr. Palmer wrote. A new bus staging area
would also need to be set up.
“As one continuous campus for all of the 2,500 children in its four
schools, this construction project would have varying degrees of impact
on all four schools, from traffic patterns, parking areas, and shared
outdoor resources for student classes and programs. This is not the
typical school configuration in which the impact can be easily
reduced,” Dr. Palmer wrote in her letter.
Mr. Landry said Bill Heiple of Triton Envirnmental, the engineer on the
wetlands remediation project, received an e-mail from Paula Kullberg of
the regulatory division of the Army Corps of Engineers New England last
week. In it, Ms. Kullberg said the town could hold off starting the
remediation work until 2012, “but we will be expecting it to be
performed then.”
Mr. Landry said he is pleased the corps is allowing the town to wait
until next summer. “There will still be some disruption, but ... we
should be able to minimize it,” he said.
Dr. Palmer said she, too, is relieved the heavy construction will not
be done while school is in session.
“I’m ecstatic we will not have a major disruption during the beginning
of the school year, especially with only two weeks notice,” she said.
The requirement to remediate the wetlands behind the middle and high
schools is a result of the school building project that began almost a
decade ago and included building the new intermediate school, and an
addition and renovations at the high school. During construction, some
wetlands were filled in. In order to be able to do that, the town
agreed to construct wetlands elsewhere.
Several attempts to create new wetlands failed. The project was then
delayed when bids came in at nearly double the estimated cost. Work was
pushed off so the project could be re-bid.
The Army Corps of Engineers notified the town on Aug. 12 that it must
begin the first phase of remediation work this fall so that the second
phase can take place in October.
The first phase consists of removing thousands of cubic yards of dirt
and other material from the field. The second phase involves crafting a
new wetlands area; the corps of enginners said the plants required to
create the wetlands need to be planted in October in order for them to
“take” properly.
Mr. Landry said he anticipates each phase of the project will take
several weeks, with the second phase likely taking less time to
complete than the first.
The project is expected to cost about $329,000.
Weston
tries to delay wetlands
remediation until next year
Weston FORUM
Written by Kimberly Donnelly
Thursday, 18 August 2011 00:00
Students beginning the new school year at Weston Middle School and
Weston High School may be heading into the midst of a major
construction zone.
Town and school officials are hoping a letter from Weston
Superintendent Colleen Palmer to the Army Corps of Engineers will allow
the town to delay the start of wetlands remediation work required on
the school campus — but the work has already been delayed for several
years.
The Army Corps of Engineers notified the town last Friday, Aug. 12,
that it must begin the first phase of remediation work this fall so
that the second phase can take place in October.
Tom Landry, town administrator, said the first phase consists of
removing “thousands and thousands of cubic yards” of dirt and other
material from the field between the middle and high school. The second
phase involves crafting a new wetlands area; the plants required to
create the wetlands need to be planted in October in order for them to
“take” properly, Mr. Landry said...full story here.

Power play: Weston eligible for
$1-million grant for fuel cell project
Weson FORUM
Written by Kimberly Donnelly
Wednesday, 11 November 2009 16:38
Calling it a “watershed” moment for Weston, Don Gary of the Building
Committee announced at last Thursday’s Board of Selectmen meeting that
it looks like the Weston schools’ fuel cell project would be eligible
for the maximum state grant of $1,000,000.
The Connecticut Clean Energy Fund (CCEF) finalized its initial review
of the pre-application for the fuel cell project, Mr. Gary said.
Weston, in conjunction with United Technologies Corporation (UTC), the
manufacturer of a 400-kW fuel cell, have been invited by CCEF to
proceed with a formal application.
“This is terrific news for the project and for the town,” Mr. Gary said.
UTC has provided the town with a draft of its Energy Services
Agreement, which is being reviewed by Town Attorney Ken Bernhard. UTC
has agreed, in principle, to construct the entire project at its cost
and to lease it back to the town for 15 years.
Mr. Gary said UTC is obligated to service and maintain the fuel cell —
including replacing it if necessary — for the life of the contract.
Fuel cell project
Mr. Gary and the Alternative
Energy Committee came to the town with the fuel cell proposal in
April of this year.
A fuel cell is an electrochemical device that combines hydrogen fuel
with oxygen from the air to produce electricity, heat and hot water.
Since the fuel is converted directly to electricity, a fuel cell can
operate at much higher efficiencies than internal combustion engines,
extracting more electricity from the same amount of fuel.
It is estimated that the 400-kW fuel cell will provide 95% of the
electricity needed for both Weston High School and Weston Middle
School, all of the heat for the pool at the middle school, a
significant amount of the heat and hot water for the middle school, and
all of the air conditioning for the middle school.
It will also eliminate approximately 900 tons of carbon dioxide from
being released per year. A fuel cell operates on natural gas, but
is
considered renewable because it doesn’t burn anything.
When the natural gas gets to the fuel cell, it pulls out the hydrogen
and forces it through a stack. Electrons from the hydrogen move from an
anode to a cathode and create an electrical current. The byproduct from
this process is hot water — which, ideally, could be used in the
schools and to heat the middle school pool.
“This is truly a green alternative,” Mr. Gary said.
Instant savings
It is also guaranteed to reap financial benefits for the town.
Because
this will be a lease arrangement with no capital expenditures by the
town, Mr. Gary said, energy cost savings will start accruing as soon as
installation of the fuel cell is complete.
While it is not yet possible to project the exact total amount of
energy savings, Mr. Gary said conservative estimates range from $1.5
million to $3 million over 15 years.
One question still remaining is the possible cost of an electrical
connection between the middle school and the high school.
Current practice dictates that CL&P may accept electricity to the
grid (and give full credit for it) through only one meter. To
physically connect both schools to one meter is estimated to cost
upwards of $900,000.
However, the town has argued it can combine the two meters by simple
accounting (adding together the amount of electricity used at each
school).
To reach a determination on this issue, First Selectman Woody Bliss and
Mr. Gary met with both engineering officials and the regional director
of CL&P to see if there are electrical or engineering reasons that
the two meters could not be accounted for as one, or “totalized,” which
is the CL&P term.
“Apparently, we did not need to do it for electrical reasons, it was a
regulatory issue only,” Mr. Gary said.
Mr. Bliss and Mr. Gary then met with engineering and executive members
of the Department of Public Utility Control (DPUC), CL&P’s
governing body, and presented Weston’s case. When they told the
DPUC
the town could just totalize the meters rather than physically connect
them, “that was very well received,” Mr. Gary said.
As a result, Weston is requesting a declaratory ruling that using both
meters would be acceptable. Mr. Gary, Mr. Bliss and Town Attorney
Bernhard drafted the letter of request and sent it to the DPUC, which
has indicated that it will expedite its decision and respond to Weston
within 30 to 60 days.
“When the town hears back from the DPUC, we will be able to present
firm numbers as to the exact savings for the town,” Mr. Gary said.
“Thank you for following up so quickly. This is really a tremendous
benefit for the town,” said Selectman Gayle Weinstein, who was sworn in
this week as the new first selectman.



TAJ MAHAL: Like the original (l.) or like
the terrorist action in Mumbai hotel "Taj" (r.)?
Booster
Barn: Cost estimates are under budget
Weston FORUM
Written by Terry Castellano
Wednesday, 22 July 2009 11:11
The following article has corrected information that was incorrect in
the July 23, 2009 print edition. Corrected information is in bold.
While there are still some “aesthetic” questions, the Booster Barn
project at Weston High School appears to be on track to open at the end
of September.
Peter Figliola, representing the Booster Club, along with First
Selectman Woody Bliss and Building Committee member Don Gary, updated
the school board on the “Weston Stadium Complex Enhancement Project” at
the board’s July 20 meeting.
The board was told the combined cost estimates for completing the
project are about $197,500, well under the $244,190 left in the
bleacher and Booster Barn budget of $513,461.
The town has lent the funds necessary to complete this project to the
Booster Club with the stipulation that revenues realized from the sale
of food and beverages at the concession stand, as well as revenues from
additional sources, will be used to reimburse the town for all money
spent in the building of the barn.
“The [school] board still needs to know what costs the board will incur
in terms of fuel and maintenance,” Ellen Uzenoff, school board
chairman, told Mr. Figliola. Ms. Uzenoff also expressed concern that
the club was proposing a flat-roofed building and asked that Mr.
Figliola research roofing options and return to the board with cost
estimates for roofing that would be more compatible with the school
buildings already in place.
“Aesthetics are key,” Ms. Uzenoff said.
Mr. Figliola reviewed with the board the following:
• The first selectman is now in charge of project oversight.
• The bleachers and press box were installed this past April.
• The Westport-Weston Health District (WWHD) granted the town a waiver
so that five portable toilets could be installed until the Booster Barn
is completed. Lavatory facilities within the high school are considered
by the health district to be too far from the bleachers; therefore, the
building plans will need to include adequate restroom facilities. The
number of toilets is based on the number of bleacher seats and must be
approved by the health district.
• Booster Club representatives have met with the prefabrication
contractor Utility Pre-Cast, the town engineer, and two members of the
building committee to discuss the location of the Booster Barn, the
building, itself, standard configurations, and potential pricing. The
discussion also included drainage system concerns and proximity to
utilities.
• Mr. Figliola, Mr. Gary, and the building inspector reviewed 38
questions from the health district. Globe Equipment, the firm chosen to
supply the kitchen equipment, was instrumental in assisting in the
completion of the health district’s questionnaire.
• Representatives from Globe Equipment also met with Mr. Figliola and
Mr. Gary to discuss the proposed size of the kitchen and equipment
needs based on menu choices.
• Surplus kitchen equipment once used by Weston schools was reviewed
for possible use at the Booster Barn. The Booster Club will accept at
no cost the school district’s surplus “fry-o-lator.”
• On July 17, discussions were held with Utility Pre-Cast to determine
the size of the Booster Barn. On the same day, the location for the
Booster Barn was reviewed and staked out.
Where project is headed
Mr. Figliola expects the project to be completed by Sept. 30 of this
year, and all site work preparation completed prior to the opening of
school.
“The project is moving along and I’m doing everything I can to get it
done,” Mr. Bliss said.
The estimate for the cost of completing the site work is $44,500. Mr.
Figliola is hoping the town and school district’s public works and
maintenance staff may be able to assist with site preparation, thus
lowering estimated costs in this phase of the project.
Most likely, the Booster Barn will need to be larger than the 24-foot x
26-foot prefabricated size originally discussed. The building can still
be prefabricated, but will need to be shipped in sections and assembled
on site. The total cost for the building and its assembly is estimated
to be between $85,000 and $90,000.
The new kitchen equipment is estimated to cost $18,200. Globe Equipment
will design the kitchen for a fee of $1,000, which will be deducted
from the cost of the kitchen equipment if purchased through Globe.
A grease storage tank needs to be purchased and installed at an
approximate cost of $6,000 to $9,000.
The Booster Club has accepted the pro bono services of a Weston
architect to provide design services and architectural drawings.
Mr. Figliola said the next steps in the process of finalizing the
Booster Barn project include:
• Addressing and resolving any further issues involving the health
district.
• Finalizing the architect’s drawings and forwarding them to Utility
Pre-Cast for a formal price quote.
• Reviewing the estimated cost proposal with the selectmen at their
meeting tonight, July 23.
Board member Joe Fitzpatrick asked that Mr. Figliola obtain the WWHD’s
full approval of the project prior to contracting for the purchase of
the building.
If approved by the school district’s facilities committee, the WWHD,
and the selectmen, purchase orders will be issued for the building and
kitchen equipment. Site preparation contractors will be hired with the
expectation that town and school district employees may be able to
assist with site preparation. And, finally, site preparation will
begin, followed by Utility Pre-Cast completing assembly of the Booster
Barn by the end of September.
Even with a 15% contingency account, there is expected to be an
approximate $46,700 budget surplus if all work is completed as proposed.
There are still some areas that need to be addressed, including
security, the building and maintenance of walkways and a stairway,
oversight of organizations’ proper use of the facility, and traffic
safety.
Jerry Belair, superintendent, asked that central office administration
and the school board be apprised of all questions and activities with
regard to this project.
“Please keep us in the loop,” Mr. Belair told Mr. Figliola.
Weston
Booster Barn supporters say: Just build a hot dog
stand, not the Taj Mahal
Weston FORUM
Written by Patricia Gay
Wednesday, June 17, 2009
Supporters of the Booster Barn do not understand why the
selectmen are considering building an expensive concession
stand/bathroom facility at the high school athletic fields, when they
presented a much less costly plan a year ago.
At a meeting of the Boosters Club on Monday, President Brian
McMahon asked First Selectman Woody Bliss to take another look at the
club’s original proposal.
“We have a plan for a Booster Barn facility that will cost
around $70,000, and probably even less in light of the economy,” said
Mr. McMahon.
Mr. Bliss agreed to take a second look at the club’s plan. “I
just want to get it built,” the first selectman said.
The discussion between the Boosters and Mr. Bliss came on the
heels of a selectmen’s meeting last week, where Mr. Bliss said he had
recently visited a concession stand/bathroom facility at Pomperaug
Regional High School in Southbury that he thought would be suitable for
Weston, at a cost of around $200,000.
In April 2008, the Boosters submitted a plan for a modular
concession stand/bathroom facility at an estimated cost of $70,000,
less than half the price of the Pomperaug design.
“We need to cut through the nonsense,” Mr. McMahon said. “A
$200,000 hot dog stand is just plain ridiculous. We’re not building the
Taj Mahal.”
He said the Booster board was enraged that the club’s name would
be associated with such a “ridiculous” proposal. The
Boosters and numerous youth sports clubs in town have a vested interest
in the cost of the Booster Barn because they are footing the entire
bill for the facility. They plan to reimburse the
town through donations and proceeds raised from the operation of the
Booster Barn.
The need for a new Booster Barn arose in 2002, when the original
one was demolished to make way for the school construction
project. Volunteers used the Booster Barn at
sporting events to sell hot dogs and sodas as a way to raise money for
athletic programs. Although the school
construction project is complete, it took several years for bleachers
to be installed at the fields and construction of the Booster Barn is
taking even longer.
Mr. McMahon said one reason for the delay was the Board of
Education didn’t like the design of the modular structure and its flat
roof, so it turned the project over to the town’s Building Committee.
Design costs
The Building Committee hired Kaestle-Boos architects to design
the bleachers and Booster Barn. The architect’s bill for the design
came in at $45,000, $17,000 of which was for the bleachers, according
to Mr. Bliss. Mr. McMahon called the design costs
“outrageous.”
“$17,000 to design bleachers? That’s absurd. Bleachers come
prefab, and they start at the 50-yard line. Site work is included in
the price of the bleachers, so I don’t understand that design price,”
he said.
“We paid $17,000, but I refused to pay the other part of the
bill. They [Kaestle-Boos] knocked [the price] down,” Mr. Bliss said.
Because the
sports community is paying for the project, Mr. McMahon said he would
like to make sure the money is well spent. “We don’t want to put
children’s money toward something like this,” he said.
Mr. McMahon
told Mr. Bliss he will re-submit the club’s original plan to the
selectmen for review.
“If you
want to see what type of facility we are talking about, the same
company has built these in Darien, Greenwich and Danbury. The color of
the brick can be made to match the high school, so it will fit in. The
structure sits on a gravel pad so there is no need for additional
drainage. Really, it’s the simplest solution,” Mr. McMahon said.
Mr. Bliss
asked if the modular unit was compliant with health codes. “It is my
understanding these buildings aren’t health compliant,” he said.
“They’re
health compliant and ADA compliant too.” Mr. McMahon said.
Don Gary, a
member of the Building Committee, who was also at Monday’s meeting,
said if the club plans to make hamburgers at the Booster Barn it will
need to install a grease trap.
“Then we
won’t serve hamburgers, or we’ll cook them on a grill outside. Let’s
sort this out with the health district,” Mr. McMahon said.
Booster Club member Peter Figliola was appointed as the club’s
“conduit” to work further with the selectmen on the Booster Barn
matter.
TOWN TO SEEK F.E.M.A. MONEY
by
BRIAN GIOIELE, FORUM (design
before the Selectmen Oct. 4 for review)
June 13,
2007
Weston settles Losito lawsuit; Electrician to receive $125,000
Weston FORUM
by PATRICIA GAY
Dec 26, 2007
The town has settled a lawsuit with
an electrical contractor that claimed it was owed money from the
intermediate school building project.
On Monday, Dec. 17, Weston’s Board
of Finance approved paying $125,000 to M.J. Losito Electrical
Contractors of Bethel to settle a lawsuit the contractor filed against
the town in May. The selectmen approved the settlement in November.
The finance board’s approval to
allocate the funds puts an end to Losito’s claims against the town,
said Tom Landry, town administrator.
Losito was the electrical contractor
for the intermediate school building project and provided electrical
service, lights, power, voice and data lines, generator, and lighting
fixtures. The school opened in 2005.
The lawsuit said Losito had a
$1,739,000 lump sum written contract with the town to perform all the
electrical work on the project, but claimed the town owed it an
additional $783,032 because of delays and “change order” work requests
that required the contractor to incur expenses that were not in the
original contract.
“When the claim first came in,
O&G said it was without merit. However, after reviewing the claim,
we saw there was some merit. So at the end of the day, we decided to
settle out,” Mr. Landry said. O&G Industries was the construction
manager for the project.
Mr. Landry said most of the claims
from the intermediate school project have been settled and paid, but
there remains one contractor who has threatened to bring a lawsuit but
has not yet done so; and there is a wrongful termination case pending
in Hartford by Harold Mindell, whom the town fired in 2004 as the
owner’s representative on the project.
Mr. Landry also said most of the
written contracts the town made with contractors in the intermediate
school project contained arbitration clauses, so if the contracts were
disputed they would be settled by an arbitration panel and not in court.
However, the Losito contract did not
contain such an arbitration clause. There were at least “a few” other
contracts from the project that did not have that clause, Mr. Landry
said.
KAESTLE-BOOS: DRAFT version discussed at
December 12, 2007
meeting - fantastic work
as far as we can tell, although my own rankings of conditions might
differ - will it get implemented - how? By the Board of Education
and its Facilities Committee, re-ordering priorities and getting real
numbers when projects are up for action...
Beginning at the Weston Middle School, it and
the other school buildings and attendant
facilities are all getting done bit by bit - big ticket items may need
different approach, however.


Building Committee looks at
old
drawings of Town Hall and its presently leaky roof in the Summer of
2006. Finally, work should begin summer of 2008...Board of Selectmen is
looking into a compromise; High School
roof project (old section of school) completed with $$ left over and
ahead of schedule!
Use there guys again!!!
We should watch this project to understand
how you plan for a public safety complex!
Montville selects architect for new
public safety building
By Megan Bard New London Day Staff Writer
Article
published Jun 21, 2010
Montville - For nearly two years, members of the Public Safety Building
Committee has been plodding away at the task of researching the need
for a new safety facility.
Last week, they found out that they're closer then they thought to
sending a proposal to taxpayers in November.
Last week, the committee reviewed architectural designs for the
single-story, 16,000-square-foot facility that could be built at a
17-acre town-owned site that overlooks Haughton Cove at 909 Norwich-New
London Turnpike (Route 32). The property is almost diagonally across
from the Corrigan-Radgowski Correctional Center.
Chairman Jack Platt and others members commented on how swift the
project seems to be moving now, since they've hired an architectural
firm and really gotten into the design work.
An official cost estimate for the project will be presented to the
committee next month but based on a suggestion made that a the group's
meeting last week, the building could cost about $5.1 million. This is
a decrease from the projected $6 million officials thought it would
cost last year.
Although the town is struggling with revenues because of a decrease in
state aid, town fees and investment interest, it is nearly an ideal
time to consider such a project because of the favorable bid market,
according to committee members.
Platt added that depending upon how a bond is structured to cover the
construction costs, it could be done at minimal impact to taxpayers.
Helping is that the town will have just paid off two fairly significant
bonds at about the same time the town would have to float a bond for
the public safety building. This would keep the town's debt at the same
level. The town will also continue to look for grants to help pay for
the construction, officials said.
In May, the town took advantage of the competitive market when it
received 14 proposals for architectural work on the project, with
officials selecting Kaestle Boos Assoc. of New Britain in May. The firm
submitted a $37,000 proposal for the preliminary design and
geotechnical and engineering work and the town added $10,000 to the
budget for contingency.
Last week, David King, an architect with the firm, presented committee
members with preliminary drawings of the proposed facility, which would
house the town's police department, a regional dispatch center and have
a community room for residents.
Members critiqued the drawings - some commented that the police
department's badge on the façade was too pronounced while others
said
they liked the masonry and brick work. Final drawings of the building
will not be available until mid- to late July.
The initial design work is expected to be completed and possibly
approved by the committee and Town Council by September. The goal is to
have a question on the November election ballot asking voters whether
the town should bond the required money to build the facility.
The committee is considering sending out a series of informational post
cards to keep people informed of the project's cost and design, Platt
said.
Weston
eyes
rehab plan for municipal buildings
By JEREMY
SOULLIERE, Hour Staff Writer
July 2, 2007
WESTON — In the coming weeks, the condition of Weston's
municipal and
school facilities will be closely examined to map out a future
rehabilitation plan for the buildings.
The town will be contracting the architectural firm, Kaestle
Boos
Associates of New Britain, to evaluate the bulk of its facilities, Town
Administrator Tom Landry said, with the arrangement close to being
finalized. Kaestle Boos will be assessing a dozen town-owned buildings,
he said, including all the schools, Town Hall, the Weston Public
Library, and the transfer station buildings.
The Board of Finance approved an appropriation of $117,000 for
the
assessment earlier this month, Landry said, approximately $110,000 of
which will be allocated to Kaestle Boos. The remaining funds are set
aside for the contractors running the town's two water pump stations
and the wastewater treatment plant, he said, who will be conducting
their own evaluations at those facilities. Town employees will also be
assessing some of the town's smaller facilities, he said, including the
dog pound and the salt shed.
The idea for a sweeping assessment of town facilities stemmed
from the
schools' request to replace a portion of the high school roof this
year, Landry said, a $1.6 million project that was approved at a
special town meeting this past March. The roof was in critical
condition, he said, and had not been on the town's capital budget radar.
Town officials wanted to avoid such a surprise in the future, he
said,
and the building assessment was a way to do that.
"It became apparent that we needed to identify all these
town-wide
needs in a systematic way," said Landry, who noted the town had not
been in the habit of compiling its long term facility needs in the
past. "We're really trying to get out of being reactive in planning our
building needs. We want to be proactive."
The three month study, which is expected to begin sometime
before the
end of July, will take an inventory of each facility, he said,
examining roofs, doors, windows, foundations, plumbing, heating,
cooling and electrical systems, among other items. They'll gauge how
old each structure and system item is, and estimate when they need to
be replaced, Landry said.
When the study's finished, the town will have a "to do list" it
can
work off of for years to come, he said.
"It will help us prioritize what needs to be done first," he
said.
Once the building priorities are identified, Landry said, town
officials will then be left with the task of determining a financial
plan that will help carry out the future renovations. The town could
decide to set aside funds each year for its building needs, he said, or
take out bonds for the construction projects.
"That's going to have to be a community decision," he said,
referring
to the financial strategy the town will take with future renovations.
ARCHITECT FOR STUDY OF TOWN
AND
SCHOOL BUILDINGS SELECTED FOR INSPECTION AND RECORDING OF
CONDITIONS REQUIRING
FUTURE REPAIR OR REPLACEMENT; FUNDING REQUEST FOR SPECIAL
APPROPRIATION GRANTED!
STUDY FUNDING
OK'd
The Capital Advisory Committee met at 7:45am Monday
morning June 11 at Town Hall to, apparently, approve the request for as
it turns out, $117,000 for a study of Town/School buildings - the Board
of Finance has included this request on their own agenda of Thursday,
June 14, 2007.
The Building Committee, members of the Capital Advisory
Committee including the Town Administrator, Board of Finance, Board of
Education and staff attended a 5:30pm Wednesday, February 7, 2007
meeting in the Commission Room (prior to the School Building/Building
Committee regular meeting, posted for 8pm but actually was right after
this first session) to interview three (3) firms who were invited to
compete for the consulting job of evaluation of schools and some town
buildings (and if we understand the RFP, perhaps looking at
attendant drainege, fields, etc. facilities as well).
"About Town" was impressed with one of the firms especially (who
presented in detail how this task could be done), but we will wait for
the next Building Committee meeting on February 21, 2007 to post news
of that Committee's decision (which will be forwarded, we presume, to
the Board of Selectmen and then to the Board of Finance).
We think it is a fine idea to do such a study so that Town and School
buildings can be maintained properly in a way that will make sure we
don't end up bailing our way out of drainage overflows and potentially
creating indoor air quality problems as mold accumulates in wet places.
----------------------------------------------------
HISTORY: ONE SUBMISSION HERE.
Three (3) responses to RFP for study of facilities of major Town
and
all School buildings received by Board of Education and its Facilities
Director and presented to the Building Committee for review at January
10, 2007 meeting. The estimates (not
considered "bids") of professional work needed and its cost were
$52k, 124k, and $135k. Review by the Building Committee to be
done prior to recommendation to the Boards of Selectmen and Finance, we
assume.
NOTE: ITEM in Captial Budget
FY'08
($175,000) for Town Hall Roof Replacement FY2008. Pictures of
exterior and interior (new section) of Weston Town Hall below (l) - and
work was done!





DO YOU THINK TOWN HALL WAS
SHABBY?
First project, a new
roof...the longer we wait, the more there will be to do; and the drips
keep coming faster now - any mold here? Voila! After roof
repaired, this is what it looks like now (January 2010)! Check
out the wonderful mural!!!
Building Committee
meets with winning firm and cost estimator April 16th...all three Selectmen ask for
"certificate of appropriateness" for fake slate May 7 at the Historic
District Commission - 4-0 "no" from that Commission.
------------
Weston Town Hall roof; Bids higher
than engineer’s estimate
Weston FORUM
by Kimberly Donnelly
Apr 10, 2008
Bids for replacing the roof at Weston Town Hall have
come in well above
the engineer’s estimate for the work. Two bids were received by
the
town and were opened Monday, April 7. Silktown
Roofing of Manchester entered a base bid of
about $607,000. Barrett Roofing of Danbury’s base bid was about
$917,000.
Tom Landry, town administrator, said the original
estimate for the roof
work was about $502,000. Mr. Landry said there is about $150,000
left
in a capital account in the current year’s budget that is designated
for the roof replacement. That is down from an allocation of $175,000,
because some of it was spent on engineering fees and asbestos testing,
he explained. The rest
of the money will likely come from the
general fund surplus,
Mr. Landry said, which will require Board of Selectmen and Board of
Finance approval, and possibly a special town meeting.
The next step now is to send the bids to the
Building Committee for
review. The Building Committee will decide if it will recommend
awarding a contract or if it will go back out for more bids. At
the Board of Selectmen meeting last Thursday,
April 3, Joe
Fitzpatrick, Building Committee chairman, said three companies had
picked up the bid package. Mr. Fitzpatrick said the job is
relatively
complex because it involves two separate roofing systems and facade and
metal work, and it “must be staged in an occupied building.”
There is also a drainage problem, but the
installation of gutters to
address that is not included in the roofing bids, Mr. Fitzpatrick said.
“We’ll work with the town on that,” he said.
Because the roof is slate, Selectman Gayle Weinstein
was concerned the
building have a sufficient support system in place, and she asked if
structural assessments have been done. Mr. Fitzpatrick said they have,
and the building is sound. Mr.
Fitzpatrick said the plan is to complete the
roof work this summer.
HIGHLIGHTS TO THE BUILDING
COMMITTEE/SCHOOL BUILDING
COMMITTEE
PAGE (in reverse chronological order):
- SPECIAL TOWN MEETING
SAYS "YES" TO AUDITORIUM REDO...PREVIOUSLY
- WHAT HAPPENED AT LATE-IN-THE-SCHOOL-YEAR TOWN MEETINGS.
- Special
Town Meeting Thursday, January 17, 2008 at 7pm, Town Hall Meeting Room
rearranged amounts among the three parts of the Nov. 15, 2001
Referendum
- Town-School
Referendum of 2001 no longer a political matter. The voters have
spoken. Revson, Auditorium at W.H.S. and enrollment still live
issues, however.
- At
"Speak Up" on Feb. 3, 2007, March 15 for a Public Hearing, March 22 for
a Special Town Meeting were dates for old section of the High School
Roof replacement project;
- Saturday.
May 13, 2006, 10:30am at Weston High School opening of new now totally
completed additions!
- February-March 2006 the latest end date for construction
of WHS and WIS work;
- Special
Town Meeting
June 17, 2004 votes "NO" on saving big tree at Revson Field - no delay
for school project most important to town;
- Construction
underway
on school projects! Check out official monthly photos HERE.
- NOW ON HOLD:Design
CompetitionW.M.S.
Auditorium/Performance Space: read all about the competition process...WINNER.
- LAST
APPROVAL
RECEIVED (Army Corps - School Road site plan) Dec. 3, 2003; first
bids awarded for steel and concrete.
- TREES
-
new trees
to go at best locations vis a vis new construction (to mitigate view of
construction or activity) - REMOVALS:
- Tree
Hearing Thursday,
November 13, 2003 at 2pm in Town Hall - trees on School Campus posted
for
removal: decision;
- Tree
Hearing,
Monday, September 22, 2003 at 1pm in the Town Hall Meeting Room - report.
- Tree
Hearing Tuesday,
August 26, 2003 re: lights on soccer/lacrosse artificial turf field/see
tree
warden decision.
- "Finishes"
sub-committee
meets early mornings to select materials and look into fine design
detail
(to keep costs down and get the best architectural result
possible)...check
out the types
of brick they may be looking at (this is only an Internet exercise
on THIS WEBpage);
- REFERENUM
VICTORY
(AGAIN) FOR 3-4-5 SCHOOL...APRIL 22 VOTE DECISIVE (65% to 35%) IN FAVOR
OF CONSTRUCION ("NO" VOTE);
- It
is
reported
that School Building Committee/Building Committee Chair. gave thorough
and professional presentation at Special Town Meeting April 10
supporting
3-4-5 school (reasons to vote "no" on April 22 Referendum, in
favor of building the 3-4-5 school);
SOME HISTORY:
- Report
given to
Board of Selectmen
December 5, 2002 by Owner's Rep on status
of school and related work being undertaken.
- First
Selectman
Woody Bliss remarked on Saturday, Nov. 23, 2003 at Kiwanis, School
projects
"on time, on budget" and moving ahead as the community would like it to
do. Former First Selectman Hal Shupack noted at the same meeting
that he was delighted to see the progress and what the project, (begun
under his administration--he did not say this) is becoming.
Everyone
present was impressed by how far the project has come, and how it is
being
managed.
- Weston School Road
Campus Site
Plan approved at October 9, 2002 School Building Committee meeting.
- Check
membership
of the School Building Committee and the Building
Committee (courtesy of the LWV of Weston);
- Referendum
passes,
and the Fletcher-Thompson
scheme approved by voters;
- Prior
to
June
Town Meeting and referendum--this
company, along with construction-managers O&G, picked up where
previous
plans had been left; To view alternatives considered by "Select
Team"
and a summary of framework for planning summer '01 design work - that
did
not take place as originally conceived (i.e. getting better specifics
on
concept designs) - click HERE;
- EVEN
MORE HISTORICAL
DATA: FINAL
OR&L PLAN
and map; unofficial
septic
background;
AND EVEN MORE HISTORY:
- Selectmen OK ED SPECS FOR
State Funding by June 30;
- Board of
Selectmen
(May 4, 2000 meeting) approved extra payment ($19,200) for School
Planner
(OR&L) to draw up education specifications...Ed Specs for four part
Plan. Four buildings and areas around them will be separate
applications.
For example: the new 3-4-5 building and attendent fill, paving,
fields
is one; the high school project plus moving School Road is
two;
the Middle School auditorium and renovations plus loop road is
three;
Hurlbutt renovations and School Road entrance is four. So easy to
explain! (These are my guesses--not confirmed what the four separate
projects
will actually be.)
- MAY 18 and May 25 Dates to
note...On May
18, 2000 at 7:30pm in the Weston Library Fuss&O'Neill presented
their
draft plan for sewers/septic to Town of Weston Boards and
Commissions.
The public was invited...but not to speak.
- On May 25, 2000 at 8pm
in the W.H.S. auditorium, there was be a PUBLIC HEARING on this same
proposal.
On June 1, 2000 (est.) at the Board of Selectmen, a decision was to be
made by that Board, and a recommendation will be made to the Board of
Finance
and then to Town Meeting...
- STOP THE PRESS...May 25 the
800 (est.)
Westonites
present put a stop to the Fuss&O'Neill sewer project option in a
loud
voice (and some great letters later in area newspapers). Thus, in
reading from old commentary on "About Town's" website, it is clear that
a previous Planning and Zoning Commission had strong backing to have
its say in these matters - read about it on this
"Select Committee" link to find out
how an alternative was found; Weston went ahead with this
non-sewer
solution...
Please
remember that this is not the official agenda/notes and if any opinions
are expressed they are those of the author of this website and no one
else's.




(L. to R.) Steve Ezzes (resigned;
now on the Boardof Finance), Ellen
Uzenoff and Dave Coprio at August 22, 2007 meeting.
Underconstruction (W.H.S. Auditorium). STANDING ROOM ONLY.
Up on the roof...
Building and School Building Committee
MEETING DATES 2011 - first
Wednesday, @7:30pm: Specials when needed
BUILDING
COMMITTEE MEETING NOTICE
August 22, 2012 7:30 PM
TOWN HALL COMMISSION ROOM
1. Discussion/decision regarding the project status
of Middle School doors and windows project including schedule, change
orders, and next steps. - William Knight, Owner Rep., Freddy Khericha,
Kaestle- Boos, Dave Secondino, Secondino and Son; Peter Folino, Eagle
Environmental/done -we left at this point.
2. Discussion/ decision regarding Secondino invoice
#4 for payment in the amount of $405,124.65
3. Discussion/decision regarding payment of Eagle
Environmental invoices 10037 ($8,505) and 10087 ( $48,135).
4. Discussion/decision regarding process for planning
and bidding the High School doors and windows project.
5. Any other items of business to be brought up for
Committee consideration
6. Adjourn.
BUILDING
COMMITTEE MEETING NOTICE
February 15, 2012 7:30 PM
TOWN HALL COMMISSION ROOM
1. Discussion/decision regarding status and progress
of the school windows/doors project bid issuance and project schedule.
2. Discussion/decision regarding status and progress
of High School doors and windows design and specifications.
3. Discussion/decision regarding approval of invoices
for doors and windows projects.
4. Discussion/decision regarding Intermediate School
parapet damage and repair, including review of proposal from Richard
Marniki.
5. Discussion/decision regarding Middle School
library renovations.
6. Any other items of business to be brought up for
Committee consideration
7. Adjourn.
BUILDING
COMMITTEE MEETING NOTICE
December 19, 2011 7:30 PM
TOWN HALL COMMISSION ROOM
1. Discussion/decision regarding design documents and
completion status of various tasks by
Kaestle-Boos for the Middle School doors and windows project/Swerdlowe,
Coprio, unan..
2. Discussion/decision regarding repair of
Intermediate School roof and wall damage.- Dan Clarke/fixes made for
this winterto be evaluated and steps taken to assure that this is not
endemic to the building's other similarly detailed features
"About Town" left at this point @9:15pm.
3. Discussion/decision regarding approval of meeting
minutes of November 30 and December 7.
4. Any other items of business to be brought up for
Committee consideration
5. Adjourn.
BUILDING
COMMITTEE MEETING NOTICE
December 7, 2011 7:30 PM
TOWN HALL COMMISSION ROOM
1. Discussion/decision regarding design documents and
completion status of various contract tasks by Kaestle-Boos for the
Middle School doors and windows project. Also, status of the school
windows/doors project environmental report for Middle School and High
School doors and windows projects, as well as the window design, SFU
approvals, work schedule, and self - certification process. – Richard
Kirby of Kaestle Boos.
2. Discussion/decision regarding status and progress
of various Town projects, including boiler project, and DPW suppression
design proposal. – Tom Landry
3. Discussion/decision regarding approval of meeting
minutes of November 30.
4. Any other items of business to be brought up for
Committee consideration
5. Adjourn.
BUILDING
COMMITTEE MEETING NOTICE
December 3, 2011 10:30 AM
MIDDLE SCHOOL FRONT STEPS ("About Town" at a previous commitment)
1.The Committee will meet to inspect conditions at the school
concerning replacement windows and doors, as well as examine existing
conditions.
2. Discussion/decision regarding self - certification process for the
Middle School doors and windows replacement project.
BUILDING
COMMITTEE MEETING NOTICE
November 30, 2011 7:30 PM
TOWN HALL COMMISSION ROOM ("About Town" was out of town at
another meeting)
1. Discussion/decision regarding status and progress
of the school windows/doors project environmental report, window
design, SFU approvals, recent work proposals, invoice approval, and
work schedule.
2. Discussion/decision regarding status and progress
of various Town projects, including boiler project, and DPW suppression
design proposal. – Tom Landry
3. Discussion/decision regarding approval of meeting
minutes of November 16.
4. Any other items of business to be brought up for
Committee consideration
5. Adjourn.
BUILDING
COMMITTEE MEETING NOTICE
November 19, 2011 10:00 AM
HIGH SCHOOL FRONT LOBBY ("About Town" was attending the "After
the Storm" meeting)
The Committee will meet to inspect conditions at the school concerning
replacement windows and doors, as well as heating and ventilation
systems and classroom layout
Building
Committee meets Monday, November 14, 2011.
With a quorum present, window and doors architects Kaestel Boos and
engineer go over time line for this complex project - to be
spreadover the next two summers. Board of Ed represented by
Director of Buildings and Grounds, who has been in contact with EPA for
its review regularly. Project is in Contract Documents Phase
prior to going out to bid.
BUILDING
COMMITTEE MEETING NOTICE
October 19, 2011 7:30 PM
TOWN HALL COMMISSION ROOM
1. Discussion/decision regarding status and progress
of the school windows/doors project environmental report, window
design, SFU approvals, recent work proposals, invoice approval, and
work schedule. Superintendent Palmer, First Selectman Weinstein, Ron
Bathrick , Richard Kirby, John F. and others invited/it is a go for
sending one of the alternatives, modified, out to bid - About Town left
to go to the Charter Revision Commission after this item.
2. Discussion/decision regarding status and progress
of various Town projects, including boiler project, and DPW suppression
design proposal. – Tom Landry
3. Discussion/decision regarding approval of meeting
minutes of October 5.
4. Any other items of business to be brought up for
Committee consideration
5. Adjourn.
BUILDING
COMMITTEE MEETING NOTICE
October 5, 2011 7:30 PM
TOWN HALL COMMISSION ROOM
1. Discussion/decision regarding status and progress
of school projects, particularly the school windows/doors project
environmental report, SFU approvals, recent work proposals, and work
schedule
2. Discussion/decision regarding status and progress
of various Town projects, including boiler project, and DPW suppression
design proposal.
3. Discussion/decision regarding approval of meeting
minutes of September 14.
4. Any other items of business to be brought up for
Committee consideration
5. Adjourn.
BUILDING
COMMITTEE MEETING NOTICE - no
quorum present.
September 14, 2011 7:30pm
TOWN HALL COMMISSION ROOM
DISCUSSED: Consultants and Board of Education facilities director
present to prepare for EPA submissions of high school/WMS windows and
doors plus environmental reports; air handlers study.
BUILDING
COMMITTEE MEETING
NOTICE
August 31, 2011 7:30 PM
TOWN HALL COMMISSION
ROOM
No quorum present.
1.
Discussion/decision regarding status and progress of school projects,
particularly the school windows/doors project environmental report, SFU
approvals, and work schedule/discussion with architect, environmental
consultant and engineer, going over project scheduling.
2.
Discussion/decision regarding status and progress of various Town
projects, including boiler project, and DPW suppression design
proposal/no discussed.
3.
Discussion/decision regarding approval of meeting minutes of August
1/not done.
4. Any other items
of business to be brought up for Committee consideration
5. Adjourn.
NOTE:
"About Town" did not attend - but stopped in @9pm to see if there was a
quorum after the Charter Revision Commission met. We were told
that Allen Swerdlowe is the new Chair.
BUILDING COMMITTEE MEETING
NOTICE
August 17, 2011 7:30 PM
TOWN HALL COMMISSION ROOM
1. Discussion/ decision regarding the selection of
Committee officers necessitated by the resignation of Chairman Don Gary
from the Committee.
2. Discussion/decision regarding status and progress
of school projects, particularly the school windows/doors project
environmental report, SFU approvals, and work schedule
3. Discussion/decision regarding status and progress
of various Town projects, including boiler design proposal.
4. Discussion/decision regarding approval of meeting
minutes of July 13.
5. Any other items of business to be brought up for
Committee consideration
6. Adjourn.
BUILDING COMMITTEE MEETING
NOTICE
July 12, 2011 7:30 PM (the 13th, actually)
TOWN HALL COMMISSION ROOM
1. Discussion/decision regarding status and progress
of school projects, including school windows environmental report.-
Carl Goedecke and consultants/provedures tightened up to make sure
bills come to the (School) Building Committee - bills authorized to be
paid that were due at this meeting.
2. Discussion/decision regarding status and progress
of various Town projects, including boiler design proposal/done.
3. Discussion/decision regarding status and progress
of fuel cell project/awaiting final approval of bill pased plus
interpretation of "net metering.".
4. Discussion/decision regarding approval of meeting
minutes of June 15 and June 29/done with correction..
5. Any other items of business to be brought up for
Committee consideration
6. Adjourn.
BUILDING COMMITTEE MEETING
NOTICE
June 29, 2011 7:30 PM
TOWN HALL COMMISSION ROOM
1. Discussion/decision regarding status and progress
of school projects, including school windows environmental report.-
Carl Goedecke/long discussion, draft reports discussed; meeting
in 2 weeks with consultants on windows/doors/environmental issues.
2. Discussion/decision regarding status and progress
of various Town projects, including boiler design proposal/proposal
received.
3. Discussion/decision regarding status and progress
of fuel cell project/report that Board of Education had voted
positively - next stop, P&Z.
4. Discussion/decision regarding approval of meeting
minutes of June 15/not done.c
5. Any other items of business to be brought up for
Committee consideration/thanks to member who was retiring from Building
Committee.
6. Adjourn.
BUILDING COMMITTEE MEETING
NOTICE
June 15, 2011 - 7:30 PM
TOWN HALL COMMISSION ROOM
1. Discussion/decision regarding status and progress
of school projects, including school windows- Carl Goedecke/no report
yet on extent of PCB's.
2. Discussion/decision regarding status and progress
of various Town projects/some items ready to go out to bid, others
not..
3. Discussion/decision regarding status and progress
of fuel cell project/good news on the legislative front..
4. Discussion/decision regarding approval of meeting
minutes of May 25/done.
5. Any other items of business to be brought up for
Committee consideration/openings - one Democrat and one Republican
available.
6. Adjourn/next meeting June 29 at 7:30, CR..
BUILDING COMMITTEE MEETING
NOTICE
May 25, 2011 7:30 PM
TOWN HALL COMMISSION ROOM
1. Discussion/decision regarding status and progress
of school projects, including school windows- Richard Kirby, Kaestle
Boos and Ron Bathrick, CES/not very promising, to put it mildly - at
least a year away
from starting, in our opinion.
2. Discussion/decision regarding status and progress
of various Town projects/moving ahead slowly on boiler replacement,
DPW projects (somewhat faster).
3. Discussion/decision regarding status and progress
of fuel cell project/nothing new, except solar panels to be put
forward??? Discussion must take place outside the meetings.
4. Discussion/decision regarding approval of meeting
minutes of April 13/approved.
5. Any other items of business to be brought up for
Board consideration - next meeting June 15.
6. Adjourn.

Window upgrades: to be used at Weston High School old sections.
BUILDING
COMMITTEE MEETING
NOTICE
April 13, 2011 7:30 PM
TOWN HALL COMMISSION ROOM
1. Discussion/decision regarding status and progress
of school projects, including school windows/review and page by page
comments on details of window replacement.
2. Discussion/decision regarding status and progress
of various Town projects, including final payment for library
roof/unanimous vote in favor of payments..
3. Discussion/decision regarding status and progress
of fuel cell project/School has gotten 2 year price better than fuel
cell rates unless Legislature SB#1 passes (with joint metering section).
4. Discussion/decision regarding approval of meeting
minutes of March 16/approved.
5. Any other items of business to be brought up for
Board consideration - other Feb. meeting apptoved
6. Adjourn.
BUILDING COMMITTEE MEETING
NOTICE
March 16, 2011 7:30 PM
TOWN HALL COMMISSION ROOM
1. Discussion/decision regarding status and progress
of various school projects, including school windows.
2. Discussion/decision regarding status and progress
of various Town projects.
3. Discussion/decision regarding status and progress
of fuel cell project.
4. Discussion/decision regarding approval of meeting
minutes of February 9.
5. Any other items of business to be brought up for
Board consideration
6. Adjourn.
BUILDING COMMITTEE MEETING
NOTICE
February 9, 2011 7:30 PM
TOWN HALL COMMISSION ROOM
1. Discussion/decision regarding status and progress
of various school projects, including school windows.
2. Discussion/decision regarding status and progress
of various Town projects.
3. Discussion/decision regarding approval of meeting
minutes of November 17.
4. Any other items of business to be brought up for
Board consideration
5. Adjourn.
BUILDING COMMITTEE MEETING
NOTICE - didn't happen
January 26, 2011 7:30 PM
TOWN HALL COMMISSION ROOM
1. Discussion/decision regarding status and progress
of various school projects.
2. Discussion/decision regarding status and progress
of various Town projects.
3. Discussion/decision regarding approval of meeting
minutes of November 17.
4. Any other items of business to be brought up for
Board consideration
5. Adjourn.
BUILDING COMMITTEE MEETING NOTICE:
Saturday, December 11, 2010, 9:30 AM INTERMEDIATE SCHOOL. Committee
members will take a walking tour of the facility with
School Facilities Manager Dan Clarke. A quorum of the Committee may be
present.
BUILDING COMMITTEE
MEETING NOTICE
November 17, 2010 7:30 PM
TOWN HALL COMMISSION ROOM
1. Discussion/decision regarding closeout of the
Middle School Roof project. Carl Goedecke/done and under budget!.
2. Discussion/decision regarding project update and
status for: Library roof, hvac replacement, Jarvis House painting, town
hall heating, and DPW sprinkler projects/going well, generally.
3. Discussion/decision regarding the Fuel Cell
project/preview of what will be presented to the Selectmen, and then to
Board of Ed, Board of Finance, (P&Z?) and Town Meeting..
4. Discussion/decision regarding approval of meeting
minutes of October 16/approved.
5. Any other items of business to be brought up for
Board consideration/future scheduling of walk of school project
condition.
6. Adjourn.
BUILDING COMMITTEE
MEETING NOTICE
October 6, 2010, 7:30 PM
TOWN HALL COMMISSION ROOM
1. Discussion/decision regarding the progress of the
Middle School Roof project. Carl Goedecke./Rain put it just a bit
behind - next week it should all be completed
2. Update on status of Library roof project, and
discussion of ongoing inspection component./Building Committee to
review just what "inspection" protocol has to be done with on site
visit
3. Discussion/decision regarding Kohler-Ronan project
proposal for Town Hall./not exactly what they were expecting
4. Discussion/decision regarding Kohler-Ronan project
proposal for DPW suppression system./looks ok
5. Discussion/decision of school grounds maintenance
and landscaping./discussion ensued.
6. Discussion/decision regarding approval of meeting
minutes of September 16/done
7. Any other items of business to be brought up for
Board consideration - fuel cell on Selectmen's agenda.
8. Adjourn.
BUILDING COMMITTEE
MEETING NOTICE
September 16, 2010, 7:30 PM
(Thursday)
TOWN HALL COMMISSION ROOM
1. Recognition of Joe Fitzpatrick for past
service/done
2. Discussion/decision regarding the progress of the
Middle School Roof project. Carl Goedecke - on time under budget a bit.
3. Discussion/decision regarding proposed
Kaestle-Boos contract for the school doors and windows project/?.
4. Discussion/decision regarding status of Library
roof project/starts next week.
5. Discussion/decision regarding insulation proposal
for Town Hall/nothing yet.
6. Discussion/decision regarding the Fuel Cell
project/discussions upcoming on possible ways to move forward.
7. Discussion/decision regarding approval of meeting
minutes of August 25/done.
8. Any other items of business to be brought up for
Board consideration/how can the general maintenance of the grounds and
buildings be improved?
9. Adjourn.
BUILDING COMMITTEE
NOTICE
Town Hall Commission Room
August 25, 2010, 7:30pm
1. Recognition of Joe Fitzpatrick for past service/rescheduled
for next meeting..
2. Discussion/decision re: progress of the Middle School Roof
project/all but one small area of roof (loading dock) finished - the
work remaining will be "quiet" work and be finished by the end of
September..
3. Discussion/decision re: proposed Kaestle Boos contract for
school doors and window project/discussion with Director of Facilities
of the Bd of Ed as to how to modify contract with KB.
4. Dikscussion/decision re: status of contract signings for
Library roof project, and the oversight component/nothing new.
5. Discussion/decision re: insulaton proposal for Town Hall/no
work decided upon after full discusson of all the different parts of
analysis needed.
6. Discussion/decision re: Fuel Cell project/DPUC heard new
request.
7. Discussion/decision re: approval of meeting minutes of June 7,
24, July 14, and August 4, 2010/approved.
8. Any other items of business to be brought up for Committee
consideration.
9. Adjourn.
BUILDING COMMITTEE
NOTICE
Town Hall Commission Room
August 4, 2010, 7:30pm
1. Approval of minutes 7-14-10/not done?
2. Discussion/decision re: progress of the WMS roof
project/@60% copmplete, on time, on budget; walk-thru of roof the
other weekend made a difference in requirements for construction that
will lengthen the life of this roof replacement..
3. Discussion/decision re: status of bid award of the Library
roof project and pursuit of project oversight component/recommendation
to Selectmen to award contract
4. Discussion/decision re: viability of geothermal HVAC systems
and/or updating conventional systems for town and school
buildings/nothing new
5. Fuel Cell update/plans moving ahead to prepare for various
Boards and Commissions and possibly DPUC again.
6. Any other items
7. Adjourn
BUILDING COMMITTEE
MEETING NOTICE
July 17, 2010 9 a.m.
MIDDLE SCHOOLFRONT STEPS
1. Site Visit to observe the progress and status of
the Middle School Roof project.
2. Adjourn.
BUILDING COMMITTEE
NOTICE
Town Hall Commission Room
July 14, 2010
1. Approval of minutes 6-24-10/done
2. Discussion/decision re: progress of the WMS roof
project/report - @60% complete; AUGUST 10 PRIMARY WILL BE HELD IN
THE CAFETERIA - NO PARKING IN THE REAR.
3. Discussion/decision re: status of bid award of the Library
roof project and pursuit of project oversight component/awarded and now
looking to hire clerk of the works.
4. Discussion/decision re: viability of geothermal HVAC systems
and/or updating conventional systems for town and school buildings/no
news
5. Fuel Cell update/ne news
6. Any other items
7. Approval of WMS roof invoices/done
8. Adjourn
BUILDING COMMITTEE
NOTICE
June 24, 2010, 7:30pm
Town Hall Commission Room
1. Discussion/decision re: progress on Middle School Roof
project/2 bills approved - comment that bills should be paid more
promptly; three parts of the more than 2 dozen part complete
without detailing; color selections.
2. Discussion/decision re: bid award or re-bid of the
Library Roof project/recommendation to the Board of Selectmen to go
ahead; unanimous recommendation of one of the proposals to do the work.
3. Discussion/decision re: viability of geothermal hvac
systems for town and school buildings/probably not, but more work to be
done to show payback...boilers at Town Hall assessment; decision
to proceed to get proposal.
4. Any other business/fuel cell update
5. Adjourned around 9:30pm..
BUILDING COMMITTEE
MEETING NOTICE
May 12, 2010 7:30 PM
TOWN HALL COMMISSION ROOM
1. Discussion/decision regarding the Middle School
roof project oversight/unanimous vote to recommend same owner's rep who
did so ably on School Construction to Board of Selectmen
2. Discussion/decision regarding status of fuel cell
project. Don Gary/further discussions taking place to make sure all
questions the Committee has are answered.
3. Discussion/decision regarding design of
replacement of Town Hall heating system/report given by member who
checked this out most recently, and analysis.
4. Any other items of business to be brought up for
Board consideration/none
5. Adjourn.
BUILDING COMMITTEE
MEETING NOTICE
March 31, 2010 - 7:30 PM
TOWN HALL COMMISSION ROOM
1. Discussion/decision regarding the Middle School
roof project ( bid review, award recommendation, project oversight ).
Kim Winchell, H.B. Fishman/done
2. Discussion/decision regarding update on the
proposed specifications for replacement of the library roof/bid
specs OK'd but deduct for newest section. .
3. Discussion/Decision regarding approval of release
of Action Air check in the amount of $45,913 for the auditorium
project/done.
4. Discussion/decision regarding design of
replacement of Town Hall heating system/will review this and act at a
later date..
5. Discussion/decision regarding status of fuel cell
project/costs estimated by CL&P and soon UTC will have theirs in
draft form.
6. Any other items of business to be brought up for
Board consideration/minutes approved from Feb.17 and March 3.
7. Adjourn.
BUILDING COMMITTEE
MEETING NOTICE
March 3, 2010, 7:30 PM
TOWN HALL COMMISSION ROOM
1.
Discussion/decision regarding update on the proposed specifications for
replacement of the Middle School roof. Kim Winchell- HB
Fishman/done
2. Any other items of business to be brought up for
Board consideration
3. Adjourn.
BUILDING COMMITTEE
MEETING NOTICE
February 10, 2010 7:30 PM - RESCHEDULED FOR FEB.
17th, 7:30pm
TOWN HALL COMMISSION ROOM
1. Discussion/Decision regarding design for DPW
garage fire suppression system- John Pokorny, Fire Marshal/discussion,
no decision
2. Discussion/decision regarding update on the
proposed specifications for replacement of the library roof/no decision
3. Discussion/decision regarding design of
replacement of Town Hall heating system/discussed
4. Any other items of business to be brought up for
Board consideration/minutes of previous meeting approved.
5. Adjourn.
BUILDING COMMITTEE
MEETING NOTICE
December 9, 2009 7:30 PM
TOWN HALL COMMISSION ROOM
1. Discussion/Decision regarding status of fuel cell
project.- Don Gary/done
2. Discussion/decision regarding the status of the
High School Auditorium closeout- Tom Landry/we will probably make a
profit.
3. Discussion/decision regarding closeout of the
School Construction Project.- Tom Landry/$500,000 reimbursement still
available on school project - change orders not included in settlements
to be resubmitted/and reviewed for missing signatures, etc. by Town
staff.
4. Discussion/decision regarding library roof design
status- Tom Landry/money in place - design prepared and should go out
to bid @January 2010 to get the best price, interest.
5. Discussion/decision regarding election of
Committee Chair and Vice Chair for January 2010-December 2011/Don Gary
elected Chair., Richard Wolf, Vice-Chair.
6. Any other items of business to be brought up for
Board consideration - Capital Advisory Committee to meet Monday,
December 14, 2009 at 7:45am in the Town Hall Meeting Room.
7. Adjourn.
BUILDING COMMITTEE
MEETING NOTICE
October 29, 2009 7:30 PM
TOWN HALL COMMISSION ROOM
1. Discussion/Decision regarding status of fuel cell
project- UTC/report and update - news to be forthcoming in 45 days or
so.
2. Discussion/decision regarding the status of the
High School Auditorium closeout/bills still need review by O&G
before School Construction Unit will make decision on eligibility for
reimbursement.
3. Discussion/decision regarding library roof
design/direction given to Town Administrator to proceed with first
phase of design (OPTION TWO), to ready for Spring bids.
4. Any other items of business to be brought up for
Board consideration/Town air conditioning replacement units reviewd.
5. Adjourn.
(Special) BUILDING
COMMITTEE NOTICE/rescheduled from
July 27) to Wednesday, August 19, 2009 at 7:30pm in the Commission Room
at Town Hall
Town Hall Commission Room
Wednesday, August 19, 2009
1. Discussion/decision
regarding status of Fuel Cell project - UTC/presentation from 7:31 to
9:13pm with discussion of the draft study and estimates for several
options serving WMS & WHS.
2. Any other items/none
3. Adjourn
(Special?) BUILDING
COMMITTEE
MEETING NOTICE
TOWN
HALL COMMISSION ROOM
April
29, 2009 7:30 PM
1. Discussion/decision re: Town Hall Roof Replacement
Project/report - last walk thru scheduled
2. Discussion/decision re: status of Booster Barn
construction project/to start up again
3. Discussion/decision re: status of the Auditorium
project/still need items such as reports.
4. Discussion/decision re: fuel cell alternative energy
project status/moving ahead along with Selectmen to pursue varies grants
5. Any other business (?)
6. Adjourn
BUILDING COMMITTEE
MEETING NOTICE
TOWN
HALL COMMISSION ROOM
April
1, 2009 7:30 PM
1.
Discussion/decision regarding status of the Town Hall roof replacement
project.- Tom Landry/last things getting fixed now; will have to
go back to Historic District Committee for approval of roof over the
Communications Center (should not be a problem).
2.
Discussion/decision regarding status of Booster Barn construction
project. Tom Landry/not to be ready for more review until after the
summer (we think that is what we heard)
3.
Discussion/decision regarding status of the Auditorium project.- Carl
Goedecke/working well ("Hello Dolly" went well)
4.
Discussion/decision regarding Energy Education Initiative/we left
before this (taken up after next item)
5.
Discussion/decision regarding fuel cell alternative energy project
status. Allen Swerdlowe/vote to ask Selectmen and Finance to fund
feasibility study
6. Any other items
of business to be brought up for Board consideration
7. Adjourn.
NO MEETING IN
FEBRUARY
Special Building Committee/School Building Committee,
Wednesday, January 21, 2009 at 7:30pm, Town
Hall Annex on School Road. See notes (draft)
1)
Attendance: quorum present (JF, DG, AS, DC, RW); JP from
WestonArts; MSW; DMcN -K-B; RG.
2) Call Meeting to Order: done
3) Approve Minutes of Previous meetings:done
4) Booster Barn: Kaestle-Boos has made changes,
Building Official reviewed these
5)
HS Auditorium Project: still no heat
6)
TOW Town Hall Roof Replacement: ?
7) Alternate Energy Committee :
Update
8) New Business as may properly come before the
meeting: none
9) Executive Session As required/none
10) Change Orders & Invoice Approval for Payment:
Consultant & Other Invoices; Submission to the SBC for review &
approval, if any/none
11) Next Meeting(s): Feb. 4, 2009 @ 7:30 PM, TOW,
Town Hall, Commission Rm.
12) Adjournment: 9:04pm
NOTE: we missed the meeting
in January (now only once a month for regulat meetings...)
Building Committee/School Building Committee,
Wednesday, December 17, 2008 at 7:30pm, Commission
Room at Town Hall.
1)
Call Meeting to Order: Meeting called to order/done
2) Approve Minutes of Previous meetings: Approve of
Meeting Minutes of 12/03/08/done;
3) Booster Barn: estimated cost too high
a)
Project Status;
b)
Permits;
c)
Budget & Schedule;
4)
HS Auditorium Project: remaining work to be done, but it opened earlier
in the week
a)
Construction & Punch List Schedule / Status;
b)
Review of requested lighting changes;
c)
Budget
5)
TOW Town Hall Roof Replacement: Project Update/?
6) Alternate Energy Committee Presentation /
Discussion: more in January
7) New Business as may properly come before the
meeting: As required;
8) Executive Session - conducted
a)
Mediation review of C&H claim;
b)
Mediation review of FT claim;
9)
Change Orders & Invoice Approval for Payment: Consultant &
Other Invoices; Submission to the SBC for review & approval, if
any
10) Election of Chairman and Vice-Chairman for
2009/Fitzpatricy, Chair., Wolf, Vice-Chair.
11) Next Meeting(s): Jan 7, 2009 @ 7:30 PM, TOW, Town
Hall, Commission Rm.
Building Committee/School Building Committee,
Wednesday, December 3, 2008 at 7:30pm, Commission
Room at Town Hall. Reconvening at WHS Auditorium @8:45pm
A quorum of
the School Building Committee was present. Minutes were
approved. Discussion of other projects, then an on-site visit to
the auditorium - which is getting there!!! See photos here.
Building Committee/School Building Committee,
Wednesday, November 19, 2008 at 7:30pm, Commission
Room at Town Hall.
A quorum of
the School Building Committee was present. Minutes were
approved. Presentation in detail of the latest working drawings
(?) of the Booster Barn and Stands/Press Box were shown by
Kaestle-Boos. The status of the High School Auditorium was next -
things going well and on schedule to be completed by the first week of
December. Seats coming next Monday - a few days to install.
Building Committee/School Building Committee,
Wednesday, November 12, 2008 at 7:30pm, Commission
Room at Town Hall.
1)
Attendance:
2) Call Meeting to Order: Meeting called to order
3) Approve Minutes of Previous meetings:
Approve of Meeting Minutes of 8/17/08; 10/15/08 &
10/29/08/done
4) Booster Barn: Design Update; Budget &
Schedule/nothing new
5) HS Auditorium Project: pressure to finish on time
a)
Auditorium Renovation:
i)
Construction & Schedule Status
ii)
Budget review
iii)
Review of pending CO’S
6)
TOW Town Hall Roof Replacement: Status discussed
7) Alternate Energy Committee Presentation /
Discussion: Sub-Committee to review progress to date
8) New Business as may properly come before the
meeting/?
9) Executive Session As Required - we left.
10) Change Orders & Invoice Approval for Payment:
Consultant & Other Invoices; Submission to the SBC for review &
approval, if any CRG
11) Next Meeting(s): November 19th 2008 @ 7:30 PM,
TOW, Town Hall, Commission Rm.
12) Adjournment:
Building Committee/School Building Committee,
Wednesday, October 29, 2008 at 7:30pm, Commission
Room at Town Hall.
1)
Attendance: quorum present
2) Call Meeting to
Order:
3) Approve Minutes of Previous meetings: 10/15/08/not
done
4) Booster Barn:
a)
Proposal / Schedule / Design considerations/go ahead given on latest
design
b)
Budget Review
5)
HS Auditorium Project: discussion of budget, which is OK for now, then
visit to WHS
a)
Auditorium Renovation:
i)
Construction Status
ii)
Schedule Update
iii)
Budget review
iv)
Review of pending CO’S (CAR’S)
6)
TOW Town Hall Roof Replacement: going great!
a)
Status
b)
Roof Gutter Design
7)
Alternate Energy Committee Discussion:
8) New Business as may properly come before the
meeting:
9) Executive Session As Required
10) Change Orders & Invoice Approval for Payment:
Consultant & Other Invoices; Submission to the SBC, if any
11) Next Meeting(s): November 12, 2008 @ 7:30 PM,
TOW, Town Hall, Commission Rm. a) Reschedule Meeting
planned for 11/26/08
12) Adjournment:
Building Committee/School Building Committee,
Wednesday, October 15, 2008 at 7:30pm, Commission
Room at Town Hall.
1)
Attendance: quorum present
2) Call Meeting to Order: Meeting called to order
@
PM
3) Approve Minutes of Previous meetings:
a) Approve of Meeting Minutes of 10/01/08/done
4) HS Auditorium Project: Full review of where
the project stands (a bit behind) and report from builder as well as
staff; payment of some bills made.
a)
Auditorium Renovation:
i)
Construction Status
ii)
Schedule Update
iii)
Review of pending CO
5)
TOW Town Hall Roof Replacement: a) Schedule
Update/moving along.
6) Booster Barn: presentation by Kaestle-Boos
with rep of Booster Barn group present - some aspects of design set,
budget still limits design possibilities.
a)
Proposal / Schedule / Design considerations
b)
Budget Review
7)
Alternate Energy Committee Discussion: a) Discussion
if any/nothing to report on RFP
8) New Business as may properly come before the
meeting:
9) Executive Session a) As Required
10) Change Orders & Invoice Approval for Payment:
a) Consultant & Other Invoices; Submission to the
SBC, if any
11) Next Meeting(s): October 29, 2008 @ 7:30 PM, TOW,
Town Hall, Commission Rm.
12) Adjournment: Meeting adjourned @ _____:_____ PM
Building Committee/School Building Committee,
Wednesday, October 1, 2008 at 7:30pm, (changed from WHS
Auditorium at 4:30pm Wednesday) TOWN HALL COMMISSION ROOM.
DRAFT agenda
posted at 4pm, Tuesday, September 30 - all "the usual suspects" on the
agenda (Auditorium, Town Hall roof replacement, Booster Barn,
Alternative Energy, new business, executive session, if needed, change
orders and invoices for payment, next meeting October 15).
BOOSTER BARN: Kaestle Boos and Board of Education came for design
discussions, will be back in 2 weeks. AUDITORIUM: budget
review and report; TOWN HALL ROOF: no work this week.
Special Building Committee/School Building Committee,
Wednesday, September 17, 2008 at 7:30pm, Weston High School Auditorium.
1.
Attendance/quorum present
2. Call the meeting to order/done
3. HS Auditorium Project: renovation progress, schedule,
financial status/on schedule and moving ahead, change orders total
discussed
4. Alternative energy committee discussion - RFP
extension/meeting next week
5. Town Hall Roof update/starting next week?
6. Booster Barn Process update/budget set, date of completion
set--now they have to see working drawing for full design, preferably
under the bleachers
7. Approval of the minutes of 9-3-08/done
8. Executive Session/we left- no vote to go into executive
session.
9. Any other business
10. Change orders and invoice approval
11. Next meeting Oct. 1, 2008 at 7:30pm
Special Building Committee/School Building Committee,
Wednesday, September 3, 2008 at 7:30pm, Weston High School Auditorium.
1)
Call Meeting to
Order:
2) HS Auditorium Project: all these items
discussed with the necessary folks - who were all in attendance
a)
Auditorium Renovation – Carlson Construction, IES,TPC, Art DiCesare
Progress/Schedule
ii) Schedule, shop drawing review, outstanding info requests, wall
finishes, seat layout
4)
Alternate Energy Committee Discussion: RFP extension/responses due very
soon
5) Town Hall Roof Update/start in
two weeks - slate delay shorter than initially thought
6) Booster Barn Process
Update/letter to Selectmen from Building Committee (it is on the
Selectmen's Agenda tonight)
7) Minutes Approval 8-06-08,
8-27-08 (?) - we left at @9:15pm
8) Executive Session ( if needed)
9) Any Other Business
10) Change Orders & Invoice
Approval:
11) Next Meeting(s): September 17,
2008 @ 7:30 PM (location?)
Special Building Committee/School Building Committee,
Wednesday, August 27, 2008 at 7:30pm, Weston High School Auditorium
(revised agenda includes Booster Barn).
1. Call
Meeting to order
2. H.S. auditorium project: Owner's rep reports on slippage in
schedule, other progress.
a. Auditorium renovation - Carlson
Construction/decisions made on details
i) Progress/schedule
ii) Carpet order and
selection/wall finishes
b. Ducharme - revision to some rows
i) Schedule status, fabric
status, layout approval
ii) Stain sample
c. IES - shop drawing review/information
request
3. Alternative Energy Committee Discussion - RFP response report
by Town Administrator.
4. Town Hall Roof update/nothing new
5. New Business (?) - Booster Barn (request from Board of
Education to make comment on two part project) - a letter from the
Building Committee will be formally written to reflect the unanimous
vote taken by the members of the Building Commmittee.
6. Minutes approval 8-06/next week
7. Executive Session (if needed)
8. Any other business (?)
9. Change orders & invoice approval
10. Next meeting Sept. 3 (NEXT WEEK ALSO AT THE AUDITORIUM)
Building Committee/School Building Committee,
Wednesday, August 6, 2008 at 7:30pm, Commission Room of Town Hall.
1)
Call Meeting to
Order - no quorum for either School or regular building committees
2) HS Auditorium Project:
a)
Auditorium Renovation – Carlson Construction/report from clerk of the
works - it was suggested by the Town Administrator that the next
meeting be held at the auditorium. Contract at the Selectmen Aug.
8 for OK
i) Progress/Schedule
ii) Carpets/ Wall Finishes
b)
Ducharme
i) Schedule Status
ii) Armrest resolution, Stain Sample
c)
IES - Shop
drawing review/ information request
4)
Alternate Energy Committee Discussion: RFP Status/sent to 3 consultants
(screened from a larger number interviewed previously); responses due
two weeks from August 8
5) Town Hall Roof Update/plans to
go ahead with project as approved by the building committee
6) Booster Barn/report from sports
group and First Selectmen
7) Middle School Roof / proposal
for repair - will consider alternative energy on both this roof and the
high school (response to "About Town" question
8) Change Orders & Invoice
Approval: O&G Invoice/approved
9) New Business as may properly
come before the meeting:
10) Minutes Approval for July 23,
2008 Meeting/approved with one change (Ellen Uzenoff did not vote on
Town Hall Roof)
12) Executive Session (if needed) -
no mention in the agenda of the item to be discussed - as no quorum was
present, discussion of whatever item was to be revealed was not in
executive session (you have to vote to go into executive session) - but
we left, so the discussion took place in open session without any
public present.
13) Next Meeting(s): August 20?, 2008 @
7:30 PM, TOW, Town Hall, Commission Rm./we did not stay, so we are not
certain of the date, time or location of the next meeting.
Building Committee/School Building Committee,
Wednesday, July 23, 2008 at 7:30pm, Commission Room of Town Hall.
1)
Call Meeting to Order/done
2) HS Auditorium Project: going well, according
to Town's representative
a)
Auditorium Renovation – Carlson Construction/work progressing;
i) Contract Status/signed copy rec'd by
Town.
ii) Carpets/ Wall
Finishes/discussion on detail of carpet, curtain and test of how walls
can be redone with consistent look
b)
Ducharme - Fabric Status/seating layout appointment July 28;
fabric ordered; Oct. 15 finish date
3) Alternate Energy Committee Discussion: RFP
Status/report on progress
4) Town Hall Roof Update/slate to
be ordered for 2 month delivery;
5) New Business as may
properly come before the meeting:
6) Executive Session ( not needed)
7) Change Orders & Invoice
Approval:
8) Next Meeting(s): August 6, 2008
@ 7:30 PM, TOW, Town Hall, Commission Rm.
Building Committee/School Building Committee,
Wednesday, July 9, 2008 at 7:30pm, Commission Room of Town Hall.
1) Attendance/quorum present
2) Call Meeting to
Order/done
3) HS Auditorium Project:
a) Auditorium
Renovation – Carlson Construction
i) Contract Status/not signed yet
ii) Proposed Schedule/week of Oct 26 is
finishing date
iii) Curtains/Carpets, Wall Finishes/discussion with clerk
of the works
b)
Ducharme
i) Contract Status/signed
ii) Fabric Status/explanations for the
clerk of the works
4) Alternate Energy Committee
Discussion: RFP Status/needs work, according to town
5) Town Hall Roof Update/Town
Administrator noted that the last word had not been heard on this
matter.
6) New Business as may
properly come before the meeting:
7) Executive Session: As Required;
C&H; FT
8) Change Orders & Invoice
Approval
9) Next Meeting(s): July 23?, 2008
@ 7:30 PM, TOW, Town Hall, Commission Rm.
10) Adjournment: Meeting
Special Building Committee/School Building Committee,
Wednesday, June 25, 2008 at 7:30pm, Commission Room of Town Hall.
No quorum present.
1. High
School Auditorium Project:
a.
Auditorium Renovation - Carlson Construction/Construction monitoring in
place with capable construction firm.
1)
Contract/to be discussed on Friday with Town
2)
Preconstruction meeting
3)
Schedule
b.
Ducharme
1)
Contract/also Friday discussion
2)
Fabric/wood finish/choices
of colors, fabrics and finish of wood made for auditorium seating
3)
Schedule
2.
Alternative Energy Committee discussion, if any/nothing new
3. New Business
4. Executive Session, as required - C&H; FT;P&P
5. Change orders and invoice approval
6. Next meeting - July 9
Special Building Committee/School Building Committee,
Wednesday, June 11, 2008 at 6:30pm, high school auditorium prior to
Special Town Meeting - "About Town" did not attend.
Special Building Committee/School Building Committee,
Wednesday, June 4, 2008 at 7:30pm, Commission Room at Town Hall
1)
Attendance:
2) Call Meeting to Order: Meeting called to order
3) Approve Minutes of Previous meetings: Approve of
Meeting Minutes of 4/30/08 & 5/14/08/done
4) HS Auditorium Project: full discussion with
both Carlson Construction and Owners Rep
a)
Auditorium Renovation:
i)
Review contract with IES & proposed contractor
ii)
Schedule
iii)
Interview of TOW Owners Rep / Project Construction Manager
5)
TOW Town Hall Roof Replacement: Schedule Update/? We left (@9pm)
at this point.
6) School Commissioning:
a)
HS:
i)
Commissioning Update & Report
b)
3-5 School:
i)
Commissioning Update / Report
7)
Alternate Energy Committee Discussion: Discussion if any
8) New Business as may properly come before the
meeting:
9) Executive Session As Required; C&H; FT; P&P
10) Change Orders & Invoice Approval:
Consultant & Other Invoices; Submission to the SBC, if any
11) Next Meeting(s): June 18, 2008 @ 7:30 PM, TOW,
Town Hall, Commission Rm.
Special Building Committee/School Building Committee,
Wednesday, May 21, 2008 at 7:30pm, Commission Room at Town Hall
1)
Call Meeting to Order: Meeting called to order @
7:30PM
2) HS Auditorium Project:
a) Auditorium
Renovation:
i) Review of
proposal and cost estimates with Innovative Engineering Solutions
3) Next Meeting(s): Tuesday, May 27, 2008 @
7:30 PM, with BOS/BOF, Town Hall Meeting Room
Building
and School Building Committee, Wednesday,
May 14, 2008 at 7:30pm, Commission Room at Town Hall:
1)
Approve Minutes of Previous meetings: Minutes of 4/30/08 - not done
2) HS Auditorium Project:
a) Auditorium
Renovation:
i) Bidding Review; SBC
recommendation to Board Of Selectman/report and need for more review
ii) Schedule/June 11
Special Town Meeting; May 27 Board of Selectmen/Board of Finance
at 8pm to decide the "call" for Special Town Meeting
iii) Hiring of Project
Construction Manager/working on it
3) TOW Town Hall Roof
Replacement: Contract / Schedule/slate selected like the existing type
(weathers after 10-15 years to varied colors)
4) O&G Schedule / Progress:
a) HS:
i) Roof Contract Close
out
ii) Commissioning
Update & Report
b) 3-5 School: Commissioning Update / Report
5) Alternate Energy
Committee Discussion: Building Committee will meet at 7pm May 27
to
6) New Business as may properly come before the
meeting:
7) Executive Session As Required; C&H; FT; P&P
8) Change Orders & Invoice Approval: Consultant
& Other Invoices; Submission to the SBC, if any
9)
Next Meeting(s): May 21; June 4, 2008 at 7pm, Town
Hall Meeting Room; 8pm Joint Board of Selectmen/Board of Finance
Building/School
Building Committee, Wednesday, April 30, 2007, 7:30pm, Commission
Room at Town Hall
1) Call Meeting to
Order - qurom present
2) Approve Minutes of Previous meetings: Meeting
Minutes of 4/2/08 & 4/16/08/done
3) HS Auditorium Project: Bid opening Tuesday,
May 6, 2008 at 2pm in Town Hall Meeting Room (we assume the Meeting
Room will be used)
a) Auditorium
Renovation:
i) Bidding Progress;
ii) Schedule;
4) TOW Roof
Replacement: Board of Selectman meeting discussion of 4/24/08/Historic
District Commission May 7 (8pm, Weston Library) to consider Selectmen's
request for non-slate roof, we think - no notice yet posted.
5) O&G Schedule / Progress: ?
a) HS: Commissioning Update & Report
b) 3-5 School:
i) Close-out; Pipe
& Power
ii) Commissioning
Update / Report
6) Alternative Energy
Committee Discussion/ All members except for one who was out of
the country met the evening of ATBM April 21 (minutes taken by a member
who will be submitting them) and considered revisions to a tentative
RFP; discussion ensued of the best way to get all parties who
will be involved in recommending funding fully informed of progress as
the revision to the RFP moves along.
7) New Business as may properly come before the
meeting:
8) Executive Session As Required; C&H; FT; P&P
9) Change Orders & Invoice Approval: Consultant
& Other Invoices; Submission to the SBC, if any
10) Next Meeting(s): May 14, 2008 @ 7:30 PM, TOW,
Town Hall, Commission Rm.
Building/School
Building Committee, Wednesday, April 16, 2007, 7:30pm, Commission
Room at Town Hall - agenda (since there are now only five members
on the Building Committee, THERE WAS A QUORUM PRESENT [Steve Ezzes
resigned effective with the Board of Selectmen's acceptance on April 3,
2008])
1) Call Meeting to
Order:
2) Approve Minutes of Previous meetings: Approve of
Meeting Minutes of 4/2/08
3) HS Auditorium Project: discussion of bidder
availibility
a) Auditorium
Renovation Bidding update: Bid due; Construction Schedule; Seating
Bid; Seating Schedule;
4) TOW Roof
Replacement: Discussion of Bids Received & Possible
Alternates/discussion of differences between estimate and bids.
5) O&G Schedule / Progress:
a) HS: Commissioning Update & Report
b) 3-5 School:
i) Close-out; Pipe
& Power
ii) Commissioning
Update / Report
6) Alternate Energy
Committee Discussion: Discussion
7) New Business as may properly come before the
meeting:
8) Executive Session As Required; C&H; FT; P&P
9) Change Orders & Invoice Approval:
a) HS: Proposed Change
Orders, if any
b) HS: Applications For
Payment, if any
c) 3-5 School: Proposed
Change Orders, if any
d) 3-5 School:
Applications For Payment, if any
e) Invoices: Other
Invoices for submission to the SBC, if any
10) Next Meeting(s):
Building/School
Building Committee, Wednesday, April 2, 2007, 7:30pm, Commission
Room at Town Hall - agenda
1)
Approve Minutes of Previous meetings: Minutes of 3/19/08/done
2) HS Auditorium Project:Auditorium Renovation Presentation;
Progress; Budget - Schedule, Bidders & Bidding/full set
of nearly complete plans for bidding shown.
3) TOW Roof
Replacement: Bid due 4/7/08;
4) O&G Schedule / Progress:
a) HS: Commissioning Update & Report
b) 3-5 School:
i) Close-out; Pipe
& Power
ii) Commissioning
Update / Report
5) Alternate Energy
Committee Discussion: Discussion/ to be included in the April 3 review
for the Selectmen
6) New Business as may properly come before the
meeting: see above--also report on Kaestle-Boos and the auditorium and
perhaps Revson.
7) Executive Session As Required; C&H; FT; P&P
8) Change Orders & Invoice Approval:
a) HS: Proposed Change
Orders, if any
b) HS: Applications For
Payment, if any
c) 3-5 School: Proposed
Change Orders, if any
d) 3-5 School:
Applications For Payment, if any
e) Invoices: Other
Invoices for submission to the SBC, if any
9) Next Meeting(s):
April 16, 2008 @ 7:30 PM, TOW, Town Hall, Commission Rm.
Building/School
Building Committee, Wednesday, March 19, 2008, 7:30pm, Commission
Room at Town Hall - agenda
1)
Approve Minutes of Previous meetings: Minutes of 3/5/08/done
2) HS Auditorium Project: Auditorium Renovation
Presentation; Progress; Budget & Schedule/long review of "probable
cost" $1,703,452, presentations by four consultants (architect,
engineer, threatre specialist and lighting and sound specialist.
3) TOW Roof Replacement: Bid meeting 3/17/08
review; bid opening April 10. At 10:25pm we left.
4) O&G Schedule / Progress:
a) HS: Commissioning Update & Report
b) 3-5 School:
i)Close-out; Pipe & Power
ii)Commissioning Update / Report
5) Alternate Energy
Committee Discussion: Discussion
6) New Business as may properly come before the
meeting:
7) Executive Session As Required; C&H; FT; P&P
8) Change Orders & Invoice Approval:
a) HS: Proposed Change
Orders, if any
b) HS: Applications For
Payment, if any
c) 3-5 School: Proposed
Change Orders, if any
d) 3-5 School:
Applications For Payment, if any
e) Invoices: Other
Invoices for submission to the SBC, if any
9) Next Meeting(s):
April 2, 2008 @ 7:30 PM, TOW, Town Hall, Commission Rm.
Building/School
Building Committee, Wednesday, March 5, 2008, 7:30pm, Commission
Room at Town Hall - agenda
1) Approve Minutes of
Previous meetings: Minutes of 2/6/08/done
2) HS Auditorium Project: moving ahead - need more
detail to be able to get price correct
a) Auditorium
Renovation Progress; Budget
i) Design Development
Update w/estimates
3) HS Roof anticipated
Close-out Update/did good!
4) TOW Roof Replacement: went out, got 4 or 5
responses; bid opening in April.
a) Bid Contract for the
Town Hall;
b) Water drainage from
Building/not discussed
5) O&G Schedule /
Progress: almost there!
a) HS:
i) Close-out; Shawn’s
Lawns
ii) Commissioning
Update & Report
b) 3-5 School:
i) Close-out; Pipe
& Power
ii) Commissioning
Update / Report
c) Hurlbutt: Close-out,
Shawn’s Lawns
6) Alternate Energy
Committee Discussion: Discussion / Interview for additional new
member/interview
7) New Business as may properly come before the
meeting: discussion of auditorium schedule
8) Executive Session - As Required; C&H; FT;
P&P
9) Change Orders & Invoice Approval:
a) HS: Proposed Change
Orders, if any
b) HS: Applications For
Payment, if any
c) 3-5 School: Proposed
Change Orders, if any
d) 3-5 School:
Applications For Payment, if any
e) Invoices: Other
Invoices for submission to the SBC, if any
10) Next Meeting(s):
March 19, 2008 @ 7:30 PM, TOW, Town Hall, Commission Rm./might be an
additional one if it will help move auditorium along.
Building/School
Building Committee, Wednesday, February 6, 2008, 7:30pm, Commission
Room at Town Hall - agenda
1) Approve Minutes of
Previous meetings: Approve of Meeting Minutes of 1/23/08/done
2) HS Auditorium Project: full discussion - Captial
Committee to review it on Friday, Feb. 8 at 8am in Town Hall.
a) Auditorium
Renovation Progress; Budget w/ alternates
i) Schematic Design
with estimates
ii) Recommended
enhancements with associated costs
3) HS Roof anticipated
final cost/almost completed.
4) HS & TOW Roof Replacement: Bid Contract for
the Town Hall; almost ready to go out.
5) O&G Schedule / Progress:
a) HS:
i) Close-out status;
Shawn’s Lawns
ii) Commissioning
Update & Report
b) 3-5 School:
i) Close-out status;
Pipe & Power
ii) Commissioning
Update / Report
c) Hurlbutt: Close-out
status, Shawn’s Lawns
6) Alternate Energy
Committee Discussion: see Alternative Energy Committee notes.
7) New Business as may properly come before the
meeting:
8) Executive Session As Required; C&H; FT
9) Change Orders & Invoice Approval:
a) HS: Proposed Change
Orders, if any
b) HS: Applications For
Payment, if any
c) 3-5 School: Proposed
Change Orders, if any
d) 3-5 School:
Applications For Payment, if any
e) Invoices: Other
Invoices for submission to the SBC, if any
10) Next Meeting(s):
February 20, 2008 @ 7:30 PM, TOW, Town Hall, Commission Rm.
Building/School
Building Committee, Wednesday, January 23, 2008, 7:30pm, Commission
Room at Town Hall -
draft agenda
1) Call Meeting to
Order: Meeting
2) Approve Minutes of Previous meetings: Approve of
Meeting Minutes of 1/09/08/done
3) HS Auditorium Project:
a) Auditorium
Renovation Progress; Presentation of revised budget w/ alternates -
fully discussed (2 hours); preparation for Board of Finance discussion
on Feb. 14.
i) Schematic Design
with estimates/we did not get a copy of the estimates, but they seemed
in the right neighborhood
ii) Recommended
enhancements with associated costs/second consultant for special
lighting may be retained
iii) Motorized vs.
Counter weight rigging with associated costs/motorized
4) HS & TOW Roof
Replacement: Comments on bid documents for the Town Hall; Proposal for
extended construction services/reviewed and suggested ideas for more
specifics in the works
5) O&G Schedule / Progress: closer
a) HS:
i) Close-out status;
Check to Nettleton authorized; Open – M J Daily, Shawn’s Lawns
ii) Commissioning
Update & Report
b) 3-5 School:
i) Close-out status;
Pipe & Power Update; Check to Losito authorized
ii) Commissioning
Update / Report
c) Hurlbutt: Close-out
status, Shawn’s Lawns
6) Alternate Energy
Committee Discussion: we left prior to this.
7) New Business as may properly come before the
meeting:
8) Executive Session As Required
9) Change Orders & Invoice Approval:
a) HS: Proposed Change
Orders, if any
b) HS: Applications For
Payment, if any
c) 3-5 School: Proposed
Change Orders, if any
d) 3-5 School:
Applications For Payment, if any
e) Invoices: Other
Invoices for submission to the SBC, if any
10) Next Meeting(s):
February 6, 2008 @ 7:30 PM, TOW, Town Hall, Commission Rm.
Building/School
Building Committee, Wednesday, January 9, 2008, 7:30pm, Commission
Room at Town Hall -
agenda
1) Call Meeting to
Order:
2) Approve Minutes of Previous meetings: Minutes of
12/12/07/done
3) HS Auditorium Project: consultant did not
show up - Building Committee to have contacts by e-mail before next
regular Building Committee meeting - when a decision about how to
proceed occurs
a) Auditorium
Renovation Progress; Presentation of revised budget w/ alternates
i) Schematic Design
with estimates
ii) Recommended
enhancements with associated costs
iii) Motorized vs.
Counter weight rigging with associated costs
4) Facilities Review:
Kaestle Boos Report/draft presented on cost summary in 2008 dollars
minus "soft costs" - work suggested to be done has been ranked 1-5 (5
being in greatest immediate need). We saw the early numbers, but
it would not be helpfull if we mentioned any, as this was a "draft"
summary.
5) HS & TOW Roof Replacement:
a) HS Roof Skylight;
Alt. Proposal “Fischer Skylight”/patch it (present patch is working)
for now
b) Final bid documents
for the Town Hall/done and presented to Building Committee - three
options and some seeming to be in-kind replacement for this structure
in the Historic District
6) O&G Schedule /
Progress: getting closer to being done
a) HS:
i) Close-out status;
Final Payment to Nettleton; Open – M J Daily, Shawn’s Lawns
ii) HS Servery Grease
Hood system
iii) Commissioning
Update & Report
b) 3-5 School:
i) Close-out status;
Pipe & Power Update; Final Payment to Losito
ii) Commissioning
Update / Report
c) Hurlbutt: Close-out
status, Shawn’s Lawns
7) Alternate Energy
Committee Discussion: applicant for sub-committee
interviewed. What are the latest F.O.I. requirements for
subcommittees? (We left at this point)
8) New Business as may properly come before the
meeting:
9) Executive Session as Required
10) Change Orders & Invoice Approval:
a) HS: Proposed Change
Orders, if any
b) HS: Applications For
Payment, if any
c) 3-5 School: Proposed
Change Orders, if any
d) 3-5 School:
Applications For Payment, if any
e) Invoices: Other
Invoices for submission to the SBC, if any
11) Next Meeting(s):
January 23, 2008 @ 7:30 PM, TOW, Town Hall, Commission Rm.
Building/School
Building Committee, Wednesday, December 12, 2007, 7:30pm, Commission
Room at Town Hall -
agenda
1) Approve Minutes of
Previous meetings: Approve of Meeting Minutes of 11/13/07 &
11/28/07/done
2) HS Auditorium Project:
a) Project Budget
Clarification Continued: understood that previous Board of Finance
understood the need for additional $$
b) Auditorium
Renovation Progress Update/moving along, meetings held with advisor to
users and users
3) Facilities Review:
Schedule, Kaestle Boos Presentation/excellent presentation of DRAFT (we
saw a copy); final user product will be in Excel or similar electronic
form permitting easy changes
4) HS & TOW Roof Replacement:
a) HS Roof Skylight;
field review of 12/12/07/more to come
b) TOW Town Hall; Phase
I, HBF; Presentation Update/?
5) O&G Schedule /
Progress: OK
a) Project Cost Report:
b) HS:
i) Close-out status;
ii) Commissioning
Update if any
c) 3-5 School:
i) Close-out status;
ii) Commissioning Update
d) Zenon Plant: Close out status; Merritt
e) Hurlbutt: Close-out
status, Shawn’s Lawns
6) Election of Officers, 2008:
a. School Building Committee, Joe
Fitzpatrick, Chair., Richard Wolf, Vice-Chair.
b. Building Committee, JF, RW
New Business as may
properly come before the SBC meeting: Alternative Energy
Subcommittee of Building Committee (Allen Swerdlow) formed
and
will
first meet Saturday, Dec. 15 at 10am, CR
7) Executive Session As Required - none required
8) Change Orders & Invoice Approval: we left
a) HS: Proposed Change
Orders, if any
b) HS: Applications For
Payment, if any
c) 3-5 School: Proposed
Change Orders, if any
d) 3-5 School:
Applications For Payment, if any
e) Invoices: Other
Invoices for submission to the SBC, if any
9) Next Meeting(s):
January 9, 2008 @ 7:30 PM, TOW, Town Hall, Commission Rm.
Building/School
Building Committee, Wednesday, November 28, 2007, 7:30pm, Commission
Room at Town Hall - draft
agenda - Quorum present; Town Administrator and Town Finance
Director present to discuss items 4 and 5
1) Approve minutes/?
2) HS Auditorium and Roof projects - acoustical consultant
proposal/approval/need assurance from Board of Finance that they
will honor the full $1.6 million estimate
3) HS and Town Hall Roof Replacements - presentation by
HBFishman/many different options, several good solutions--costs may
vary from original $175k to $350k to $470k for al slate or fake slate -
final report on what project will look like due in January.
4) Facilities Review: Kaestle Boos schedule/draft of raw
data in the hands of Schools and Building Committee for review (copies
for members being made)
5) O&G Progress/Schedule/comparison of Town accounting vs.
O&G - not much difference--but three-part bond issue needs to be
reconfigured to show that more money was spent on
6) Alternative Energy Committee Proposal/we left (9:50pm)
7) New Business
8) Executive Session as required
9) Change Orders
NEXT MEETING: Dec. 12 and the one after that January 9.
SPECIAL Building
Committee/School
Building Committee, TUESDAY,
November 13,
2007, 7:30pm, Basement of Town Hall
1) Call Meeting to
Order/done
2) Approve Minutes of Previous meetings: Approve of
Meeting Minutes of 10/31/07/done
3) HS Auditorium & HS Roof Project Budget: budget
questions as related to the Town Meeting call - need to return to the
Board of Finance to complete the auditorium (the roof came in at $2.1
million of the total amount approved at the March 22 Special Town
Meeting. First Selectman, Town Administrator and Town Finance
Director present for this.
a) Project Budget Clarification:
b) Acoustical Consultant’s proposal: to be
discussed at the next meeting
4) HS & TOW Roof Replacement:
a) HS Roof Skylight; update/nothing new
b) TOW Town Hall; Phase I, HBF;
Presentation/going to cost several times the amount in the Capital
Budget 2007-2008
5) Facilities Review: Schedule, Kaestle
Boos/nothing to see yet.
6) O&G Schedule / Progress: still no agreement
about how much money was spent - Town has one amount and O&G
calculate differently.
a) Project Cost Report: Review
b) HS:
i) Close-out status;
ii) Commissioning Update if any
c) 3-5 School:
i) Close-out status;
ii) Commissioning Update
d) Zenon Plant: Close out status; Merritt
e) Hurlbutt: Close-out status, Shawn’s
Lawns
7) Alternative Energy Committee
Proposal/to be presented at the Board of Selectmen - NOTE: no
agenda yet available to the general public, but the Building Committee
knows about it (?)
8) New Business as may properly come before the SBC
meeting:
9) Executive Session As Required/we left at this point
10) Change Orders & Invoice Approval:
a) HS: Proposed Change Orders, if any
b) HS: Applications For Payment, if any
c) 3-5 School: Proposed Change Orders, if
any
d) 3-5 School: Applications For Payment,
if any
e) Invoices: Other Invoices for submission
to the SBC, if any
11) Next Meeting: November 28, 2007
Building Committee/School
Building Committee, Wednesday, October 31,
2007, 7:30pm, Commission Room at Town Hall
1) Approve Minutes of Previous
meetings:Minutes of 10/03/07 & 10/17/07/done
2) HS Auditorium: Architect (IES)/schedule to
complete drawings set.
a) Project Update:
b) Project Schedule, Schematic Design,
Budget
3) HS & TOW Roof Replacement:
done
a) HS Roof Skylight; update
b) TOW Town Hall; Phase I, HBF;
Presentation
4) Facilities Review: Schedule, Kaestle
Boos/draft in hand
5) O&G Schedule / Progress:
a) Project Cost Report: Status - still not
clear
b) HS:
i) Close-out status;
ii) Site; Richards, Grading, HS requested
sidewalk; retainage reduction
iii) Commissioning Update if any
c) 3-5 School: almost there?
i) Close-out status;
ii) Commissioning Update
(1) Balancing proposal recommended by
K&R corrections (Wings)
d) Zenon Plant: Close out status; Merritt/done?
e) Hurlbutt: Close-out status, Shawn’s
Lawns
6) Alternative Energy Study/not discussed
7) New Business as may properly come before the SBC
meeting:
8) Executive Session: as Required
9) Change Orders & Invoice Approval:
a) HS: Proposed Change Orders, if any
b) HS: Applications For Payment, if any
c) 3-5 School: Proposed Change Orders, if
any
d) 3-5 School: Applications For Payment,
if any
e) Invoices: Other Invoices for submission
to the SBC, if any
10) Next Meeting(s): November 14, 2007 @
7:30 PM, TOW, Town Hall, Commission Rm.
Building Committee/School
Building Committee, Wednesday, October 17,
2007, 7:30pm, Town Hall - Draft agenda (10/10)
1 Minutes
2. Facilities review
3. Roof replacement - Town Hall, HS skylight
4. O&G - various closeout requirements on all projects; final
project cost report (to be issued Oct 17)
5. HS auditorium
6. New business
7. Exec Session - HS AUDITORIUM contract; claims, as required
8. Change orders and invoice approvals
NEXT MEETING: October 31, 2007, 7:30pm, Commission Room
Building Committee/School
Building Committee, Wednesday, October 3,
2007, 7:30pm, Town Hall Meeting Room/revised agenda removes Revson
issue.
1. Minutes September 5, 18/OK
2. Facilities Review - Kaestle Boos/to be ready with numbers for
Board of Education facilities by (draft)October-final in November
3. HS and Town Roof reflacement:
- HS- Silktown, skylight/roof done, skylight needs work
- TOW - existing conditions, Town Hall, field survey/in the
works--not settled yet as to exactly what will be done over Commission
Room
4. O&G schedule: Final project cost report
- HS - closeout, Silktown, Commissioning/in the works
- 3-4-5 -Commissioning, balancing corrections/"
- MFP - close out status - Shawn's lawns, Sentrale/?
- Zenon - close out, Merritt/?
- Hurlbutt - close out - Shawn's lawns/?
5. Revson
Field-not on revised agenda
6. New Business
7. Executive Session - contracts - HS Auditorium, claims as
required
8. Change orders
9. NEXT MEETING? Friday, at Board of Education annex,
7:45am, Kaestle Boos review in Dr. Keatings' office (?)
NOTE:
Revised agenda issued Friday re-arranges order of items, removed
specific item on high school roof-photovoltaic cells.
Special Building
Committee/School Building Committee, Tuesday, September 18, 2007,
7:30pm,Commission Room at Town Hall
Approve Minutes of Previous meetings: Approve of Meeting Minutes of
9/05/07 SBC
Executive
Session -/not needed
a) Contracts – HS
Auditorium
b) Claims; as
required
JF, CRG
Facilities Review: Schedule, Kaestle Boos
JF/SBC; DC/see above.
HS & TOW Roof Replacement:/discussion
a) HS Construction Review: Update /
Skylight JF/Chairman; SBC; CRG
b) TOW Town Hall; Phase I, HBF; Existing
Condition Plans, Field Survey JF/Chairman; SBC; TL
O&G Schedule / Progress: /getting down to
last bits
a) Final Project Cost
Report RM/O&G
b) HS:
i) Close-out status; see updated listing;
MB-RM/O&G; JF
ii) Site; Richards, Grading, As-Built
Drawings, Fire Tank Access CRG
c) 3-5 School: Close-out status; see updated listing;
MB-MS/O&G; JF
d) MFP: Close-out status; Sentrale, Shawn’s Lawns
RM/O&G
e) Zenon Plant: Close out status; Merritt RM &
MS/O&G
f) Hurlbutt: Close-out status, Shawn’s
Lawns RM/O&G
Revson Field DG / DC/ REVIEW AND
PREPARATION TO SUPPORT PROPOSAL FOR REPAIR ALREADY APPROVED BY
COMMITTEE AND SENT BACK BY SELECTMEN
Review hiring
an MEP consultant for a HS photovoltaic
system DG / SBC
New Business as may properly come before the SBC
meeting: All/discussion about regulation lighting to
conserve energy
Change Orders & Invoice Approval:
a) HS: Proposed Change Orders, if
any O&G/RM, CRG
b) HS: Applications For Payment, if
any O&G/RM, CRG
c) 3-5 School: Proposed Change Orders, if
any O&G/MS, CRG
d) 3-5 School: Applications For Payment,
if any O&G/MS, CRG
e) Invoices: Other Invoices for submission
to the SBC, if any CRG
Next Meeting(s): October 3, 2007 @ 7:30 PM, TOW, Town Hall,
Commission Rm. All
Adjournment: Meeting adjourned @ _____:_____ PM
JF/Chairman
Building Committee/School
Building Committee, Wednesday, September 5,
2007, 7:30pm, Town Hall Meeting Room
AGENDA/present: Fitzpatrick, Coprio, Gary, Wolf (quorum);
Martin Strasmore
1) Approve Minutes of Previous meetings:
8/22/07/done
2) Executive Session/vote after Exec. Session to
approves IES and TPC conditionally
a) Contracts – HS Auditorium
b) Claims; as required
3) Facilities Review: Schedule, Kaestle
Boos/move it ahead rapidly
4) HS & TOW Roof Replacement:
a) HS Construction Review: Progress update: Resolution of clogged roof drain at girls locker room/fixed!
b) TOW Town Hall; Phase I; Plans for
HBF/discussion
5) O&G Schedule / Progress: almost all
done!
a) Final Project Cost Report
b) HS:
i) Close-out status; see updated listing;
ii) Site Drainage, Richards
c) 3-5 School: Close-out status; see updated listing;
d) MFP: Close-out status; Sentrale, Shawn’s Lawns
e) Zenon Plant:
i) Close out status; Merritt
f) Hurlbutt: Close-out status, Shawn’s
Lawns
6) Alternative Power Study/presentation to
Selectmen reported, progress report.
7) Revson Field/recommendation to Selectmen for
reconditioning of out and infields over two years or so without taking
Revson 2 fields(sharted outfield) out of service - to go to Selectmen
and then Board of Finance;
8) New Business as may properly come before the SBC
meeting:
a) Middle School Windows Replacement
(BC/BOE)
b) Dugouts for Little League; review &
comments of info distributed 8/22/07/long discussion and detailed.
9) Change Orders & Invoice Approval:
a) HS: Proposed Change Orders, if any
b) HS: Applications For Payment, if any
c) 3-5 School: Proposed Change Orders, if
any
d) 3-5 School: Applications For Payment,
if any
e) Invoices: Other Invoices for submission
to the SBC, if any
10) Next Meeting(s): To Be
Determined/approx. in 2 weeks.
Weston
Building and School Building Committee, Wednesday, August 22, 2007,
7:30pm, Commission Room at Town Hall
1. H.S. Auditorium Renovation:
- Architect/Engineer Interviews/done
- TPC Contract updates/nothing new
2. Executive Session as required (put at end of agenda)
3. Minutes/OK
4. FACILITIES REVIEW SCHEDULE/to be starting soon to be complete
in time for budget process 2008-2009.
5. H.S. and TOW Roof Replacement:
- H.S. Construction Review; progress update (resolution of
clogged roof drain in girls' locker room)/will get to it before school
starts (next week)
- TOW Town Hall - Phase One - plans for H.B. Fishman/???
6. O&G Schedule/Progress: LAST PAPERWORK ALMOST DONE!!!
- HS Consolidated punch list update status
- 3-4-5
- MFP
- Zenon Plant
- Hurlbutt
7. New business: Revson Field proposal by
Milone&MacBroom discussed (not circulated to public, but discussion
of time out of use and no fields, just study, at the end of lengthy
period ($40,000 as well) led some members to investigate other
options; more in two weeks. WE LEFT AS EXECUTIVE SESSION called.
8. Change orders
9. NEXT MEETING: September 5
ATTENTION:
e-mail received mid-day Monday that a quorum would not be available on
Aug.1--this meeting to be rescheduled for Aug. 8
RE-SCHEDULED FOR AUGUST 8, POSTED
IN TOWN CLERK'S OFFICE
Weston
Building and School Building Committee, Wednesday, August 1 - now the 8th - 2007,
7:30pm, Commission Room at Town Hall
1. Executive Session:claims (as required)
2. Minutes/OK
3. High School Auditorium Renovation:
- TPC Contract and Schedule (TPC Gene Leitermann)/next
meeting (Town Att'y comments needed)
- Architure/Engineer RFP/interview next meeting
4. Facilities Review - no schedule presented--next time?
5. High School and Town Roof Replacement:
- HS construction review - progress update; Water pooling
C.O./working some problems out, stuck drains...
- Town Hall Roof proposal signed; Phase 1/architect wants
plans for original section, also to see if the addition meets code - see photo above
6. O&G Schedule/progress:
- HS consolodated punch list/close out status/?
- 3-4-5 school close out status (see updated listing)/pretty
much done
- Morehouse Farm Park ("MFP") - close out status, Sentrale,
Shawn's Lawns/still not ready to be closed out
- Zenon Plant - close out status, Merritt/another flood (2
toilets kept running all weekend at the Middle School)
- Hurlbutt - Close out status, Shawn's Lawns/?
7. New business/photovoltaic cells
grant proposal suggested for total high school roof--sell back energy
to the grid in summer!
8. Change orders/we left
NEXT MEETING in 3 weeks (August 22,
2007) @ 7:30pm
Weston
Building and School Building Committee, Wednesday, July 11, 2007,
7:30pm, Commission Room at Town Hall
1. Executive Session - claims,
as required/placed at the foot of the agenda, if necessary.
2. Approve minutes/done
3. H.S. Auditorium Renovation:
- Theater project consultants proposal and schedule/vote to
retain TPC
- Architectgure/Engineer RFP/more discussion
4. High School and Town of Weston Roof Replacement:
- H.S. Construction Review: progress,
update/excellent progress, some details and minor problems.
- TOW Roof Proposal signed, Phase One, coordination/need more
5. O&G schedule - close out status:
- H.S. Punch List/small stuff
- 3-5 school/stuff
- Morehouse Farm Park/?
- Zenon Plant/going OK
- Hurlbutt/?
6. New Business/lighting coordination needed
7. Change Orders and invoive approval/we left before this took
place
8. NEXT MEETING: Wednesday, August 1, 2007, 7:30pm
WESTON
SCHOOL BUILDING COMMITTEE, Wednesday, June 27, 2007, 6:30pm, Commission Room, Town
Hall
1) Call Meeting to
Order - quorum present
2) Executive Session: Special Meeting with Board of
Selectman / Cohen & Wolf; 6:30 PM - Claim; Settlements; Comments;
as required/done in somewhat more than an hour.
3) Approve Minutes of Previous meetings: Approve of
Meeting Minutes of 5/23/07 & 6/6/07/done
4) HS Auditorium Renovation:
a) Theater Projects Consultants Proposal
& Schedule; (TPC-Gene Leitermann)/rec'd Monday - consideraion at
next meeting - not enough time for detailed review
b) Architecture / Engineer RFP/next meeting
5) HS & TOW Roof Replacement: -
discussion of progress to date (to begin hot patch again on roof)
a) HS Construction Review: Progress
update;
b) TOW Roof Proposal Signed; Phase I;
Coordination/brief discussion
6) O&G Schedule / Progress:
a) HS Consolidated Punch List Update /
Status:
i) Punch List status; see consolidated
list; HS Dumpster Fence (Total Fence)
ii) Close-out status; see updated listing;
O&G response to JF
b) 3-5 School: Close-out status; see listing,
c) MFP:
i) Shawn’s Lawns tree planting status
ii) Close-out status; Sentrale, Shawn’s
Lawns
d) Zenon Plant: fixed!
i) Water flow & Maintenance /
Operation update; pipe HS south clean-out
ii) Close out status; Merritt
e) Hurlbutt: Close-out status, Shawn’s
Lawns
7) New Business as may properly come
before the SBC meeting:
8) Change Orders & Invoice Approval:
a) HS: Proposed Change Orders, if any
b) HS: Applications For Payment, if any
c) 3-5 School: Proposed Change Orders, if
any
d) 3-5 School: Applications For Payment,
if any
e) Invoices: Other Invoices for submission
to the SBC, if any
9) Next Meeting(s): Wednesday
07/11/07 @ 7:30 PM
WESTON
SCHOOL BUILDING COMMITTEE, Wednesday, June 6, 2007, 7:30pm,
Commission Room, Town Hall
1) Approve Minutes of Previous meetings:
Approve of Meeting Minutes of 5/23/07
2) HS Auditorium Renovation: Discussion
with Theater Projects Consultants; Gene Leitermann/discussion, in
two weeks (next meeting) there will be a proposal with details;
time schedule previously discussed (for work to be done next
summer--which working backward means out to bid in winter-spring, we
think we heard...)
3) HS & TOW Roof Replacement:
a) HS Construction Review: Progress
update/ahead of schedule and under budget
b) TOW Roof Proposal/next step is up to
Selectmen
4) O&G Schedule / Progress:
a) HS Consolidated Punch List Update /
Status:/done
i) Punch List status; see consolidated
list; HS Dumpster Fence (Total Fence)
ii) Close-out status; see updated listing;
O&G response to JF
b) 3-5 School: Close-out status; see listing,/done
c) MFP:/done
i) Shawn’s Lawns tree planting status
ii) Close-out status; Sentrale, Shawn’s
Lawns
d) Zenon Plant:
i) Water flow & Maintenance /
Operation update; pipe HS south clean-out/done
ii) Close out status; Merritt/?
e) Hurlbutt: Close-out status, Shawn’s
Lawns/?
5) New Business as may properly come
before the SBC meeting:
6) Executive Session: Claim; Settlements; Comments;
as required/we left
7) Change Orders & Invoice Approval:
a) HS: Proposed Change Orders, if any
b) HS: Applications For Payment, if any
c) 3-5 School: Proposed Change Orders, if
any
d) 3-5 School: Applications For Payment,
if any
e) Invoices: Other Invoices for submission
to the SBC, if any
8) Next Meeting(s): Wednesday
06/20/07 @ 7:30 PM
9) Adjournment: Meeting adjourned @ _____:_____ PM
WESTON
SCHOOL/BUILDING COMMITTEE, Wednesday, May 23, 2007, 7:30pm,
Commission Room, Town Hall
- Approval of minutes, future meeting schedule/quorum
present; see below -
two weeks from now; minutes approved.
- Roof replacements: High School and Town of
Weston/drawing showing exactly what is done, is being done, and what is
held for time when school is out. Updated DAILY
- HS Auditorium - theatreconsultant and architects'
contracts/discussion, meeting scheduled (see below)
- O&G - close-outs on 5 projects including tertiary
treatment ("wastewater flow and maintenance/pipe high school south
clean-out)/guck in pipes - where did it come from?
- Executive Session: claims, settlements, as
required/not
- NEXT
meeting Wednesday, June 6/will
entertain presentation and ask
questions of Theatre design specialty consultant.
WESTON
SCHOOL BUILDING COMMITTEE, Wednesday, May 9, 2007, 7:30pm,
Commission Room, Town Hall
- Approval of minutes/done.
- Next is "HS Roof Replacement"
construction schedule and progress update/work continuing after brief
stoppage, new methods an techniques to be employed to assure no
disruption of teaching and learning as the leaky old roof gives way to
a brand new one..
- "HS Auditorium" Theatre
Consultant Contract; Architect Contract/to go out before next
meeting.
- O&G Schedule/Progress - HS punch-list, close-out
status; 3-5 close-put status/still some things that need to be
addressed, incuding methods and procedures for operating facilities
connected to new systems.
- Executive Session: Claim Settlements, Comments, as
required/we left at this point.
- Change Orders and Invoices;
Next meeting, May 23.
WESTON
SCHOOL BUILDING COMMITTEE, Wednesday, April 25, 2007, 7:30pm,
Commission Room, Town Hall
1)
Attendance: quorum present
2) Call Meeting to Order: Meeting called to
order/done
3) Approve Minutes of Previous meetings: Approval of
Meeting Minutes of 4/11/07.done
4) HS Roof Replacement: Construction start and
progress update/started Thursday instead of the previous week - going
well and on schedule (not working Sundays but working longer the rest
of the days to make up for late start.
5) HS Auditorium: Next step discussion/RFP to be
developed for theatre consultant for rehab design and then architect to
make the rehab design work.
6) O&G Schedule / Progress:
a) HS Consolidated Punch List Update /
Status: OK
i) Punch List status; see consolidated list
ii) Close-out status; see updated listing
from O&G
b) 3-5 School: Close-out status; see listing, going well
c) MFP:
i) Shawn’s Lawns tree planting status/?
ii) Close-out status; Sentrale, Shawn’s
Lawns/?
d) Zenon Plant:
i) Water flow & Maintenance/Operation
update/did well during storm, timers needed for monitoring
ii) Close out status; Merritt/?
e) Hurlbutt: Close-out status, Shawn’s
Lawns/?
7) New Business as may properly come
before the SBC meeting:
8) Executive Session: Claim; Settlements; Comments;
as required
9) Change Orders & Invoice Approval:
a) HS: Proposed Change Orders, if any
b) HS: Applications For Payment, if any
c) 3-5 School: Proposed Change Orders, if
any
d) 3-5 School: Applications For Payment,
if any
e) Invoices: Other Invoices for submission
to the SBC, if any
10) Next Meeting(s): Wednesday
5/08/07 @ 7:30 PM
WESTON
BUILDING AND SCHOOL BUILDING COMMITTEE, Wednesday, April 25, 2007,
7:30pm,
Commission Room, Town Hall
AGENDA
1) Approve Minutes of Previous meetings: Approval of
Meeting Minutes of 3/21/07 & 3/28/07/done.
2) Facilities Discussion: Facilities RFP interview of
Kaestle Boos/discussion of which facilities need more work than others.
3) Green/Sustainability Study: Discussion with Steven
Winter Assoc./discussion begins about this issue as far as Town of
Weston is concerned--overall view-study first and than exploration of
special features of Weston's centrality as it would serve to make
Weston a likely candidate for a successful sustainibility
program. In particular, pool at W.M.S. a prospect for some
investigation. Energy Audit. Photovoltaic. Solar.
4) HS Roof Replacement:
a) Contract start & update, 4/14/07 -
getting started this weekend.
i) TOW location to deposit roof ballast or
possible sale/working on it.
5) HS Auditorium: Next step discussion -
Arts faculty input, timing of when LEAST disruption to arts program
would be made.
6) O&G Schedule / Progress:
a) HS Consolidated Punch List Update /
Status:
i) Punch List status; see consolidated list
ii) Close-out status; see updated listing
from O&G
iii) MEP Commissioning Contract; Kohler
Ronan, LLC
b) 3-5 School - Close-out status; see listing,
c) MFP:
i) Shawn’s Lawns tree planting status
ii) Close-out status; Sentrale, Shawn’s
Lawns
d) Zenon Plant:
i) Water flow & Maintenance/Operation
update - next meeting.
ii) Close out status; Merritt
e) Hurlbutt: Close-out status, Shawn’s
Lawns
7) New Business as may properly come
before the SBC meeting:
8) Executive Session: Claim; Settlements; Comments;
required - we left.
9) Change Orders & Invoice Approval:
a) HS: Proposed Change Orders, if any
b) HS: Applications For Payment, if any
c) 3-5 School: Proposed Change Orders, if
any
d) 3-5 School: Applications For Payment,
if any
e) Invoices: Other Invoices for submission
to the SBC, if any
10) Next Meeting(s): Wednesday4/25/07 @ 7:30 PM
WESTON
SCHOOL BUILDING COMMITTEE, Wednesday, March 28, 2007, 7:30pm,
Commission Room, Town Hall
Agenda posted Wednesday
afternoon-but note that this special meeting would take place was noted
on the Town
Clerk's Calendar as well as
on the Appointed
Committees agenda board
(behind the door); elected Commissions and Boards
agendae appear on the bulletin board next to the Town Clerk's desk.
1. In attendance was a quorum of
the Building Committee plus School Building Committee members as
well. Director of Facilities for Board of Ed was present.
The high school roof project contract will be signed this week and work
will commence - Spring Vacation is the time the "ballast" on top of the
room is to be removed--it was suggested that the roof contractor might
be asked to arrange for disposition of the stones and adjust contract
accordingly.
2. RFP on buildings' condition evaluation and resulting
interviews of 3 firms took place. It was decided by the Building
Committee that one firm was best suited for this job, and the Chair. is
directed to contact that firm and discuss the assignment (we do not
identify which firm on the Internet).
3. Review of work still to be completed, problems still
identified.
4. Executive Session: Claims, settlements.
NEXT MEETING IN ONE WEEK (March 28,
7:30pm) - meetings will be rescheduled at a rate of once every two
weeks beginning March 28.
WESTON
SCHOOL BUILDING COMMITTEE, Wednesday, March 21, 2007, 7:30pm,
Commission Room, Town Hall
Part A - TOW / BUILDING COMMITTEE AGENDA
1) Attendance: quorum present
2) Call Meeting to Order: Meeting called to
order
3) HS Roof Replacement:
a) H. B. Fishman & Co.; Board of
Selectman roof status/Special Town Meeting 3-22-07 at 8pm
i) HBF Construction Administration
Contract continued discussion
ii) Environmental
contract
iii) TOW location to deposit roof
ballast/lots to dispose of
iv) Roof construction sequence; auditorium
roof work/first
v) Contract details, start date &
possible “Letter of Intent”, start date 4/14-16/07 if
possible/if it passes
4) TOW, Town Hall Roof: Plan for roof
repair and/or replacement/ATBM Capital Item
5) Facilities RFP Discussion: WE LEFT
MID-DISCUSSION
Part B - TOW / SCHOOL BUILDING COMMITTEE AGENDA
1) Approve Minutes of Previous meetings: Approval of
Meeting Minutes of 1/24/07, 2/07/07, 2/21/07 &
3/7/07/done
2) O&G Schedule / Progress:
a) HS Consolidated Punch List Update /
Status:
i) Punch List status; see consolidated
list RM/O&G
ii) Close-out status; see updated listing
from O&G RM/O&G
iii) MEP Commissioning Proposal; Kohler
Ronan, LLC JF/SBC Chairman
b) 3-5 School - Close-out status; see listing, MS/O&G;
CRG; SBC
c) MFP:
i) Shawn’s Lawns tree planting
status RM/O&G
ii) Close-out status; Sentrale, Shawn’s
Lawns RM/O&G
d) Zenon Plant: still working to find leak
or overflow of rainwater
i) Water flow & Maintenance/Operation
update SF / CRG / CT Water / BOE
ii) Close out status;
Merritt RM & MS/O&G
e) Hurlbutt: Close-out status, Shawn’s
Lawns RM/O&G
3) New Business as may properly come
before the SBC meeting: All
4) Executive Session: Claim;
Settlements; Comments; as required SBC
5) Change Orders & Invoice
Approval:
a) HS: Review of Proposed Change Orders,
if any O&G/RM, CRG
b) HS: Applications For Payment, if
any O&G/RM, CRG
c) 3-5 School: Review of Proposed Change
Orders, if any O&G/MS, CRG
d) 3-5 School: Applications For Payment,
if any O&G/MS, CRG
e) Invoices: Other Invoices for submission
to the SBC, if any CRG
6) Next Meeting(s): Wednesday
4/04/07 @ 7:30 PM All
7) Adjournment: Meeting adjourned @ ________
PM RW/SBC Vice Chairmen
WESTON
SCHOOL BUILDING COMMITTEE, Wednesday, March 7, 2007, 7:30pm,
Commission Room, Town Hall - No
quorum. Discussion about many of the items on the agenda,
including 2a.
1) Call Meeting to Order: Meeting called
to order
2) HS Roof Replacement:
a) H. B. Fishman & Co.; Contractor recommendation
to Board of Selectman BC; KW; DC/BOE; CRG
i) Executive Session if required to select
contractor
ii) HBF Construction Administration
Contract BC
3) Facilities RFP
Discussion: JF/BC, Chairman
Part B - TOW / SCHOOL BUILDING COMMITTEE AGENDA
1) Approve Minutes of Previous
meetings:
a) Approval of Meeting Minutes of
1/24/07 BC/SBC
b) Approval of Meeting Minutes of
2/07/07 BC/SBC
c) Approval of Meeting Minutes of
2/21/07 BC/SBC
2) O&G Schedule /
Progress:
a) HS Consolidated Punch List Update /
Status:
i) Punch List status; see consolidated
list RM/O&G
ii) Close-out status; see updated listing
from O&G RM/O&G
iii) MEP Commissioning Proposal; Kohler
Ronan, LLC JF/SBC Chairman
b) 3-5 School - Close-out status; see listing,
MS/O&G; CRG; SBC
c) MFP:
i) Shawn’s Lawns tree planting
status RM/O&G
ii) Close-out status; Sentrale, Shawn’s
Lawns RM/O&G
d) Zenon Plant: Close out status;
Merritt RM & MS/O&G - Water flow & Maintenance/Operation
update SF / CRG / CT Water / BOE
e) Hurlbutt: Close-out status, Shawn’s
Lawns RM/O&G
3) New Business as may properly come
before the SBC meeting: All
4) Executive Session: Claim; Settlements; Comments;
as required SBC
5) Change Orders & Invoice
Approval:
a) HS: Review of Proposed Change Orders,
if any O&G/RM, CRG
b) HS: Applications For Payment, if
any O&G/RM, CRG
c) 3-5 School: Review of Proposed Change
Orders, if any O&G/MS, CRG
d) 3-5 School: Applications For Payment,
if any O&G/MS, CRG
e) Invoices: Other Invoices for submission
to the SBC, if any CRG
6) Next Meeting(s): Wednesday
3/21/07 @ 7:30 PM All
7) Adjournment: Meeting adjourned @ ________
PM RW/SBC Vice Chairmen
WESTON
SCHOOL BUILDING COMMITTEE, Wednesday, February 21, 2007, 7:30pm,
Commission Room, Town Hall - No quorum
Part
A - TOW / BUILDING COMMITTEE AGENDA
1. Call Meeting to Order: Meeting called to
order RW/BC, Vice Chairman
2.
Attendance:
3) Facilities RFP
Discussion: RW/BC, Vice Chairman
4) HS Roof Replacement:
a) H. B. Fishman & Co.; continued
discussion re: Schedule / Financing & Bid Review
BC; DC/BOE; CRG
i) HBF Construction Administration
Contract BC
Part B - TOW / SCHOOL BUILDING
COMMITTEE AGENDA
1) Approve Minutes of Previous
meetings:
a) Approval of Meeting Minutes of
1/24/07 SBC
b) Approval of Meeting Minutes of
2/07/07 SBC
2) O&G Schedule /
Progress:
a) HS Consolidated Punch List Update /
Status:
i) Punch List status; see consolidated
list RM/O&G
ii) Close-out status; see updated listing
from O&G RM/O&G
iii) MEP Commissioning Proposal; Kohler
Ronan, LLC RW/SBC Vice Chairman
b) 3-5 School
i) Close-out status; see
listing, CRG/MS; SBC
ii) Display Cases, information sent to A.
Swerdlowe AS/BOE
c) MFP:
i) Shawn’s Lawns tree planting
status RM/O&G
ii) Close-out status; Sentrale, Shawn’s
Lawns RM/O&G
d) Zenon Plant: i) Water flow update SF
/ CRG / CT Water / BOE
Close out status;
Merritt RM & MS/O&G
e) Hurlbutt: Close-out status, Shawn’s
Lawns RM/O&G
3) New Business as may properly come
before the SBC meeting: All
4) Executive Session: a) Claim;
Settlements; Comments; as required SBC
5) Change Orders & Invoice
Approval:
a) HS: Review of Proposed Change Orders,
if any O&G/RM, CRG
b) HS: Applications For Payment, if
any O&G/RM, CRG
c) 3-5 School: Review of Proposed Change
Orders, if any O&G/MS, CRG
d) 3-5 School: Applications For Payment,
if any O&G/MS, CRG
e) Invoices: Other Invoices for submission
to the SBC, if any CRG
6) Next Meeting(s): Wednesday 3/7/07
@ 7:30 PM All
7) Adjournment: Meeting adjourned @ ________
PM RW/SBC Vice Chairmen
SPECIAL
WESTON
SCHOOL BUILDING COMMITTEE/BUILDING COMMITTEE, Wednesday, February 7,
2007, 5:30pm,
Commission Room, Town Hall
Part A - TOW / BUILDING COMMITTEE AGENDA / Cap. Assessment
(Advisory???)
Comm. – 5:30 PM
1) Attendance:
2) Call Meeting to Order: Meeting called to order
@
3) Interviews for RFP: no action recommendation
on baseline study of town and school building conditions - hint: Town Hall needs work.
a) Kaestle Boos Associates
Inc. 45 Min Presentation; 5:45–6:30 PM
b) The SLAM
Collaborative 45 Min Presentation; 6:30-7:15 PM
c) Savin Engineers P.C.
45 Min Presentation; 7:15-8:00 PM
Part B - TOW / SCHOOL BUILDING COMMITTEE AGENDA – 8:00 PM
1) Approve Minutes of Previous meetings: Approval of
Meeting Minutes of 1/24/07/done
2) Change Orders & Invoice
Approval:
a) HS: Review of Proposed Change Orders,
if any O&G/RM, CRG
b) HS: Applications For Payment, if
any O&G/RM, CRG
c) 3-5 School: Review of Proposed Change
Orders, if any O&G/MS, CRG
d) 3-5 School: Applications For Payment,
if any O&G/MS, CRG
e) Invoices: Other Invoices for submission
to the SBC, if any CRG
Part C - TOW / BUILDING COMMITTEE
1) Next Meeting(s): Wednesday 02/21/07 @ 7:30
PM THE AGENDA - WILL IT CONTAIN AN ITEM CALLING
FOR ACTION ON THE STUDY? THE ROOF? WHEN WILL THE INTERVIEW
GROUP ANNOUNCE THEIR CHOICE? WILL IT BE MADE AT THE NEXT BUILDING
COMMITTEE MEETING?
2) Adjournment: Meeting adjourned @ ________
PM JF/BC Chairman
WESTON
SCHOOL BUILDING COMMITTEE, Wednesday, January 24, 2007, 7:30pm,
Commission Room, Town Hall
Part A -
TOW / SCHOOL BUILDING COMMITTEE AGENDA
1) Attendance: quorum present
2) Call Meeting to Order: Meeting called to order
3) Approve Minutes of Previous meetings - done
4) O&G Schedule / Progress: done - some
items still outstanding, some new ideas for completion of some
a) HS Consolidated Punch List Update /
Status:
i) Punch List status; see consolidated
list RM/O&G
ii) Close-out status; see updated listing
from O&G RM/O&G
iii) Cablevision RF extension
approval CRG, CBC
b) 3-5 School
i) Close-out status; see listing, Drywall
Associates; Losito CRG/MS; SBC
ii) 3-5 School MEP Commissioning
report CRG & DC/BOE
iii) Display Cases, FT
Request AS/BOE
c) MS / Site / Tennis Courts: i) Designing Nature planting update; tree
move @ HS sign area SBC / CRG
d) MFP:
i) Shawn’s Lawns tree planting
status RM/O&G
ii) Close-out status; Sentrale, Shawn’s
Lawns RM/O&G
e) Zenon Plant: Close out status; Merritt,
James T. Kay RM & MS/O&G
f) Hurlbutt: Close-out status, Shawn’s
Lawns RM/O&G
5) New Business as may properly come
before the SBC meeting: ?
6) Executive Session:
a) Claim; Settlements; Comments; as required
- none
7) Change Orders & Invoice
Approval: done
a) HS: Review of Proposed Change Orders,
if any O&G/RM, CRG
b) HS: Applications For Payment, if
any O&G/RM, CRG
c) 3-5 School: Review of Proposed Change
Orders, if any O&G/MS, CRG
d) 3-5 School: Applications For Payment,
if any O&G/MS, CRG
e) Invoices: Other Invoices for submission
to the SBC, if any CRG
Part B - TOW / BUILDING COMMITTEE
AGENDA
1) HS Roof Replacement: nothing final yet -
seek to narrow start-finish time so as not to work while school is in
session
a) H. B. Fishman & Co.; continued
discussion re: Schedule / Financing & Bid Review
BC; DC/BOE; CRG
i) HBF Construction Administration
Contract BC
2) Next Meeting(s): Wednesday
02/07/07 - roofing contractors selected by Fishman to be interview @
5:30 PM; next SBC/BC meeting at @7:30pm All
3) Adjournment: Meeting adjourned @ ________
PM JF/BC Chairman
WESTON
SCHOOL BUILDING COMMITTEE, Wednesday, January 10, 2007, 7:30pm,
Commission Room, Town Hall
AGENDA (NO ELECTION OF OFFICERS while we were in attendance [7:30pm -
9:30pm])
1) Attendance: Quorum present
2) Call Meeting to Order: Meeting called to
order
3) HS Roof; Building Committee - Review of HS
Roof submittal by HBF with Kim Winchell, HBF & Matt Myers,
EnviroScience/no numbers mentioned.
4) O&G Schedule / Progress: SBC
- almost done on punch list, but disturbing note: claims being
submitted anew for items thought to be over and done!
a) HS Consolidated Punch List Update /
Status:
i) Punch List status; see consolidated
list
ii) Close-out status; see updated listing
from O&G
iii) Additional Computers for 2 Health
Classrooms; E04 & E10
b) 3-5 School
i) Punch List status; see
listing MS / O&G
ii) Close-out status; see
listing CRG / MS / SBC
iii) 3-5 School MEP Commissioning in
progress
iv) Display
cases
c) MS / Site / Tennis Courts: - Designing Nature planting update; tree move @ HS
sign area
d) MFP:
i) Tree planting status
ii) Close-out status; Sentrale, Shawn’s
Lawns
e) Zenon Plant: Close out status; Merritt,
James T. Kay
f) Hurlbutt: Close-out status, Shawn’s
Lawns RM / O&G
5) Approve Minutes of Previous
meetings: - Approval of Meeting Minutes of 11/29/06,
12/13/06 - we didn't hear them do this
6) New Business as may properly come before the SBC
meeting: l
7) Executive Session: none while we were present
a) Claim; Settlements; Comments; as
required
b) Matters pertaining to Litigation
8) Change Orders & Invoice
Approval: same as above
a) HS: Review of Proposed Change Orders,
if any O&G/RM, CRG
b) HS: Applications For Payment, if
any O&G/RM, CRG
c) 3-5 School: Review of Proposed Change
Orders, if any O&G/MS, CRG
d) 3-5 School: Applications For Payment,
if any O&G/MS, CRG
e) Invoices: Other Invoices for submission
to the SBC, if any CRG
9) Next Meeting(s): Wednesday
01/24/07 @ 7:30 PM
10) Adjournment:
Part B - TOW / BUILDING COMMITTEE AGENDA
1) HS Roof Replacement: see above # 3 - H. B.
Fishman & Co.; Schedule / financing / bid review
2) Information for Future
Consideration
a) Proposals for Facilities
Assessment - three (3) companies responded to RFP; Building
Committee to review
b) HS Auditorium Program & Schematic
Budget Estimate - we left prior to this item - however, the WestonArts
reps were present to witness this.
3) Adjournment:
WESTON SCHOOL BUILDING COMMITTEE,
Wednesday, December 13, 2006, 7:30pm,
Commission Room, Town Hall
1) Call Meeting to Order: NO QUORUM
2) O&G Schedule / Progress: SBC
a) HS Consolidated Punch List Update /
Status:
i) Punch List Review; see consolidated
list RM / O&G
ii) Close-out status; see updated listing
from O&G RM / O&G
b) 3-5 School
i) Close-out status; Drywall Assoc.,
Losito (payment & claim), NE Interiors, Pipe & Power; Pro.
Painting MS / O&G
ii) Final Payment: Merritt; Schenectady
Steel; Walker Products; APG; Cent. Conn. Acoustics; BKM
Flooring CRG / MS / SBC
iii) 3-5 School MEP Commissioning in
progress CRG & DC / BOE
c) MS / Site / Tennis Courts: Designing Nature planting update, tree move @ HS sign
area SBC / CRG
d) MFP: RM / O&G
i) Tree planting status
ii) Close-out status; Sentrale, Shawn’s
Lawns; O&G updated listing RM / O&G
e) Zenon Plant: Close out status; Merritt,
James T. Kay RM & MS / O&G
f) Hurlbutt: Close-out, Shawn’s Lawns
RM / O&G
3) School Building Committee: Election of
Officers, Schedule Meetings for 2007 SBC
4) Approve Minutes of Previous meetings - Approval of
Meeting Minutes of 11/29/06 SBC
5) New Business as may properly come before the SBC
meeting: All
6) Executive Session: Claim reviews,
settlements; as required SBC
7) Change Orders & Invoice
Approval:
a) HS: Review of Proposed Change Orders,
if any O&G/RM, CRG
b) HS: Applications For Payment, if
any O&G/RM, CRG
c) 3-5 School: Review of Proposed Change
Orders, if any O&G/MS, CRG
d) 3-5 School: Applications For Payment,
if any O&G/MS, CRG
e) Invoices: Other Invoices for submission
to the SBC, if any CRG
8) Next Meeting(s): Wednesday
01/10/07 @ 7:30 PM All
9) Adjournment: Meeting
Part B - TOW / BUILDING COMMITTEE AGENDA
1) HS Roof Replacement:
a) H. B. Fishman & Co.; Schedule / financing /
bid review CRG; SBC; DC / BOE
WESTON SCHOOL BUILDING COMMITTEE,
Wednesday, November 29, 2006, 7:30pm,
Commission Room, Town Hall
AGENDA
1) O&G Schedule / Progress:
SBC/review and most things to be finished in 2 weeks.
a)
HS Consolidated Punch List Update / Status:
i)
Punch List Review; see consolidated list RM / O&G
ii)
Storm water cross connection test report of 11/7/06 from
NEPCCO CRG, DC / BOE
iii)
Close-out status; see updated listing from O&G RM
/ O&G
b)
3-5 School/"
i)
Close-out status; Drywall Assoc., Losito, NE Interiors, Merritt, Pipe
& Power; Pro. Painting; Schenectady Steel; see updated O&G
listing MS / O&G
ii)
3-5 School MEP Commissioning: Schedule CRG & DC /
BOE
c)
MS / Site / Tennis Courts: ?
i)
Designing Nature planting update & SBC site walk of
11/25 SBC / CRG/trees total 119, some to be relocated
ii)
Wetland Report Status RM / O&G/Army Corps to get
full set of completed drawings (as-built?) of mitigation, etc.
d)
MFP: Tree planting status; RM / O&G - Close-out
status; Sentrale, Shawn’s Lawns; O&G updated
listing RM / O&G
e)
Zenon Plant: Close out
status; Merritt, James T. Kay; O&G updated
listing RM & MS / O&G/looking good
f)
Hurlbutt: Close-out, Shawn’s Lawns; O&G updated listing;
RM / O&G/OK as far as work to be done for
Referendum is concerned
2)
Revson Field Report: Selectman’s comments to letter of 11/16
meeting TL / SBC/nothing in writing
3) Approve Minutes of Previous meetings: Approval of
Meeting Minutes of 11/15/06 SBC/done
4) New Business as may properly come before the SBC
meeting: All/?
5) Executive Session: Claim reviews,
settlements; FT, others if any SBC/?
6) Change Orders & Invoice
Approval: ?
a)
HS: Review of Proposed Change Orders, if any
O&G/RM, CRG
b)
HS: Applications For Payment, if any O&G/RM, CRG
c)
3-5 School: Review of Proposed Change Orders, if any
O&G/MS, CRG
d)
3-5 School: Applications For Payment, if any
O&G/MS, CRG
e)
Invoices: Other Invoices for submission to the SBC, if
any CRG
7)
Next Meeting(s): Wednesday 12/13/06 @ 7:30 PM
All
8) Adjournment: Meeting adjourned @ ________
PM RW, Chairman
Part B - TOW / BUILDING COMMITTEE AGENDA
1) HS Roof Replacement: H. B. Fishman &
Co.; Schedule for HS CRG; SBC; DC / BOE/this and
capital projects advisory discussed
WESTON SCHOOL BUILDING COMMITTEE, Wednesday, November 15, 2006, 7:30pm,
Commission Room, Town Hall
1) O&G Schedule /
Progress: SBC
a) HS Consolidated Punch List Update /
Status:
i) Punch List Review; see consolidated
list/review of outstanding items
ii) Storm water cross connection test
report of 11/7/06/looks like groundwater problem, based upon early
November tests
iii) Close-out status; see listing/several
items still need to be completed
b) 3-5 School
i)
Close-out status; Drywall Assoc., Losito, NE Interiors, Merritt, Pipe
& Power; Pro. Painting; Schenectady Steel/what will it take to get
last bits done?
ii) School water pressure/some new ideas
iii) 3-5 School MEP Commissioning:
Schedule/no report
c) MS / Site / Tennis Courts: Site walk-thru
November 25 at 10am - meet at the 3-5 entrance
i) Close-out status; Richards, THP/to be
determined
ii) Designing Nature planting
update/looking good
iii) Wetland Report Status/ see "site
walk" above - O&G pointed out the differences between several
engineering reports.
d) MFP: Tree planting status/?
i) Close-out status;
Sentrale, Shawn’s Lawns/?
e) Zenon Plant: Fire pump use, WFD wants
to draw water, not in design/after discussion with Town Engineer, it
appears a good idea (our interpretation)
i) Close out status; Merritt, James T.
Kay/?
f) Hurlbutt: Close-out, Shawn’s Lawns/?
2) Revson Field Report: Selectman’s
comments to letter of 11/7 if any/no one present was able to make the
next Board of Selectmen's meeting.
3) Approve Minutes of Previous meetings:
a) Approval of Meeting Minutes of 10/4/06, notes of
10/18/06 & 11/1/06/OK - those w/o quorum no approved (no action
taken, anyway)
4) New Business as may properly come before the SBC
meeting/none
5) Executive Session: a) Claim
reviews, settlements; FT, others if any/no action
6) Change Orders & Invoice Approval: discussed in
previous sections of minutes
a) HS: Review of Proposed Change Orders,
if any O&G/RM, CRG
b) HS: Applications For Payment, if
any O&G/RM, CRG
c) 3-5 School: Review of Proposed Change
Orders, if any O&G/MS, CRG
d) 3-5 School: Applications For Payment,
if any O&G/MS, CRG
e) Invoices: Other Invoices for submission
to the SBC, if any CRG
7) Next Meeting(s): Wednesday
11/29/06 @ 7:30 PM All
Building Committee:
1) TOW, Town Hall Roof Replacement: Replacement,
Update, TOW comments/program/to be part of study of all Town Buildings
to be proposed by Boardof Education
2) Capitol Budget Advisory Committee: Report to
BC/next meeting November 29, 7:45am in Town Hall
3) HS Roof Replacement: H. B. Fishman & Co.;
Schedule for HS/Designs due Dec. 15 at 1/8 slope (NO $$ from State of
CT); discussion of best time to bid project and the particulars
of how timing of sending out RFP works with Special Town Meeting (our
assumption there would have to be a Town Meeting)
WESTON SCHOOL BUILDING COMMITTEE, Wednesday, November 1,
2006, 7:30pm, Commission Room, Town Hall
No quorum, no actions.
Discussion of all items: note item #2.
1) O&G Schedule / Progress:
a) HS Consolidated Punch List Update /
Status:
i) Punch List Review; see consolidated list
ii) Storm water cross connection test
schedule; 11/7/06
iii) United Masons settlement
iv) Close-out status; see listing
b) 3-5 School
i)
Close-out status; Drywall Assoc., Losito, NE Interiors, Merritt, Pipe
& Power; Pro. Painting; Schenectady Steel
ii) School water pressure
iii) 3-5 School MEP Commissioning: Schedule
c) MS / Site / Tennis
Courts:
i) Close-out status; Richards
ii) Pro-Seal repair
iii) Designing Nature planting
update
d) MS: Close-out, Richards, THP - Wetland Report Status
e) MFP: Tree planting status - Close-out status; Sentrale, Shawn’s Lawns
f) Zenon Plant: Fire pump use, WFD wants
to draw water, not in design - Close out status; Merritt, James T. Kay
g) Hurlbutt: Close-out, Shawn’s Lawns
2)
Revson Field Report: SBC Review/ citizens involved in school athletics
came to try to find out why Revson Field doesn't drain properly.
3) Approve Minutes of Previous meetings: Approval of
Meeting Minutes of 10/4/06/not done because of lack of quorum.
4) New Business as may properly come before the SBC
meeting: All
5) Executive Session: Claim reviews, settlements, if
any; Conn. Acoustics, UM, others
6) Change Orders & Invoice
Approval:
a) HS: Review of Proposed Change Orders,
if any
b) HS: Applications For Payment, if any
c) 3-5 School: Review of Proposed Change
Orders, if any
d) 3-5 School: Applications For Payment,
if any
e) Invoices: Other Invoices for submission
to the SBC, if any
7) Next Meeting(s): Wednesday
11/15/06 @ 7:30 PM
8) Adjournment
Building Committee:
1) TOW, Town Hall Roof Replacement: Replacement,
Update SBC - there will be documents prepared to have
an outside party proceed with this effort.
2) Capitol Budget Advisory Committee: Report to
BC AS/no report
3) HS Roof Replacement: H. B. Fishman & Co.;
Schedule for HS; cost est.; CRG; SBC; DC /
BOE/making progress but nothing in writing yet re: waiver from State
Board of Ed requirements - however, there still is the matter of
evaluating cost-benefit for proceeding at 1/8 inch slope with no
reimbursement or 1/4 inch slope with some unknown % reimbursement and a
more expensive project...more to come.
WESTON SCHOOL BUILDING COMMITTEE, Wednesday, October 18,
2006, 7:30pm, Commission Room, Town Hall
AGENDA - items in bold
1) O&G Schedule / Progress: review and discussion of details (O&G not present)
a) HS Consolidated Punch List Update /
Status:
i) Punch
List Review; see listing
ii) Storm water cross connection test
schedule
iii)
Close-out status; see listing
b) 3-5 School
i)
Close-out status; Drywall Assoc., Losito, NE Interiors, Merritt,
Pipe
& Power; Pro. Painting; Schenectady Steel
ii) School water pressure
iii) 3-5 School MEP Commissioning: Schedule
c) MS / Site / Tennis Courts:
i) Close-out
status; Richards
ii) Pro-Seal repair
iii) Designing Nature planting update
d) MS:
Close-out, Richards, THP - Wetland Report Status
e) MFP: Tree planting status - Close-out status;
Sentrale, Shawn’s Lawns
f) Zenon Plant: Fire pump use, WFD wants
to draw water, not in design - Close out status;
Merritt, James T. Kay
g) Hurlbutt: Close-out, Shawn’s Lawns
2)
Revson Field Report: SBC Review/could be very expensive to resolve the
problems of field construction undertaken by The Town of Weston at the
recommendation of former athletic director (using community
contribution for project with no guarantees on materials; or liability
for faulty construction);
3) Approve Minutes of Previous meetings: Approval of
Meeting Minutes of 10/4/06
4) New Business as may properly come before the SBC
meeting:
5) Executive Session: Claim reviews, settlements, if
any; Conn. Acoustics, UM, others/we did not hear any of this...
6) Change Orders & Invoice Approval:
a) HS: Review of Proposed Change Orders,
if any
b) HS: Applications For Payment, if any
c) 3-5 School: Review of Proposed Change
Orders, if any
d) 3-5 School: Applications For Payment,
if any
e) Invoices: Other Invoices for submission
to the SBC, if any
7) Next Meeting(s): Wednesday
11/01/06 @ 7:30 PM
8) Adjournment: Meeting adjourned @ ________ PM
Building Committee: both projects a bit behind
1) TOW, Town Hall Roof Replacement: Town Hall Roof
Replacement, Update
2) HS Roof Replacement: H. B. Fishman & Co.;
Schedule for HS, Update
WESTON SCHOOL BUILDING COMMITTEE, Wednesday, October 4, 2006, 7:30pm,
Commission Room, Town Hall
- This
meeting of significance because O&G fully represented by staff
responsible for high school, intermediate school and major, very
helpful and capable main office management now making it their business
to finish off all outstanding items left on the "punch list."
- Report
on trees for campus, in particular, location of what may be the
"booster barn" - it was recommended to wait on these trees because
their growth could be stunted if construction nearby upset their
expanding root system as they developed (our words).
- 3-5 school - change order OK'd to repair new cafetorium
stage stairs (design did not take into account expanding and
contracting through the changing seasons - condition developing that
would not be good for safety.
- H.S. kilns in place (not being used), but proper venting
still to be done - request from Bd. of Ed. to act PROMPTLY, please.
Meeting adjourned. Then the agenda for the Building
Committee was discussed...
BUILDING COMMITTEE ITEMS
Two roof items and projected before the Committee.
First, the old part of the
high school.
On schedule (HBFishman and his consultant) for making the case that it
would be a hardship to have to meet latest codes on roof design for
schools. The issue is "pitch" of the roof - structural analysis
is close to finished, evaluating what various degrees of slant on the
roof to be replaced would do to already existing and functioning
drainage systems (the greating the degree of pitch to the roof, the
faster rainwater, for example, would run off into drains - and perhaps
overflow the detainage provisions in the existing design???). The
question before the Committee is which alternative (1. as-is
pitch; 2. 1/4" with possibility of some State
funding, 3. 1/8" with no possibility of State rebate) to
recommend to the Selectmen. We hesitate to mention costs/rebate
from State numbers on-line, but this is one of the considerations that
will be part of decision-making--also, the more the pitch increases,
requiring additional modification to the drainage system at the high
school - the more the school program will be impacted (inside work).
Second, the old part of Town
Hall.
No reimbursement issues here. The old, "historic" part of Town Hall
needs a new-old roof (fitting the existing character of Town
Hall/historic district).
NOTE: About Weston
did not attend the meeting of September 20, which we understand was not
too well attended by school distric-related folks (back-to-school
nights).
WESTON SCHOOL BUILDING/BUILDING COMMITTEE, Wednesday,
September 6, 2006, 7:30pm, Commission Room, Town Hall
Nothing new, progress not moving forward to finish the
project; design for old section of high school's roof
progressing. Perhaps some direction coming (of a favorable
nature) from State education department re: design requirements
soon. We did not stay to find out about next meeting date.
WESTON SCHOOL BUILDING/BUILDING COMMITTEE, Wednesday,
August 23, 2006, 7:30pm, Commission Room, Town Hall
1. O&G Schedule/Progress/Budget Review for...
- high school punch list and close-out status/discussion of
how close it out - by October - took place with O&G
- 3-5 - punch list and close-out status/by September 16th
- MS and site - punch list and close-out status and review
of planting schedule/"moonscape" appearance questioned
- Zenon Plant - punch list and close-out
status/isolated overflow cause, perhaps, and now awaiting a plan from
MacDonald-Sharpe (Stu Fairbank) for monitoring the system we assume so
that there is no future uncertainty of what to do during excessive flow
events.
- Hurlbutt - punch list and close-out status/?
- MFP - punch list completion and close-out status/retained
assistance (Board of Ed assisted here)
2. Approve minutes of July 13, 26, 16, 2006/done
3. New business
4. Executive session - claim review, settlementss, if
any/none
5. Change orders and invoice approval/done
6. Next meeting September 6
BUILDING COMMITTEE
1. Town Hall roof replacement/no
discussion
2. HB Fishman & Co. - schedule for high school/nothing new.
SPECIAL WESTON
SCHOOL BUILDING/BUILDING COMMITTEE, Wednesday, August 16, 2006, 7:30pm,
Commission Room, Town Hall - agenda the same (?) as for August 9.
This was a meeting that also did not have a quorum (5 members
present). Next meeting next week.
WESTON SCHOOL BUILDING/BUILDING COMMITTEE, Wednesday,
August 9, 2006, 7:30pm, Commission Room, Town Hall/no quorum present
1. Approval of minutes of July 13 and 27
2. O&G schedule/Progress/Budget Review
- General stuff
- high school punch list and back charges
- 3-5 school - punch list and water pressure
- site - review tree planting schedule, top soil installed
by Richards, update on Revson Field Drainage (Milone&MacBroom -
8-14), update for flo monitoring proposal, wetland corrections, tennis
court repair, Route 57 culvert installation
3. New business
4. Executive Session on claims reviews, close-out settlements, if
any
5. Change orders, etc.
6. NEXT MEETING August 23 at 7:30pm; adjourn School Building
Committee
BUILDING COMMITTEE
1. Town of Weston, H.S. Roof Replacements:
- Town Hall
- H.B. Fishman, schedule for high school
WESTON SCHOOL BUILDING/BUILDING COMMITTEE, Wednesday,
July 25, 2006, 7:30pm, Commission Room, Town Hall
1. Approve minutes/no quorum present
2. O&G:
- MFP commissioning, 3-5/discussed
- HS:
- punch list completion status/two main items, other
smaller ones
- status of high school accounting and back charge/Town of
Weston paid some bills twice
- funds to hold by percentage of retainage & remaining
work/still OK!
- date for HS walk-thru/ mid August
- Cablevision proposal to extend HS d-mark (?)/Board of
Education to attend to this
- 3-5:
- punch list/almost there
- water flow/pressure/still no resolution - but there
should be in a week or two
- Site:
- review tree planting schedule by "Designing Nature"/to
be done this summer
- proposal by Town of Weston group for locating memorial
trees adjacent to the football field/OK
- update for Revson Field drainage:
Milone&MacBroom/not underway yet
- wetland corrections (Triton)/Town
committed to Army Corps for multi-year monitoring - also, some recent
work, some by Town of Weston on Revson Field, not done in according to
the wetland plan - not a big deal to repair, however
- tennis court repair/still not done (contractor paid)
3. New business
4. Executive Session-claims reviews, close outs if any/no
executive session
5. Change Orders, Invoice approvals/discussed
6. NEXT MEETING August 9, 2006
BUILDING COMMITTEE
Town of
Weston - high school and Town Hall roof replacement/High School Roof
work for proposal underway; photos of general condition of new
section of Town Hall here; all of
old section needs to be redone.
Special meeting of the
WESTON SCHOOL BUILDING/BUILDING COMMITTEE, Thursday, July 13, 2006,
7:30pm, Commission Room, Town Hall
1. Approve minutes of 6/28/06
2. Town of Weston, HS and Town Hall roof replacement:
- HB Fishman, HS contract update, supervision by
whom/discussion
- Town Hall roof replacement/discussion
3. O&G Schedule/progress/budget review
- General: MEP commissioning status/mechanical,
electrical and plumbing discussion
- HS - punch list/going way down!
- WIS - punch list/still one matter left...
- Site:
- Review tree planting schedule/to be completed
- Update Revson Field Drainage - Milone
& MacBroom/no report yet - review of what had been done at Revson
confirms that design should have been adequate
- Update for Zenon flo monitoring proposal/nothing new,
nothing resolved
4. New Business (is this appropriate at a Special
Meeting?)/"About Town" left after item #3
5. Executive Session - claims reviews; close-out
settlements, if any
6. Change orders & Invoice Approval
7. NEXT MEETING Wednesday, 7/26/06 or TBD @7:30pm.
WESTON SCHOOL BUILDING/BUILDING COMMITTEE, Wednesday,
June 28, 2006, 7:30pm, Commission Room, Town Hall - meeting NOT attended by "About Town"
(the first one we have missed in its entirety since November 15, 2001)
1. Approve minutes of 6/14/06
2. Town of Weston, HS and Town Hall roof replacement:
- HB Fishman, HS contract update, supervision by whom
- Town Hall roof replacement
3. O&G schedule/progress/budget review:
- HS - punch list completion status
- 3-5 school - punch list completion status
- Site:
- review of plan for street trees
- Revson Field drainage
- review of Zenon flow monitoring proposal
4. New Business as may properly come before the meeting
5. Executive Session: claims review, close-out settlements,
if any
6. Change orders and invoice approvals
7. Next meeting (to be announced) - our
sources suggest that the meeting took place and was over @9pm; it
is reported that the next Building Committee/SchoolBuilding Committee
meeting will be in 2 weeks (est. Wednesday, July 12, 7:30pm).
WESTON SCHOOL BUILDING/BUILDING COMMITTEE, Wednesday,
June 14, 2006, 7:30pm, Commission Room, Town Hall
1. Approve minutes of May 31/done
2. Town of Weston, HS and Town Hall roof replacements
- HB Fishman, HS update/discussion - particulars of what is
needed to move ahead
- Town Hall roof replacement/discussion - how
this roof is a different class of project from the high school,
requiring different approach
3. O&G Schedule/progress/budget review
- HS punch list completion status/must be finished
- 3-5 school punch list completion status/must be finished
- Site: approve proposal for street trees,
Revson Field Drainage (Milone & MacBroom), review Zenon flow
monitoring proposal/$7500 proposal OKd; more tested recommended
by present consultant to F-T at $2700 first week (less for a second
week), to determine where storm water is invading the septic/sewer lines
4. New business: Hurlbutt windows shop drawings to
be reviewed (after schools close June 22nd)
5. Executive session: claims reviews, closeout settlements
if any
6. Change orders
NEXT MEETING June 28, 2006, 7:30pm, Commission Room
WESTON SCHOOL BUILDING/BUILDING COMMITTEE, Wednesday, May
31, 2006, 7:30pm, Commission Room, Town Hall
1. Change order approvals/earlier in the agenda than
usual--SBC being especially careful about these last approvals
2. Executive session: claims reviews; close-out
settlements, if any/held at the end
3. Town of Weston: high school & Town Hall roof
replacements - HB Fishmann proposal/vote in favor of recommending HB
Fishman proposal (items1,2,3) to Board of Selectmen for high school
roof design; no action taken on Town Hall foof proposal.
4. Approval of minutes of 5/17 and 5/24/done
5. O&G Schedule/Progress/Budget Review - high school and WIS
punch list completion status; site: approve street tree
"Designing Nature" and Revson Field Drainage/we left before this item
was complaeted
NEXT meeting June 7, 7:30pm, Commission Room
WESTON SCHOOL BUILDING/BUILDING COMMITTEE, Wednesday, May
24, 2006, 7:30pm, Commission Room, Town Hall
1. Call meeting to order
2. 3-5 School
a. punch list completion status/not finished
b. O&G program to complete the project and
close out/?
3. Executive Session: FAI report (?); claims reviews
- close-out settlements (?)/Town Attorney present for this plus
consultants (more than an hour)
4. Town of Weston, Town Hall Roof Replacement - H.B. Fishman
& Co. proposal/proposal for Town Hall discussed - Town will wait to
proceed on this.
5. Minutes/not done
6. O&G Schedule/Progress/Budget Review
a. H.S. punch list and O&G program/?
b. Site: Zenon Plant: tests,
review and Revson Field Drainage/problem appears to be associated with
rain events--flow increases dramatically 4 hours after rainfall
ends; sump in old kitchen area one suspect: as-built
drawings to be prepared by June 2 for use during "flow tests" at
manholes (?)
7. New Business and any other new business/we left before this
item.
8. Change Orders and Unvoice Approval
9. Next meeting - May 31, 7:30pm
WESTON SCHOOL BUILDING/BUILDING COMMITTEE, Wednesday, May
17, 2006, 7:30pm, Commission Room, Town Hall
1. Call meeting to order
2. HS roof replacement/Town Hall roof, reference checks/done (OK)
3. Approve minutes of May 3 & 10/done
4. O&G schedule, progress, budget review/O&G not present
- HS - punch list, railing at auditorium,
etc/still out there
- WIS - punch list/"
- Site - Zenon plant/still not resolved
5. New business/several items, including new trees
6. Executive session: claims reviews, close out
settlements/we left
7. Change orders
8. Next meeting - 5-24-06
WESTON SCHOOL BUILDING/BUILDING COMMITTEE, Wednesday, May
10, 2006, 7:30pm, Commission Room, Town Hall
1. Call meeting to order
2. HS Roof Replacement and Town Hall Roof Replacement
- architects interview/discussion about roof condition, alternatives,
timing, with consultant
3. Minutes approval, May 3
4. Audit Controls/discussion of how Town is to go about review
5. O&G Schedule/Progress/Budget Review
a. at HS (O&G not present)
1)update, critical items
2)threshhold installation, dumpster fence;rail for
auditorium;K courtyard closers; Door B01 astragal; roof leak, new
areas; punch list progress, concrete power washing of hs/good
progress
3)kiln design build/good proposal, will
proceed
4)location of brick memorial
patio/Board of Education will handle this
b. 3-5
1)punch list/not done yet
2)entrance vestibule/"""
c. Site - Zenon plant test, review/first rain
observations yield some answers - one or two more experiments to
6. New Business/discussion of landscaping nd neatening up
7. Executive Session claims reviews, close out settlements
8. Change Orders
WESTON SCHOOL BUILDING COMMITTEE, Wednesday, May 3, 2006,
7:30pm, Commission Room, Town Hall (next meeting one week later on
the 10th?)
1) Call Meeting to Order: no
representative of O&G present
2) HS Roof Replacement, Architect
Selection/discussion and consensus re: roles of Facilities
Committee and Building Committee in retaining roof consultant
3) TOW, Town Hall roof replacement/no report
4) Memory Patio: Location/discussion
5) Approve Minutes of Previous meetings: not
done while "About Town" was present - Minutes of 4/26/06
6) Meeting Schedule/?
7) O&G Schedule / Progress / Budget Review:
a) HS:
i) Critical item construction list update/?
ii) Punch List progress and O&G
program/?
iii) Kiln Design Build proposal from
O&G/not looking as if anything is being done
iv) Progress with concrete power washing
of HS/?
v) Location of brick memorial patio/?
b) 3-5 School:
i) Punch List Completion Status; to
continue 5/10/06/no yet!
(1) Notification of failure to complete
their contract; Silktown, Losito/they seem to be responding
c) Site: Zenon Plant: tests, next steps, BOE Schedule/die tests to
be run next Tuesday to find the perhaps mistaken connections
8) Middle School Auditorium/?
9) New Business as may properly come before the SBC
meeting: we left
10) Executive Session: Claim reviews; Close-out
settlements
11) Change Orders & Invoice Approval:
a) HS: Review of Proposed Change Orders,
if any
b) HS: Applications For Payment, if any
c) 3-5 School: Review of Proposed Change
Orders, if any
d) 3-5 School: Applications For Payment,
if any
e) Invoices: Other Invoices for submission
to the SBC, if any
WESTON SCHOOL BUILDING COMMITTEE, Wednesday, April 26,
2006, 7:30pm, Commission Room, Town Hall
1) Call Meeting to Order: note that items were
taken out of order because visitors showed up at different times.
2) HS Roof Replacement Presentation/discussion with
consulting roof architect, then among Committee members. Prices
of materials, options to explore (phasing) and relationship to State Ed
requirements/funding ensued. "About Town" does not discuss
numbers (cost) because we did not receive a written copy of the
estimate, and thus are relying only on what we may have heard (and
heard incorrectly, perchance)
3) Approve Minutes of Previous meetings: Approve
Meeting Minutes of 4/19/06
4) Meeting Schedule
5) O&G Schedule / Progress / Budget Review: (we
had left)
a) HS:
i) Critical item construction list update
ii) Punch List progress and O&G program
iii) Kiln Design Build proposal from
O&G
iv) Power wash for HS concrete
b) 3-5 School: Update:
Punch List Completion Status; Selected Items as follows: (on-going wjen
we left - however, it was being discussed as we left that perhaps it
was time to assure that work on the punch list was completed.
(1) Status of As-Built drawings
(2) Resubmitting of the corrected
balancing report that FT marked up in Nov. for correction
(3) Mechanical corrections noted by
Edgerton
(4) Weather stripping, correction for all
doors
(5) Silktown corrections/punch list -
entrances, courtyard
(6) Electrical punch list and as built (by
others if not Losito)
(7) Cafetorium top stage riser
(8) Remaining open punch list completion
(9) Close out of all contracts
(10) Claim status
c) Site: Zenon
Plant: tests, next steps/we wanted to hear about this, and how it
worked out during the past weekend flooding, but we had to leave)
6)
Middle School Auditorium/discussion started by First Selectman -
considering the fact that no auditorium can be built for budget in
Referenum (consultant's view)
7) Hurlbutt School Window Replacement/gets OK
8) New Business as may properly come before the SBC
meeting:
SPECIAL WESTON SCHOOL BUILDING COMMITTEE, Wednesday,
April 19, 2006, 6:30pm, Commission Room at Town Hall.
1) Landscape proposal presentation/approved
2) Approve Minutes of Previous meetings:
Approve Meeting Minutes of 4/05/06/approved
3) O&G Schedule / Progress / Budget Review:
a) HS: still 4 items outstanding but end
in sight!
i) Critical item construction list update
ii) Punch List progress and O&G program
iii) HS occupancy update/confirmation
iv) Kiln Design Build proposal from O&G
v) Power wash for HS concrete
b) 3-5 School: Update: Punch List Completion Status/?
c) Site: Zenon Plant: tests, next steps, no rain/still OK
4) New Business as may properly come
before the SBC meeting:
5) Executive Session: Claim reviews; Close-out
settlements
6) Change Orders & Invoice Approval:
a) HS: Review of Proposed Change Orders,
if any
b) HS: Applications For Payment, if any
c) 3-5 School: Review of Proposed Change
Orders, if any
d) 3-5 School: Applications For Payment,
if any
e) Invoices: Other Invoices for submission
to the SBC, if any
7) Next Meeting(s): Wednesday
04/26/06 @ 7:30 PM
WESTON SCHOOL BUILDING COMMITTEE, Wednesday, April 5,
2006, 7:30pm, Commission Room at Town Hall. (Not
much happened at March 29, 2006 meeting - a quorum was present,
discussion of the few problems still present at WIS; WHS opening
later in May; kiln problem, no rain to test for Zenon corrections
yet.)
1) Approve Minutes of Previous
meetings: Minutes of 3/29/06/done
2) O&G Schedule / Progress / Budget Review:
a) HS:
i) Critical item construction list
update/getting smaller
ii) Punch List progress and O&G
program/?
iii)
HS occupancy update/confirmation/getting closer! May 13, 2006 at
10:30am set as of now for "opening" of new wings.
iv)
Kiln, Design Build proposal from O&G/a big deal, needs more work
(but temporary, for this school year "work-around" in play);
b) 3-5 School: Update: Punch List Completion Status/not finished yet
c) Site:
i)
Landscape Design proposals/a proposal within budget for 130+ trees plus
groundcover, etc. OK'd - more detail to come.
ii)
Zenon Plant: tests, next step, no rain/Good news - no flooding recent
rain - BUT, it is also possible that some basement fixes at high school
may be at least part of the cause of flooding (water from storm drains
flooding into sewers and ultimately tertiary treatment plant);
3) New Business as may properly come
before the SBC meeting: ?
4) Executive Session: Claim reviews; Contract
extension; Close-out settlements/ "About Town" left
5) Change Orders & Invoice Approval:
a) HS: Review of Proposed Change Orders,
if any
b) HS: Applications For Payment, if any
c) 3-5 School: Review of Proposed Change
Orders, if any
d) 3-5 School: Applications For Payment,
if any
e) Invoices: Other Invoices for submission
to the SBC, if any
6) Next Meeting(s): Wednesday
04/12/06 @ 7:30 PM
WESTON SCHOOL BUILDING COMMITTEE, Wednesday, March 22,
2006, 7:30pm, Commission Room at Town Hall
1) Call Meeting to
Order:
2) Approve Minutes of Previous meetings:
a) Approve Meeting Minutes of 3/08/06/done
b) Approve Meeting Minutes of 3/15/06/done
3) Executive Session: Claim reviews;
Contract extension; Close-out settlements/placed at end of agenda
4) O&G Schedule / Progress / Budget Review:
a) HS: Critical item construction list/ reviewed for outstanding
work
b) 3-5 School: Update: Punch List Completion Status/almost there!
c) Site:
i) Landscape Design - Memorial trees, location/scaled back but excellent plan in
the works!
ii) Zenon Plant; tests, next step/no rain,
no way to make observations...
5) New Business as may properly come
before the SBC meeting:
6) Change Orders & Invoice Approval: "About Town"
left.
a) HS: Review of Proposed Change Orders,
if any
b) HS: Applications For Payment, if any
c) 3-5 School: Review of Proposed Change
Orders, if any
d) 3-5 School: Applications For Payment,
if any
e) Invoices: Other Invoices for submission
to the SBC, if any
7) Next Meeting(s): Wednesday
03/29/06 @ 7:30 PM
WESTON SCHOOL BUILDING COMMITTEE, Wednesday, March 15,
2006, 7:30pm, Commission Room at Town Hall
1) Approve Minutes of Previous
meetings: Meeting Minutes of 3/08/06
2) Executive Session: Claim reviews; Contract
extension; Close-out settlements/discussed NOT in executive session
(not all items ready for discussion, either)
3) O&G Schedule / Progress / Budget Review:
a) HS:
i) Critical item construction list
update/in progress
ii) VFD operational update/things seem to
be working out re: power.
b) 3-5 School: Update: Punch List Completion Status/still not done
c) Site:
i) Landscape Design - Memorial trees, location/not finished
ii) Zenon Plant; tests, next step/Zenon
bought-out by GE
iii) Above grade height vents, possible
revised vent cap/a solution will be found soon
4) New Business as may properly come
before the SBC meeting:
5) Change Orders & Invoice Approval: we left at
this point
a) HS: Review of Proposed Change Orders,
if any
b) HS: Applications For Payment, if any
c) 3-5 School: Review of Proposed Change
Orders, if any
d) 3-5 School: Applications For Payment,
if any
e) Invoices: Other Invoices for submission
to the SBC, if any
6) Next Meeting(s): Wednesday
03/22/06 @ 7:30 PM
WESTON SCHOOL BUILDING COMMITTEE, Wednesday, March 8,
2006, 7:30pm, Commission Room at Town Hall
1)
Call Meeting to Order: Meeting was called to
order
2) Approve Minutes of Previous meeting - 3/01/06?
3) Building Committee: TOW co-generation options,
7:30 PM/Town Administrator presented co-generation propopsal idea
4) Executive Session:/done, no decisions made after
a) Consultant Interview; expert witness; 8
PM
b) Claim reviews; Contract extension;
Close-out settlement
5) O&G Schedule / Progress / Budget
Review:?
a) HS:
i) Critical item construction list update
ii) VFD operational update
b) 3-5 School: Punch List Completion Status
c) Site: Landscape Design
(1) Memorial trees, location/nothing new
(2) Ball field layout between MS and
HS/nothing new
ii)
Zenon Plant; tests, next step/next rain, staf and consultants will try
to run down where misconnections to system are
iii) Above grade height vents, possible
revised vent cap/?
6) New Business as may properly come
before the SBC meeting: "About Town" left
7) Change Orders & Invoice Approval:
a) HS: Review of Proposed Change Orders,
if any
b) HS: Applications For Payment, if any
c) 3-5 School: Review of Proposed Change
Orders, if any
d) 3-5 School: Applications For Payment,
if any
e) Invoices: Other Invoices for submission
to the SBC, if any
8) Next Meeting(s): Wednesday
03/15/06 @ 7:30 PM
WESTON SCHOOL BUILDING COMMITTEE, Wednesday, March 1,
2006, 7:30pm, Commission Room at Town Hall
1) Approve Minutes of Previous meetings:
2/22/06/done
2) O&G Schedule / Progress / Budget Review:
a) HS:
i) Critical item construction
list update/discussed
ii) MEP Deficiency Report
a) Power study/in progress
b) VFD/?
c) Glycol system/looking good
b) 3-5 School: Update: Punch List Completion Status/open issues
c) Site:
i) Landscape Design - (1) Memorial trees, location/full report
from Bd. of Ed.
ii) Zenon Plant; tests, next step/nothing
new
iii) Above grade height vents, possible
revised vent cap/?
iv) Revson Field ball field drainage/not
draining rapidly or totally so that fields are not dry in two days
3)
Hurlbutt Window Replacement: BOE revised window proposal
details/to go out to bid with modified solution
4) Meeting schedule for claims consultant/one
interview, one contract negotiation at next meeting (which may begin
early)
5) New Business as may properly come before the SBC
meeting: Town wants to install generator - Bldg Comm advises to
get a few bids
6) Executive Session: Claim reviews; Contract
extension; Close-out settlement/we left prior to this item
7) Change Orders & Invoice Approval:
a) HS: Review of Proposed Change Orders,
if any
b) HS: Applications For Payment, if any
c) 3-5 School: Review of Proposed Change
Orders, if any
d) 3-5 School: Applications For Payment,
if any
e) Invoices: Other Invoices for submission
to the SBC, if any
8) Next Meeting(s): Wednesday
03/08/06 @ 7:30 PM
WESTON SCHOOL BUILDING COMMITTEE, Wednesday, February 22,
2006, 7:30pm, Commission Room at Town Hall
1) Approve Minutes of Previous meetings: a,b,c
approved
a) Approve Meeting Minutes of 1/25/06
b) Approve Meeting Minutes of 2/1/06
c) Approve Meeting Minutes of 2/8/06
2) O&G Schedule / Progress / Budget
Review:
a) Review of January O&G cost
report/done
b) 3-5 School:/ work on going or completed
i) Northeast Interior Systems Cabinet
Repair
ii) Update: RTU-1 repair status
iii) Update: Punch List Completion Status
c) HS:
i) Dumpster/Other fence & pricing/
will wait
ii) O&G glycol cost proposal
review/discussed
iii) TS&E additional costs (HS) &
consulting time / fee extension/OK'd
iv) Critical item construction list
update/reviewed
v) Entrance Vestibule resolution/door
redesigned
d) Site:
i) Landscape Design/waiting
ii) Zenon Plant, smoke test 2/17/smoke
test not conclusive, more observations during rain events necessary
iii) Above grade height of bollards,
hydrants, vents, etc./discussed
3) Hurlbutt Window Replacement: BOE
revised proposal/ready for Building Committee review
4) New Business as may properly come before the SBC
meeting: we left after this.
5) Executive Session: a)
Claim reviews; Contract Extension; Close-out settlement
6) Change Orders & Invoice Approval:
a) HS: Review of Proposed Change Orders,
if any
b) HS: Applications For Payment, if any
c) 3-5 School: Review of Proposed Change
Orders, if any
d) 3-5 School: Applications For Payment,
if any
e) Invoices: Other Invoices for submission
to the SBC, if any
7) Next Meeting(s): Wednesday
03/01/06 @ 7:30 PM
CANCELLED
WESTON SCHOOL BUILDING COMMITTEE, Wednesday, February 15,
2006, 7:30pm, DOWNSTAIRS MEETING ROOM (in basement)
1) Approve Minutes of Previous meetings:
a) Approve Meeting Minutes of 1/25/06
b) Approve Meeting Minutes of 2/1/06
c) Approve Meeting Minutes of 2/8/06
2) O&G Schedule / Progress / Budget
Review:
a) Review of January O&G cost report
b) 3-5 School:
i) Northeast Interior Systems Cabinet
Repair
ii) Update: RTU-1 repair status
iii) Update: Punch List Completion Status
c) HS:
i) Dumpster/Other fence & pricing
ii) O&G glycol cost proposal review
iii) TS&E additional costs (HS) &
consulting time / fee extension
iv) Critical item construction list update
v) Entrance Vestibule resolution
d) Site:
i) Landscape Design
ii) Zenon Plant, smoke test 2/17
iii) Above grade height of bollards,
hydrants, vents, etc.
3) Hurlbutt Window Replacement: BOE
revised proposal
4) New Business as may properly come before the SBC
meeting:
5) Executive Session: Claim reviews; Contract
Extension; Close-out settlement
6) Change Orders & Invoice Approval:
a) HS: Review of Proposed Change Orders,
if any
b) HS: Applications For Payment, if any
c) 3-5 School: Review of Proposed Change
Orders, if any
d) 3-5 School: Applications For Payment,
if any
e) Invoices: Other Invoices for submission
to the SBC, if any
7) Next Meeting(s): Wednesday
02/22/06 @ 7:30 PM
WESTON SCHOOL BUILDING COMMITTEE, Wednesday, February 8, 2006, 7:30pm,
Commission Room at Town Hall
No quorum present nor was there a representative of
O&G; discussion on items but no action taken.
1) Approve Minutes of Previous meetings:
Approve Meeting Minutes of 1/25/06, 2/1/06
2) O&G Schedule / Progress / Budget Review:
a) Review of January O&G cost report
b) 3-5 School:
i) Northeast Interior Systems Cabinet
Repair
ii) Update; RTU-1 repair status
iii) Punch List Completion Status
c) HS:
i) Dumpster/Other fence & pricing
ii) O&G glycol cost proposal review
iii) TS&E additional costs (HS) &
consulting time / fee extension
iv) Critical item construction list update
v) Coordination of new requested work:
roofs, CL&P rebate, additional requirements, etc.
vi) Entrance Vestibule resolution
d) Site:
i) Landscape Design
ii) Zenon Plant, smoke test 2/17
iii) Above grade height of bollards,
hydrants, vents, etc.
3) Hurlbutt Window Replacement: BOE
revised proposal
4) New Business as may properly come before the SBC
meeting:
5) Executive Session: Claim reviews; Contract
extension; Close-out settlement
6) Change Orders & Invoice Approval:
a) HS: Review of Proposed Change Orders,
if any
b) HS: Applications For Payment, if any
c) 3-5 School: Review of Proposed Change
Orders, if any
d) 3-5 School: Applications For Payment,
if any
e) Invoices: Other Invoices for submission
to the SBC, if any
7) Next Meeting(s): Wednesday
02/15/06 @ 7:30 PM
WESTON SCHOOL BUILDING COMMITTEE, Wednesday, February 1, 2006, 7:30pm,
Commission Room at Town Hall
1) Approve Minutes of Previous
meetings: Minutes of 1/25/06/not done
2) O&G Schedule / Progress / Budget Review:
a) 3-5 School:
i) Review of Northeast Interior Systems
settlement proposal/?
ii) Update; RTU-1 repair status/?
b) HS:
i) Dumpster fence design & pricing/no
decision
ii) O&G glycol cost proposal/no
decision
iii) Update on
Poulsen light fixture, mtg.
1.31.06/good explanation, no final decision
iv) TS&E additional costs (HS) &
consulting time / fee extension/not done
v) Critical item construction list
update/discussed
vi) Entrance Vestibule/solutions for
uneven entry area offered
c) Site:
i) Landscape Design/in two weeks, $$
proposal to be in
ii)
Update on Zenon Plant discharge report/over Presidents' 4-day weekend,
smoke and die tests to be run on campus
iii) Above grade height of bollards,
hydrants, vents, etc./solution at hand
3) Hurlbutt Window Replacement: BOE
revised proposal/may be put back
4) New Business as may properly come before the SBC
meeting:
5) Executive Session: "About Town" left at this
point
a) O&G agreement & O&G ‘s
response
b) Pipe & Power revised settlement
claim letter
c) C.H. Nickerson Close-out settlement
6) Change Orders & Invoice Approval:
a) HS: Review of Proposed Change Orders,
if any
b) HS: Applications For Payment, if any
c) 3-5 School: Review of Proposed Change
Orders, if any
d) 3-5 School: Applications For Payment,
if any
e) Invoices: Other Invoices for submission
to the SBC, if any
7) Next Meeting(s): Wednesday
02/08/06 @ 7:30 PM
WESTON SCHOOL BUILDING COMMITTEE, Wednesday, January 25,
2006, 7:30pm, Commission Room at Town Hall
1) Approve Minutes of Previous
meetings: Approve Meeting Minutes of 1/11/06 and 1/18/06/done
2) O&G Schedule / Progress / Budget Review:
a) 3-5 School
i) Update punch list status/still some
things outstanding
ii) Losito’s punch list status/"
iii) RUT-1 status/"
iv)
Cabinet details for Media Center & Administration
Area/sub-committee discussed this during latter part of this
evening--we left before any decision.
v) Stage floor crack/? But will not
interfere with "Aladdin"
b) HS:
i) Dumpster fence design & pricing/?
ii) O&G glycol cost proposal review/?
iii) Update on
Poulsen light fixture
lamping / power test/company President or rep to visit to check it out.
iv) TS&E consulting contract
additional cost request/not discused
v)
Update critical construction items/problematic issue, perhaps big $$ -
but further study to be done before final presentation of draft
findings.
vi)
Glass changes for the Guidance Area/further check on this request
because architect believes the glass now in place was what was called
for in the first place.
vii)
Roof repair proposal/H.S. roof must be totally replaced pronto (last
proposal for total redo was in mid-1980's)
viii) Cafeteria / Kitchen fire alarm/still
figuring out why emergency alarm going off in the whole school
c) Site:
i) Landscape Design for the
Campus/minimalist approach
ii) Zenon Plant discharge report/probably
problem from Masy '05 when the high school was connected
iii) Sentrale proposed settlement/to be
covered by action of Boards of Selectmen and Finance
3)
MS Auditorium: ARO’s MS auditorium BOE meeting schedule/Facilities
Committee to meet Feb. 3rd at 2pm in room 224 of W.I.S.
4) Hurlbutt Window Replacement: BOE revised
proposal/? and we left at this point
5) Executive Session:
a) To review O&G response to SBC
agreement
b) To review Pipe & Power claim
settlement proposal
6) New Business as may properly come
before the SBC meeting:
7) Change Orders & Invoice Approval:
a) HS: Review of Proposed Change Orders,
if any
b) HS: Applications For Payment, if any
c) 3-5 School: Review of Proposed Change
Orders, if any
d) 3-5 School: Applications For Payment,
if any
e) Invoices: Other Invoices for submission
to the SBC, if any
8) Next Meeting(s): Wednesday
02/01/06 @ 7:30 PM
WESTON SCHOOL BUILDING COMMITTEE, Wednesday, January 18,
2006, 7:30pm, Commission Room at Town Hall
1)
Approve Minutes of Previous meetings: Approve Meeting Minutes of
1/11/06 - not to be done this evening
2) Executive Session:
a) To review O&G agreement &
O&G ‘s response
b) To review Pipe & Power proposal to
settle claim
3) O&G Schedule / Progress / Budget
Review:
a) 3-5 School
i) Review of Northeast Interior Systems
settlement proposal/done
ii) Review of Losito’s 1/5 site punch list
review/only one item left
iii) RTU-1 repair status/?
b) HS:
i) Dumpster fence design &
pricing/next week
ii) O&G glycol cost proposal/next week
iii) Update on
Poulsen light fixture
lamping/?
iv) TS&E additional costs (HS) &
consulting time / fee extension/discussion next week
v) Critical item construction listing
update/document prsented for later review
c) Site:
i) Update on Landscape Design Changes; 3-5
& Campus; BB scope/not done
ii)
Update on Zenon Plant discharge report/tomorrow meeting with CT Water,
MacDonald Sharp, O&G, Owner's Rep (?) and School rep (?) to go over
all records of events; only after this analysis, "smake test" to be done
iii) Above grade height of bollards,
hydrants, vents, etc./?
4)
MS Auditorium: ARO’s MS auditorium contract; BOE meeting schedule/to be
discussed at a Facilitiies Subcommittee of the Board of Education,
T.B.A.
5) Change Orders & Invoice Approval: ("About
Town" left...)
a) HS: Review of Proposed Change Orders,
if any
b) HS: Applications For Payment, if any
c) 3-5 School: Review of Proposed Change
Orders, if any
d) 3-5 School: Applications For Payment,
if any
e) Invoices: Other Invoices for submission
to the SBC, if any
6) Next Meeting(s): Wednesday
01/25/06 @ 7:30 PM
WESTON SCHOOL BUILDING COMMITTEE, Wednesday, January 11,
2006, 7:30pm, Commission Room at Town Hall
1) Approve Minutes of Previous meetings:
Approve Meeting Minutes of 1/04/06/done
2) O&G Schedule / Progress / Budget Review:
a) 3-5 School
i) Review of SBC Punch-List walk thru for
1/7/06 @ 10:00 AM/done
ii) Review of Losito’s 1/5 site punch list
review/in process of completing
iii) RTU-1 status/?
b) HS:
i) Dumpster fence design & pricing/2
alternatives to be priced
ii) O&G glycol cost proposal/OK
iii) Update on
Poulsen light fixture
lamping/excellent report from sub-committee
iv) TS&E additional costs &
consulting extras/more detail needed
v) Listing of outstanding, critical
construction items/some could be difficult (those requested from Fire)
c) Site:
i) Update on Landscape Design Changes; 3-5
& Campus; BB scope/nothing new
ii)
Update on Zenon Plant discharge report/CT Water has not yet produced
Zenon Plant data that can be correlated with weather reports and
flooding events records
3)
MS Auditorium: ARO’s MS auditorium proposal; BOE meeting schedule/no
money to do anything but clean up HS auditorium - study by ARO for
modified program for "box" for WMS auditorium
4) Executive Session: To review agreement with
O&G for contract extension/done first - we left when items 4a-e
were discussed in open session
a) HS: Review of Proposed Change Orders,
if any
b) HS: Applications For Payment, if any
c) 3-5 School: Review of Proposed Change
Orders, if any
d) 3-5 School: Applications For Payment,
if any
e) Invoices: Other Invoices for submission
to the SBC, if any
6) Next Meeting(s): Wednesday
01/18/06 @ 7:30 PM
WESTON SCHOOL BUILDING COMMITTEE, Wednesday, January 4, 2006,
7:30pm, Commission Room at Town Hall
1) Approve Minutes of Previous
meetings: Approve Meeting Minutes of 12/14/05 & 12/21/05/OK
2) O&G Schedule / Progress / Budget Review:
a) Meeting with SBC & O&G for
1/5/06/held in Town Hall
b) 3-5 School
i) SBC Punch-List walk thru for 1/7/06 @
10:00 AM/announced
ii) Losito completion status/may be done?
c) HS:
i) Update on design for dumpster fence
& split locations/Design Subcommittee job?
ii) O&G glycol cost proposal/no
presentation
iii) Update on
Poulsen light fixture
lamping/not solved yet
iv) Update on voltage testing at
transformer, NE Elec Testing/to done soon
v) Technology Systems & Equipment:
additional costs & consulting extras/discussed
vi) Vanguard Application for Payment &
future P.O.s by Town of Weston/to be OK'd
d) Site:
i) Update on Landscape Design Changes; 3-5
& Campus; BB scope/not ready for report
ii) Update on Zenon Plant discharge
report/nothing new
3) MS Auditorium: ARO’s MS auditorium
proposal; BOE meeting schedule/ARO to do study for modified design
4) Change Orders & Invoice Approval: (we
left)
a) HS: Review of Proposed Change Orders,
if any
b) HS: Applications For Payment, if any
c) 3-5 School: Review of Proposed Change
Orders, if any
d) 3-5 School: Applications For Payment,
if any
e) Invoices: Other Invoices for submission
to the SBC, if any
5) Next Meeting(s): Wednesday
01/11/06 @ 7:30 PM
WESTON SCHOOL BUILDING COMMITTEE, Wednesday, December 21, 2005,
7:30pm, Commission Room at Town Hall Revised
Agenda
1) Approve Minutes of Previous meetings -
12/14/05
2) O&G Schedule / Progress / Budget Review:
a) 3-5 School - Update Report on “Close-Out” & punch list
completion/still need more info
b) HS:
i) Update on design solution for dumpster
fence & split locations/still on-going
ii) CO for FT glycol design proposal/?
iii) Update on
Poulsen light fixture
lamping/still going on
iv) Update on voltage testing at
transformer, NE Elec Testing/no answers yet
v) Completion of
sheet rock
in Lobby & Administrative Area/report
c) Site:
i) Update on Landscape Design Changes; 3-5
& Campus; BB scope/CT DOE needs to OK changes
ii) Update on Zenon Plant discharge
report/problem related to heavy rainfall (confirmation)
3)
MS Auditorium: ARO’s proposal for the MS auditorium/first phase of
proposal for revised performance space OK'd (we left at this point)
4) Any other business that may properly come before
the meeting: Claims dispute procedure
5) Change Orders & Invoice Approval:
a) HS: Review of Proposed Change Orders,
if any
b) HS: Applications For Payment, if any
c) 3-5 School: Review of Proposed Change
Orders
d) 3-5 School: Applications For Payment,
if any
e) Invoices: Other Invoices for submission
to the SBC
6) Next Meeting(s): Wednesday
01/04/06 @ 7:30 PM
WESTON SCHOOL BUILDING COMMITTEE, Wednesday,
December 14, 2005, 7:30pm, Commission Room at Town Hall
1) Approve Minutes of Previous
meetings: Minutes of 12/7/05
2) O&G Schedule / Progress / Budget Review:
a) 3-5 School - Report on “Close-Out” & punch list completion/ only 2
items still outstanding and not quickly to be fixed
b) HS:
i) Update on design solution for dumpster
fence & split locations/discussed
ii)
Review / Approval of FT glycol design proposal/too expensive and not
necessary - back to the drawing boards!
iii) Update on Poulsen
light fixture
lamping/not fixed yet
iv) Update on CL&P voltage testing at
transformer & NE Elec Testing/not done yet
c) Site:
i) Update on Landscape Design Changes; 3-5
& Campus; BB scope/proposals for other solutions due
ii)
Update on Zenon Plant discharge report/GOOD NEWS...engineer back on job
and seeking fix: CT Water wants smoke test at WHS (first flood in
June when WHS connected); O&G believes it is at WMS and
suggests die test (to be continued...)
3)
Any other business that may properly come before the meeting: ARO
proposal discussed re: WMS Auditorium. ARO could explore
feasibility of building structure to house activities and fixtures for
auditorium-performance space for at least 300 (this is how I heard
it--no copies circulated to Committee, so we did not ask for copy) for
@$34,000 and be ready to give their opinion by end of January 2006.
4) Change Orders & Invoice Approval: we
left.
a) HS: Review of Proposed Change Orders
b) HS: Invoices for submission to the SBC
c) HS: Applications For Payment
d) 3-5 School: Review of Proposed Change
Orders
e) 3-5 School: Invoices for submission to
the SBC
f) 3-5 School: Applications For Payment
g) Invoices: Other Invoices for submission
to the SBC
5) Next Meeting(s): Wednesday
12/21/05 @ 7:30 PM
WESTON SCHOOL BUILDING COMMITTEE, Wednesday,
December 7, 2005, 7:30pm, Commission Room at Town Hall
Order of items
changed to accomodate visitors (F-T and Bd of Ed Director of
Facilities)
1) Approve Minutes of Previous
meetings: Minutes of 11/30/05/done
2) Election of Officers/changed to later in the
agenda - we understand, from a reliable source, that current leadership
will serve another year.
3) O&G Schedule / Progress / Budget Review:
O&G not present, Owner's Rep's rep reported
a) HS:
i)
Design solution for dumpster fence; update/memo read from Building
Committee member assigned to this task (we think we heard the solution
to dumpster issue: move 30-yard container to east side of high
school, leave two 10-yard containers in original position);
ii)
Update on Poulsen light fixture lamping/discussion ensued - concerns
about what is causing the erratic color changes in light bulbs
iii)
Need and pricing for glycol additive for RTU-5 heating/cooling
loop/Director of Facilities for Bd of Ed made presentation (F-T will
provide drawings);
iv)
Power fluctuation problems and need to test voltage from
transformer/Director of Facilities hopes to get power company to test
the set up;
b) 3-5 School: Status
of M.J. Losito punch list completion/Committee wants one list confirmed
as "final" list and then schedule for when work will be done (and we
presume, a way of measuring what was done when);
c) Site:
i) Landscape Design Changes; 3-5 &
Campus/no decision as to how to finish this
ii) Zenon Plant discharge report;
update/no decision how to finish this
4) Any other business that may properly
come before the meeting:
5) Change Orders & Invoice Approval:/not done
until after we had left;
a) HS: Review of outstanding Proposed
Change Orders
b) HS: Invoices for submission to the SBC
c) 3-5 School: Review of outstanding
Proposed Change Orders
d) 3-5 School: Invoices for submission to
the SBC
e) Invoices: Other Invoices for submission
to the SBC
6)
Executive Session/School Building Committee went into the Executive
Session with motion for discussion of "pending litigation" and
"contract negotiations" at 8:50pm; we waited for re-ordered
agenda item #2, but at 9:34pm, we had to leave while Executive Session
was still on-going...
7) Next Meeting(s): Wednesday 12/14/05 @
7:30 PM
WESTON SCHOOL BUILDING COMMITTEE, Wednesday,
November 30, 2005, 7:30pm, Commission Room at Town Hall
1) Approve Minutes of Previous meeting -
11/16/05/done
2) O&G Schedule / Progress / Budget Review:
a) Review of October Monthly Progress
Report (#16)/done
b) HS:
i) Design solution for dumpster fence;
update/drawing shown, agreement reached
ii)
Update on Poulsen light fixture lamping/no
solution yet - before more
fixtures installed elsewhere, it was suggested that a more succinct
explanation and one satisfactory to budget (looking forward) be
forthcoming
iii) Additional FF&E - Supplemental
Equipment Request for Mats in Gymnasium/done
iv) Schedule for completion and turnover
of unoccupied areas/report given
v) Schedule for completion of occupied
areas/report given
vi) Schedule for completion of exterior
site work/no satisfactory solution for the completion yet at hand
c) 3-5 School:
i) Review of final commemorative plaque
submission/done
ii) Additional FF&E – Cafeteria
Chairs/OK
iii) Schedule for completion of
outstanding punch list items/OK
d) Site:
i)
Fencing at Revson Field on Collin’s border; update/memo from Town (and
other correspondence) presented - vote 5-2 to recommend no action
(please remember that this is not the official record of this
meeting--we did not have copies of all of the items in the file to
review);
ii) Landscape Design Changes; 3-5 &
Campus/see b)vi
iii)
Zenon Plant discharge report; update/CT Water not yet on the job
working with MacDonald -Sharp and the Schools to tract down the faulty
connection
e) Review of Outstanding O&G
Payments/letter read aloud
3) Any other business that may properly
come before the meeting: (We left at this point)
4) Change Orders & Invoice Approval:
a) HS: Review of outstanding Proposed
Change Orders
b) HS: Invoices for submission to the SBC
c) 3-5 School: Review of outstanding
Proposed Change Orders
d) 3-5 School: Invoices for submission to
the SBC
5) Next Meeting(s): Wednesday
12/7/05 @ 7:30 PM
WESTON SCHOOL BUILDING COMMITTEE, Wednesday,
November 16, 2005, 7:30pm, Commission Room at Town Hall
1) Approve Minutes of Previous
meetings: Approve Meeting Minutes of 11/9/05
2) O&G Schedule / Progress / Budget Review:
a) HS:
i) Design solution for dumpster fence;
update
ii) Update on
Poulsen light fixture
lamping, change of bulbs
iii) Power washing of old façade
b) 3-5 School: Update of Close-Out Status; Media door replacement
c) Site:
i) Fencing at Revson Field on Collin’s
border; update
ii) Landscaping; 3-5 & Campus
iii) Zenon Plant discharge report; update
iv) Zenon Plant Screening
d) MS: BOE costs to respond to flooding at MS
e) MS Auditorium: BOE Program for Design, Budget & Schedule for a new
Auditorium
3) Any other business that may properly
come before the meeting:
4) Change Orders & Invoice Approval:
a) HS: Invoices for submission to the SBC
b) 3-5 School: Invoices for submission to
the SBC
c) Invoices: Other Invoices for submission
to the SBC
5) Next Meeting(s): Wednesday
11/30/05 @ 7:30 PM
WESTON SCHOOL BUILDING COMMITTEE, Wednesday,
November 9, 2005, 7:30pm, Commission Room at Town Hall
AGENDA ("About Town" modified agenda format)
1. Minutes/approved
2. O&G Schedule, Progress/Budget Review:
a) HS:
i) Construction Completion & Punch
List in areas with C of O:
(1) Delivery of Cabinets for Area C &
other Classrooms/ready for review
(2)
Schedule for PA / Clock System/working in areas of highest use!
Now designated staff must learn system adjustment techniques
(3) Milcon schedule & water tight
building/working
ii) Dumpster fence/need more detail on low cost
option design
iii) New main entrance proposed revisions;
update/should not be additional cost
iv) FT report on
Poulsen light fixture
lamping/bulbs being tested first
b) 3-5 School:
i) Update Close-Out Status update; Media door replacement/close
to close
ii) additional
FF&E/2 big tables for lunchroom (chairs?)
c) Site:
i)
Fencing at Revson Field on Collin’s border/discussed and further
information needed for full review as per Selectmen's request.
ii) Work north of MS - confirm
completion/parking lot in!
iii) Landscaping; 3-5 & Campus/in
progress finding design option
iv) Zenon plant discharge report update/no
news from MacDonald-Sharp
d) MS: Pool wall completion date update/?
e) MS Auditorium: BOE
Program for Design, Budget & Schedule for a new Auditorium/draft
presented for $2 million option "bare bones" project with 400 seats
(for "class" performances plus parents); house lights,, heat,
airconditioning, 5' stage height (45'x35') pit area provided, wings, no
fly, no curtain, pipes for voice, etc. Seating raked (3 options -
temporary, 1/2 temp. and all permanent)
f) Hurlbutt: Installation Schedule for Construction of Rt. 57 crossing
- TBS/soon!
3. Any other business, executive session, change orders
and invoice approvals/we left
WESTON SCHOOL BUILDING COMMITTEE, Wednesday, November 2, 2005,
7:30pm, Commission Room at Town Hall - NO QUORUM
1) Approve Minutes of Previous meetings: Approve
Meeting Minutes of 10/12/05 & 10/26/05
2) Executive Session
3) O&G Schedule / Progress / Budget Review:
a) HS:
i) O&G to issue a revised Schedule;
Areas “A & B” & occupied areas;
ii) Construction Completion & Punch
List in areas with C of O:
(1) Delivery of Cabinets for Area C &
other Classrooms
(2) Schedule for PA / Clock System
(3) Milcon schedule & water tight
building
iii) New main entrance proposed revisions;
update
iv) FT report on Poulsen light fixture
lamping
b) 3-5 School: Update Close-Out Status update; Media door replacement
c) Site:
i) Fencing at Revson Field on Collin’s
border
ii) Schedule update for work North of the
MS
iii) Landscaping; 3-5 & Campus
iv) Zenon plant discharge report update
d) MS: Pool wall completion date update
e) MS Auditorium: BOE Program for Design, Budget & Schedule for a new
Auditorium
f) Hurlbutt: Installation Schedule for Construction of Rt. 57 crossing
- TBS
4) Any other business that may properly
come before the meeting:
5) Change Orders & Invoice Approval:
a) HS: Invoices for submission to the SBC
b) 3-5 School: Invoices for submission to
the SBC
c) Invoices: Other Invoices for submission
to the SBC
6) Next Meeting(s): Wednesday
11/09/05 @ 7:30 PM
WESTON SCHOOL BUILDING
COMMITTEE, October 26, 2005, 7:30pm, Commission Room at Town Hall
1)Approve Minutes of Previous meetings - 10/12/05/done
2) Executive Session/moved to end of agenda
3) O&G Schedule / Progress / Budget Review:
a) HS:
i) Schedule; Areas “A & B” &
occupied areas
ii) Construction Completion & Punch
List in areas with C of O:
(1) Update Cabinets for Area C & other
Classrooms
(2) Update PA / Clock System
(3) Milcon schedule & water tight
building
iii) New main entrance proposed revisions
b) 3-5 School - Update Close-Out Status update/close to close-out
c) Site:
i) Schedule for work North of the
MS/parking lot to be finished before Election Day
ii) Landscaping; 3-5 & Campus/some
more BIG trees to be donated! (THANKS YOU!!!)
d) MS - Pool wall completion date update/close
e) MS Auditorium - BOE Program for Design, Budget & Schedule for a new
Auditorium/Board of Education to approved revisions within 2 weeks+
f) Hurlbutt - Installation Schedule for Construction of Rt. 57 crossing
- TBS
4) Any other business that may properly
come before the meeting:
5) Change Orders & Invoice Approval: (we left)
a) HS: Invoices for submission to the SBC
b) 3-5 School: Invoices for submission to
the SBC
c) Invoices: Other Invoices for submission
to the SBC
6) Next Meeting(s): Wednesday
11/02/05 @ 7:30 PM
WESTON SCHOOL BUILDING
COMMITTEE, Wednesday, October 12, 2005, 7:30pm, Commission Room at
Town Hall
1) Approve Minutes of Previous
meetings: 9/21/05, 9/28/05 & 10/05/05
2) O&G Schedule / Progress / Budget Review:
a) HS:
i) Revised Schedule; Areas “A & B”
& occupied areas/done
ii) Review O&G Report # 15; CRG to
include overview/some time sequences need changing
iii) Construction Completion & Punch
List in areas with C of O:
(1) Update Cabinets for Area C & other
Classrooms/on-going
(2) Update PA / Clock System/more OK
(3) Update O&G Schedule to move office
trailers/soon - to old portables on the side of WMS.
b) 3-5 School: Update Close-Out Status update/on time
c) Site:
i) Schedule for work North of the MS/?
ii)
Landscaping; 3-5 & Campus; BB declined to provide services/must
proceed with tree planting (to use another service)
d) MS: Pool wall replacement / completion date update/on-going
e) MS Auditorium: BOE Program for Design, Budget & Schedule for a new
Auditorium.Bd of Ed finalizing program
f) Hurlbutt: Installation Schedule for Construction of Rt. 57 crossing
- ?
3)
Any other business that may properly come before the meeting: (we left
after discussion of probable cancellation of SBC meeting next week)
4) Change Orders & Invoice Approval:
a) HS: Invoices for submission to the SBC
b) 3-5 School: Invoices for submission to
the SBC
c) Invoices: Other Invoices for submission
to the SBC
5) Next Meeting(s): Wednesday
10/19/05 @ 7:30 PM
WESTON SCHOOL BUILDING
COMMITTEE, Wednesday, October 5, 2005, 7:30pm, Commission Room at
Town Hall
1) Approve Minutes of Previous
meetings: Approve Meeting Minutes of 9/21/05 & 9/28/05
2) O&G Schedule / Progress / Budget Review:
a) HS:
i) O&G to Issue Revised Schedule;
Areas “A & B” & occupied areas
ii) O&G to Issue Report # 15; CRG to
include overview/should be OK
iii) Construction Completion & Punch
List in areas with C of O:
(1) Cabinets for Area C & other
Classrooms/will go ahead next week
(2) PA / Clock System/plan complete
(3) O&G Schedule to move office
trailers/2 weeks
(4) Additional FF&E for science wing,
see FT letter attached/to be done next week
b) 3-5 School: Close-Out Status update/OK
c) Site:
i) Schedule for work North of the MS/?
ii) Landscaping; 3-5 & Campus/plan
discussed
d) MS: Pool wall replacement / completion date update/some things
don't exactly fit, but this may be simply solved...
e) MS Auditorium: BOE
Program for Design, Budget & Schedule for a new Auditorium/$2.9
million (now worth $2.5 when cost increases figure in) left - Board of
Education coming up with plan
f) Hurlbutt: Installation Schedule for Construction of Rt. 57 crossing
- TBS/being coordinated
3)
Any other business that may properly come before the meeting:
Letter from First Selectman requestion review by School Building
Committee of fence on Revson Field issue - it will be on agenda at a
future meeting after proper review to see what had been planned for
this part of Revson Field site in official plans/drawings.
4) Change Orders & Invoice Approval:
a) HS: Invoices for submission to the SBC
b) 3-5 School: Invoices for submission to
the SBC
c) Invoices: Other Invoices for submission
to the SBC
5) Next Meeting(s): Wednesday
10/12/05 @ 7:30 PM/plus 6:30pm design sub-committee
WESTON SCHOOL BUILDING
COMMITTEE, Wednesday, September 28, 2005, 7:30pm, Commission Room
at Town Hall
1) Approve Minutes of Previous
meetings: Meeting Minutes of 9/21/05
2) O&G Schedule / Progress / Budget Review:
Budget to be discussed next week.
a)
HS: From what we heard, O&G is intending to be finished with
the job by mid-December (more managerial manpower to be assigned)
i) Issue Revised Schedule to complete
Areas “A & B” & occupied areas/see above
ii) Issue of O&G Report # 15; CRG
overview? when/next week
iii) Construction Completion & Punch
List in areas with C of O:
(1) Cabinets for Area C & other
Classrooms/cabinet making company discusses their take on the issue
(2) Galleria/not first priority
(3) PA / Clock System/first priority
(4) Building Security/done-fixed
(5) O&G Schedule to move office
trailers/to be done if O&G hierarchy OK's it
b) 3-5 School:
i) Close-Out Status/close
ii) Acoustical panels, CO approval /
Schedule//
c) Site:
i)
Schedule for work North of the MS schedule/first week in November
completion--doesn't this mean we won't have access to the MS for voting?
ii) Landscaping; 3-5 & Campus/?
iii) Correct site yard drain at MS field,
when?/in progress?
d) MS: Pool wall replacement / completion date
e) MS Auditorium: Discussion
for the Program / Design & Schedule for the new Auditorium/$2.9
million left in budget for this (estimates from 2001 out of date)
f) Hurlbutt:Installation Schedule for Construction of Rt. 57 crossing
- TBS/? - we left.
3) Any other business that may properly
come before the meeting:
4) Change Orders & Invoice Approval:
a) HS: Invoices & Applications for
Payment for submission to the SBC
b) 3-5 School: Invoices & Applications
for Payment for submission to the SBC
c) Invoices: Other Invoices for submission
to the SBC
5) Next Meeting(s): Wednesday
10/05/05 @ 7:30 PM
WESTON SCHOOL BUILDING
COMMITTEE, Wednesday, September 21, 2005, 7:30pm, Commission Room
at Town Hall
1)
Call Meeting to Order: Meeting was called to order/@7:40pm
2) Motion to call Executive Session: Discussion of
FT Fee Negotiations/done
3) Motion to end Executive Session and return to
regular meeting/done
4) Approve Minutes of Previous meetings:
Approve Meeting Minutes of 9/14/05/done
5) O&G Schedule / Progress / Budget Review:
a) HS: O&G not present
i) Issue Revised Schedule to complete
Areas “A & B”; occupied areas
ii) Issue of O&G Report # 15; CRG
overview
iii) Construction Completion & Punch
List in areas with C of O:
(1) Gym
(2) Cabinets for Area C & other
Classrooms
(3) Galleria
(4) PA / Clock System
(5) Tel. / Data
(6) Dumpster fencing
b) 3-5 School/O&G not present
i) Punch List Schedule Update
ii) Close-Out Status
iii) Landscaping; 3-5 & Campus
iv) Acoustical panels
c) Site: Schedule for work North of the MS/moving ahead
d) MS: Pool wall replacement/ completion date estimate/in progress
e) Hurlbutt: Installation Schedule for Construction of Rt. 57 crossing
- TBS/?
6) Any other business that may properly
come before the meeting:
7) Change Orders & Invoice Approval:
a) HS: Invoices & Applications for
Payment for submission to the SBC
b) 3-5 School: Invoices & Applications
for Payment for submission to the SBC
c) Invoices: Other Invoices for submission
to the SBC
8) Next Meeting(s): Wednesday
9/28/05 @ 7:30 PM
9) Adjournment: Meeting adjourned
@
PM
WESTON SCHOOL BUILDING
COMMITTEE, Wednesday, September 14, 2005, 7:30pm, Commission Room
at Town Hall
1)
Approve Minutes of Previous meetings: a)
Approve Meeting Minutes of 8/31/05 & 9/7/05
2) O&G Schedule / Progress / Budget Review:
a) 3-5 School:
(1) Punch List Schedule Update/to be
finished by the end of September
(2) Close-Out Status/moving along
b) HS: Construction Completion Schedule
Review
(1) Review completion of: Punch List,
etc.;/NOTE: Committee not satisfied with slippages in dates
(a) Gym
(b) Cabinets for Area C & other
Classrooms
(c) Galleria
(d) PA / Clock System
(e) Tel. / Data
(2) Issue Revised Schedule to complete
Areas “A & B”
(a) FF&E deliveries schedule update
(b) TS&E delivery & Installation
schedule update
c) Site: Schedule for work North of the MS/ coming along
d) MS: Pool wall replacement/ completion date estimate/coming along
e) Hurlbutt: Installation Schedule for Construction of Rt. 57 crossing
- TBS/?
3) Change Orders & Invoice Approval:
a) HS: Invoices & Applications for
Payment for submission to the SBC/done
b) 3-5 School: Invoices & Applications
for Payment for submission to the SBC/done
c) Invoices: Other Invoices for submission
to the SBC/some really old ones...done
4) Any other business that may properly
come before the meeting:
5) Next Meeting(s): Wednesday 9/21/05 @
7:30 PM
WESTON SCHOOL BUILDING
COMMITTEE, Wednesday, September 7, 2005, 7:30pm, Commission Room
at Town Hall
1) Approve Minutes of Previous meetings:
a) Approve Meeting Minutes of 8/31/05
2) O&G Schedule / Progress / Budget Review:
a) Review of Financial Report # 14, July
2005/done
b) 3-5 School: i) Construction completion schedule to
close out project; punch list, as-built, etc./going well
c) HS: i) Construction completion schedule
review/they have a plan
d) MS: i) Pool wall replacement/ completion date
9/??/05/?
3) Change Orders & Invoice Approval:
a) HS: Invoices & Applications for
Payment for submission to the SBC/?
b) 3-5 School: Invoices & Applications
for Payment for submission to the SBC/?
c) Invoices: Other Invoices for submission
to the SBC/?
4) Any other business that may properly
come before the meeting:
5) Next Meeting(s): Wednesday 9/14/05 @
7:30 PM
WESTON SCHOOL BUILDING
COMMITTEE, Wednesday, August 31, 2005, 7:30pm, Commission
Room at Town Hall
Approve Minutes of Previous meeting - Minutes of 8/24/05
New Items:
a) Revson Field sprinkler update/in
progress
b) Revson Field Silt Fencing Removal &
Additional Drainage/must leave silt fencing in place
O&G Schedule / Progress / Budget Review:
a) 3-5 School:
i) C of O update / SCHEDULE/will be
getting it momentarily (in time for school to open Tuesday!)
ii) Construction completion schedule
review/just about buttoned up
iii) FF&E deliveries schedule
update/almost 100%
iv) TS&E delivery & Installation
schedule update/same
b) HS:
i)
C of O update / SCHEDULE/Joe Payola (may not be spelled correctly;
retained by the Fire Marshall to inspect the fire alarm system and
other related matters) will approved the high school tomorrow.
ii)
Construction completion schedule review/working ongoing--still trying
to separate work areas from classroom space
iii) FF&E deliveries schedule update/?
iv) TS&E delivery & Installation
schedule update/?
c) Site: CL&P / SNET & Cablevision installation
update/Cablevision has not finished removing old wires from old pole.
d) MS: Pool
wall replacement/ completion date 9/1/05/DONE!!! What is more,
they found out why the pool wall has been "moving" for 20+ years...the
concrete floor/sill was never "tied down"
e) Hurlbutt: Installation Schedule for Construction of Rt. 57 crossing -
schedule/no problem
Change Orders & Invoice Approval: "About town"
left (9:45pm)
a) HS: Invoices & Applications for
Payment for submission to the SBC
b) 3-5 School: Invoices & Applications
for Payment for submission to the SBC
c) Invoices: Other Invoices for submission
to the SBC
Any other business that may properly come before the meeting:
Next Meeting(s): Wednesday 9/7/05 @ 7:30 PM
WESTON SCHOOL BUILDING
COMMITTEE, Wednesday, August 24, 2005, 7:30pm, Commission
Room at Town Hall
Approve Minutes of Previous
meetings: Minutes of 8/10/05 and 8/17/05/done
New Items:
a) Revson Field Irrigation/Town and school
project to share cost
b) Shawn’s Lawns Tree relocation cost
approval/to be done
O&G Schedule / Progress / Budget Review:
a) 3-5 School:
i) C of O update / SCHEDULE/looking good!
ii) Construction completion schedule
review/a few things left to do
iii) Rotunda Curved panels/they're up--but
for weather protection only.
iv) FF&E deliveries schedule
update/on-going
v) TS&E delivery & Installation
schedule update/on-going
b) HS:
i) C of O update / SCHEDULE/only Fire
Marshal remains
ii) Construction completion schedule
review/moving along (on those parts expected to be ready this Fall)
iii) Stone wall re-pricing; Stecks/will do
beginning tomorrow
iv) Report on Cabinetry/what more can one
say?
v) FF&E deliveries schedule
update/on-going
vi) TS&E delivery & Installation
schedule update/on-going
c) Site:
i) CL&P installation time / update
(SNET & Cablevision)/in the works
ii) Municipal water system - Schedule
update/ok and almost formally approved
d) MS: Pool wall replacement/ completion date 9/1/05/moving along
e) Hurlbutt: Installation
Schedule for Construction of Rt. 57 crossing – 8/25/05/some big pipes
not yet done--but another crossing project revised downward by DOT
Change Orders & Invoice Approval: "About Town" left at
this point
a) HS: Invoices & Applications for
Payment for submission to the SBC
b) 3-5 School: Invoices & Applications
for Payment for submission to the SBC
c) Invoices: Other Invoices for submission
to the SBC
Any other business that may properly come before the meeting:
Next Meeting(s): Wednesday 8/31/05 @ 7:30 PM
WESTON SCHOOL BUILDING
COMMITTEE, Wednesday, August 17, 2005, 7:30pm, Commission Room at Town Hall
Approve Minutes of 8/10/05
New Items:
O&G Schedule / Progress / Budget Review:
a) 3-5 School:
i) C of O update / SCHEDULE /on schedule
ii) Construction completion schedule review/"
iii) Rotunda Curved panels/this will be done correctly
as indicated by design
iv) FF&E deliveries schedule update/OK
v) TS&E delivery & Installation schedule
update/OK
b) HS:
i)
C of O update / SCHEDULE/partial completion of several areas including
science wing, gallaria, cafeteria, gym (not to be finished with
bleachers) plus some other rooms.
ii) Construction completion schedule
review/working to get it done by the scheduled finishing date
iii) Stone wall re-pricing; Stecks/some redesign
suggested by SBC after walking the property today
iv) Report on Cabinetry/F-T read a letter indicating
that installation was not as envisioned
v) Slate Installation/on-going
vi) Greenhouse cabinet alternate/? (we left at 10pm)
vii) FF&E deliveries schedule update/going OK (discussed
earlier under 3-4-5)
viii)TS&E delivery & Installation schedule
update/" "
c) Site:
i) CL&P installation time / update
(SNET & Cablevision)/not to quick
ii) Municipal water system - Schedule
update/should be OK
d) MS: Pool wall replacement/ completion date 9/1/05/we left before
this item...?
e) Hurlbutt: Installation Schedule for Construction of Rt. 57 crossing –
8/25/05
Change Orders & Invoice Approval: /?
for the rest.
a) HS: Invoices & Applications for
Payment for submission to the SBC
b) 3-5 School: Invoices & Applications
for Payment for submission to the SBC
c) Invoices: Other Invoices for submission
to the SBC
Any other business that may properly come before the
meeting:
Next Meeting(s): Wednesday 8/24/05 @ 7:30 PM
WESTON SCHOOL BUILDING
COMMITTEE, Wednesday, August 10, 2005, 7:30pm, Commission
Room at Town Hall
Approve Minutes of Previous meetings: 7/27/05
& 8/3/05/done
New Items:
O&G Schedule / Progress / Budget Review: discussion of where
we stand in re: budget (still OK)
a) 3-5 School:
i) C of O update / SCHEDULE/progressing
ii) Construction completion schedule
review/some odds and ends to be done
iii) Rotunda Curved panels/next week final
decision - but indications are to go with on site solution
iv) Water proof membrane for gallery
floor/maybe
v) FF&E deliveries schedule
update/moving along
vi) TS&E delivery & Installation
schedule update/moving along
b) HS:
i) C of O update / SCHEDULE/looking good
for advanced parts
ii) Construction completion schedule
review/some ahead, some behind
iii) Stone wall re-pricing; Stecks/looks
funny, but will be ameleorated
iv) Greenhouse cabinet alternate/next week
- there is a solution!
v) FF&E deliveries schedule
update/on-going
vi) TS&E delivery & Installation
schedule update/in progress
c) Site:
i) CL&P installation time / update
(SNET & Cablevision)/?
ii) Municipal water system - Schedule
update/final bit still due
d) MS: Pool wall replacement schedule (start date) / completion
date 9/1/05 - ?
e) Zenon: ?
f) Hurlbutt:?
i) Installation Schedule for Construction
of Rt. 57 crossing – 8/25/05 - ?
Change Orders & Invoice Approval:
a) HS: Invoices & Applications for
Payment for submission to the SBC
b) 3-5 School: Invoices & Applications
for Payment for submission to the SBC
c) Invoices: Other Invoices for submission
to the SBC
5) Any other business that may properly
come before the meeting:
6) Next Meeting(s): Wednesday 8/17/05 @
7:30 PM
WESTON SCHOOL BUILDING
COMMITTEE, Wednesday, August 3, 2005, 7:30pm, Commission Room
at Town Hall
Approve Minutes of Previous meetings: Minutes of 7/27/05
O&G Schedule / Progress / Budget Review:
a) 3-5 School:
i) C of O
update / SCHEDULE/on schedule to open on time
ii) Construction completion schedule
review/reviewed in detail
iii) FF&E deliveries schedule update/next
week
iv) TS&E delivery & Installation
schedule update/on-going
b) HS:
i) C of O
update / SCHEDULE/Fire inspections, etc. scheduled - boilers,
etc. to be OK'd by State of CT; WWHD checking kitchen
ii) Construction completion schedule
review/detailed, day by day plan reviewed
iii) HS Detail Schedule & Plan by
Area(s)/shown above
iv) 9/6 occupancy / fire exits plan/ready to
be OK'd
v) FF&E deliveries schedule update/?
vi) TS&E delivery & Installation
schedule update/?
c) Site:
i) CL&P
installation time / update (SNET & Cablevision)/progressing
ii) Municipal water system - Schedule
update/one more OK needed
d) MS: Pool wall
replacement schedule (start date) / completion date 9/1/05/we think, in
progress
e) Zenon:
i) Punch List
completion review & acceptance by FT/done?
ii) DEP conditional certification/in the mail?
f) Hurlbutt: Installation
Schedule for Construction of Rt. 57 crossing – 8/25/05/looking good
Change Orders & Invoice Approval: "About Town" left at this
point
a) HS:
Invoices & Applications for Payment for submission to the SBC
b) 3-5 School: Invoices & Applications for
Payment for submission to the SBC
c) Invoices: Other Invoices for submission to
the SBC
Any other business that may properly come before the meeting:
Next Meeting(s): Wednesday 8/10/05 @ 7:30 PM
WESTON SCHOOL BUILDING
COMMITTEE,
Wednesday, July 27, 2005, 7:30pm, Commission Room at Town Hall
Approve Minutes of Previous
meetings:
Minutes of 7/20/05/OK
New Items: Discussion Re:
O&G Monthly Progress Report # 12
O&G Schedule / Progress /
Budget
Review:
a) 3-5 School:
i) C of O update /
SCHEDULE/depends on how some inspections turn out
ii) Construction completion
schedule
review/new schedule format presented
iii) FF&E deliveries
schedule
update/on-going
iv) TS&E delivery &
Installation
schedule update/on-going - safety concerns related to first floor
locations
b) HS:
i) HS Detail
Schedule &
Plan by Area(s)/altered to work with actual
progress of construction
ii) 9/6 occupancy / fire exits
plan/plan in place - need OK from Fire
establishment
iii) C of O update / SCHEDULE /will
be area by area
iv) Construction completion
schedule
review/see above
v) Daily Staff Records/being
kept
c) Site:
i) CL&P
installation
time / update (SNET & Cablevision)/soon
ii) Municipal water system -
Schedule
update/soon
d) MS: Pool wall replacement
schedule
(start date) / completion date 9/1/05/?
e) Zenon:
i) Punch List
completion
review & acceptance by FT/close
ii) DEP conditional
certification/close
f) Hurlbutt:
i) Status update of
parking
lot light installation, Completion date?/lights
are working at Hurlbutt!!!
ii) Installation Schedule for
Construction
of Rt. 57 crossing/soon
Change Orders & Invoice
Approval: "About Town" left at this point
a) HS: Invoices &
Applications
for Payment for submission to the SBC
b) 3-5 School: Invoices &
Applications
for Payment for submission to the SBC
c) Invoices: Other Invoices for
submission to the SBC
Any other business that may
properly
come before the meeting:
Next Meeting(s): Wednesday
8/3/05 @ 7:30 PM
WESTON SCHOOL BUILDING
COMMITTEE,
July
20, 2005, 7:30pm, Commission Room at Town Hall. NOTE:
"About
Town" left the meeting to record the decisions made at the DTC Caucus
and
then returned to SBC - don't know what happened at SBC in some cases
because
we were out of the room (as far as the Caucus goes, no opposition for
any
Board or Commission-picked very impressive candidates to fill slots
being
vacated.) P&Z nominee a lawyer.
Approve
Minutes of Previous
meetings:
Minutes of 7/6/05 & 7/13/05/done
New Items: O&G Monthly
Progress Report # 12/project in good shape financially, so it seems as
of this report.
O&G Schedule / Progress /
Budget
Review:
a) 3-5 School:
i) C of O update /
SCHEDULE/dates
for all needed OK's set
ii) Construction completion
schedule
review/too much dirt inside
iii) FF&E deliveries
schedule/?
iv) TS&E delivery &
Installation
schedule/?
b) HS:
i) Anticipated date
for
presentation of HS Detail Schedule & Plan by Area/in two
weeks?
ii) Anticipated date for
enlarged
plan for 9/6 occupancy / fire exits/pretty close
iii) C of O update /
SCHEDULE/will
be achieved in time for parts completed
iv) Daily Staff
Records/questions
about procedure
c) Site:
i) CL&P
installation
time / update (SNET & Cablevision)/Florida hurricane slowing it up,
but it will be done
ii) Municipal water system -
Schedule
update/on schedule for August 1
d) MS: Pool wall
replacement schedule
/ completion/?
e) Zenon:
i) Punch List
completion
date/?
ii) DEP conditional
certification/need
McDonald-Sharpe and DEP moving ahead on this
f) Hurlbutt:
i) Status update of
parking
lot light installation, start 6/22/?
ii) Installation Schedule for
Construction
of Rt. 57 crossing/?
Executive Session: Contract
related
issues/we left at this point
Change Orders & Invoice
Approval:
a) HS: Invoices &
Applications
for Payment for submission to the SBC
b) 3-5 School: Invoices &
Applications
for Payment for submission to the SBC
c) Invoices: Other Invoices for
submission to the SBC
Any other business that may
properly
come before the meeting:
Next Meeting(s): Wednesday
7/27/05 @ 7:30 PM
WESTON SCHOOL BUILDING
COMMITTEE,
Wednesday,
July 13, 2005, 7:30pm, Commission Room at Town Hall
Approve Minutes of Previous
meetings:
Minutes of 7/6/05
New Items:
a) Presentation of HS
Schedule/no
O&G report
b) Extra work: proceed
authorization;
HS/OK two trades - need more info from O&G before moving ahead any
further
O&G Schedule / Progress /
Budget
Review:
a)
3-5
School:
i) Monthly Progress
Report
# 12/on track!
ii) C of O update /
SCHEDULE/addition
notes on future reports--Town on the job, proceeding
b) HS:
i) Monthly Progress
Report
# 12/no O&G report
ii) C of O update / SCHEDULE/
no
O&G report
c) Site:
i) CL&P / CRS
installation
time / update/working on it
ii) Municipal water system -
Schedule
update/working on it
d) MS: Pool wall replacement
bid/OK
e) Zenon: Punch List
completion
date/almost done! (a few screws need fixing)
f) Hurlbutt: Status update
of parking lot light installation, start 6/22/?
Change Orders & Invoice
Approval:
we left at this point...
a) HS: as submitted to
the
SBC
b) 3-5 School: as submitted to
the
SBC
c) Invoices: as submitted to the
SBC
Any other business that may
properly
come before the meeting:
Next Meeting(s): Wednesday
7/20/05 @ 7:30 PM
WESTON SCHOOL BUILDING
COMMITTEE,
Wednesday,
July 6, 2005, 7:30pm, Commission Room at Town Hall.
Approve Minutes of 6/22/05/ok
New Items:
a) Review summer
schedule
of meetings for SBC/will be meeting every week from now on until
schools
are opened
b) Use of soccer field by men’s
soccer league/may use soccer field and park in high school parking lot
c) FF&E delivery and
installation
responsibility BOE/as many as five or six steps on a schedule with
school
staff playing a role in receipt of deliveries
d) Metal Panel Color CO
discussion/report
reviewing the status of this point of possible conflict--decision that
contractor should proceed, and arrangement will be worked out to
everyone's
agreement
e) C&H: CO for cable repair
& upgrade/?
f) Extra work: proceed
authorization;
HS/next week final decision (will do it if justified)
g) Construction in space C5; new
program/space will stay open and be cleaned up
O&G Schedule / Progress /
Budget
Review:
a) 3-5 School:
i) Monthly Progress
Report
# 12 O&G/ready by end of week for next meeting
ii) C of O update:
O&G
reports progress on some items
iii) Metal Panel: installation
schedule
- update O&G (going well)
iv) Scheduling update/ O&G
reports
due next week
v)
b) HS:
i) Monthly Progress
Report
# 12 O&G/next week
ii) Schedule update: metal
panels,
electrical/?
iii) HS Stone Wall –
installation
status - O&G reports wall just begun
iv) C of O update/?
c) Site: note - Town of
Weston
must provide assistance for prompt completion of both these items.
i) CL&P CRS
installation
time
ii) Municipal water system
d) MS: Pool wall
replacement,
bids - will decide next weeks on contractor and then proceed to do the
work
e) Zenon: Punch List completion
date/about ready
f) Hurlbutt: Status update
of parking lot light installation, start 6/22/we were out of the room
when
this was discussed
Change Orders & Invoice
Approval:
a) HS: as submitted to
the
SBC O&G
b) 3-5 School: as submitted to
the
SBC O&G
c) Invoices: as submitted to the
SBC
Any other business that may
properly
come before the meeting:
Next Meeting(s): Wednesday
7/20/05 @ 7:30 PM/NEXT MEETING JULY 13, 2005 at 7:30pm,
Commission
Room
WESTON SCHOOL BUILDING
COMMITTEE,
Wednesday, June 22, 2005, 7:30pm, Commission Room at Town Hall
1) Approve Minutes of Previous
meeting:
Approve Meeting Minutes of 6/08/05/done
2) New Items:
a) Municipal water
system/in
the last stages of completion for oppening of schools
b) Site security; who’s
responsibility/schools
will continue this
c) HS Stone wall
review/approval/just
about OK'd
d) FF&E delivery and
installation
responsibility/need to name a responsible party to check deliveries
3) O&G Schedule / Progress /
Budget
Review: please ote that "About Town" did not have a copy of
report
#11, thus the "?" notes
a) 3-5 School:
i) Monthly Progress
Report
# 11/going very well
ii) C of O update, fire pump
test/passed!
iii) Metal Panel installation
schedule
update/a bit behind, but will be done
iv) Scheduling update/?
b) HS:
i) Monthly Progress
Report
# 11/lots of things going on at once
ii) Schedule update/?
c) Site: CL&P CRS submission
&
installation time/should be ok
d) MS: Pool wall
replacement,
O&G bid/full report next meeting
e) Zenon: Punch List completion
date/done?
f) Hurlbutt: Status update of
parking
lot light installation, start 6/22/?
4) Change Orders & Invoice
Approval:
we left at this point
a) HS; as submitted to
the
SBC
b) 3-5 School; as submitted to
the
SBC
c) Invoices; as submitted to the
SBC
5) Any other business that may
properly
come before the meeting:
6) Next Meeting(s):
Wednesday
7/6/05 @ 7:30 PM
WESTON SCHOOL BUILDING
COMMITTEE,
Wednesday,
June 7, 2005 - Special - begins at 7pm, Commission Room at Town Hall
NOTE: Item added to agenda
re: Review of "T, S&E" bids/ Peter Oliver presented bids,
choices
SBC OK'd them.
Motion to call Executive Session
(Discussion of F-T claim proposal)/no action taken after
Approve Minutes of Previous
meetings:
5/25/05/done
New Items:
a) Discussion RE: FT
Architectural
Service Reduction proposal at the MS / MS Auditorium/not discussed
b) Site security and how it is
invoiced/reaffirmation
of previous protocol (we hire, pay, forward charge to O&G)
O&G Schedule / Progress /
Review:
a) 3-5 School:
i) C of O status at
new
3-5 School/town
building inspector lays out requirements for C.O. (or partial C.O.)
ii) Metal Panel installation
schedule
update/some amount of time delay, but will be done on time for Fall term
iii) Skylight guard rails/no
issue
b) HS: FF&E bid
revision for
approval/good solution to installation of TV monitors - flat screen
makes
it unnecessary to hang things from the ceilings, etc.
c) Site:
i) Parks & Rec.
Tennis
Court bid review & approval/looking good to have additional funding
from the community for easier surface in time to fit into SBC schedule
ii) Maki/Levi trees,
authorization
to proceed with Weston Gardens/?
d) MS:
i) Pool wall
replacement,
O&G bid status/still not satisfied that this "fix" will actually
solve
the 30 yr problem
ii) Power Options, MS North;
BB
proposal; move poles, CL&P response/? we think we heard that
Landscape Architect has this under control (without going to most
expensive
alternative discussed by Construction Manager
e) Zenon: Punch List completion
date/almost
there
f) Hurlbutt: Status update
of parking lot light installation, start 6/22/on hold until School is
out
for summer
Change Orders & Invoice
Approval:
we left
a) HS; as submitted to
the
SBC
b) 3-5 School; as submitted to
the
SBC
c) Invoices; as submitted to the
SBC
7) Any other business that may
properly
come before the meeting: (not allowed at a Special Meeting)
8) Next Meeting(s):
Wednesday
6/22/05 @ 7:30 PM
WESTON
SCHOOL BUILDING
COMMITTEE,
Wednesday,
May 25, 2005, 7:30pm, Commission Room at Town Hall
Approve Minutes of Previous
meetings:
Minutes of 5/11/05/OK'd
New Items:
a) Update-Tree replacement @ Maki
/ Revson/to be done NOW
b) Discussion RE: FT Architectural
Service Reduction proposal at the MS / MS Auditorium/ok
i) MS / Aud.
Construction
start requirements dates by State of CT/no problem
c) Update: Play Area at the 3-5
School
/ drainage/Building Committee voted to pay for the drainage (THANKS to
PTO for playscape donation!)
d) Hanging TV questions/ok to
figure
out how to do it (F-T and O&G)
e) Status of Marker / Interactive
/ Tack Bd’s
f) Stone Wall site List or Sample
Wall Const. update/Committee will pick out the kind of wall they are
looking
for and tell Steck's about it
g) Silverstein Property line
items,
berm, trees, erosion, fence repair/ok on berm
h) HS Media Library Shelving (LF
= 50% short)/F-T will contact librarian (I think they said they would
do
this--measuring shelf space is part of architect's job, and there is
enough
shelf space--but if not, other shelves can be procured.
i) MS, EDO-49 State Required
approval
by SBC for work by the BOE/Director of Bldgs and Grounds Mr. Clarke
received
voted approvals on three projects.
O&G
Schedule / Progress /
Review:
a) 3-5 School:
i) Metal Panel
installation
schedule, staff / material/only back pieces left--should be ready in
time
for C.O. if not sooner
ii) Staffing for Losito
Electric/on
the job
iii) Guard Rail at Skylight,
straight
or curved/?
iv) O&G Landscape bids for
the
3-5 School Court Yard/bid ok'd and work to be done
v) Furniture bid approval for
ordering/ok
b) HS:
i) Locker room
abuse-resistant/discussion
ii) Nettleton replacement
(bankrupt)/on
the job
iii) P-1, Louis Poulsen, fixture
status/dicsussion
c) Site:
i) Parks & Rec.
Tennis
Court bid approval/will review it, but ok to add needed funds to get
the
job done in time for school - discussion of added feature to surface
(see
Board of Selectmen's notes May 19)
ii) Tree Installation update for
Levi / Maki/se above
d) MS:
i) Pool Backwash
schedule/?
ii) Pool wall replacement,
status (Marnicki will have bid drawings by 5/26)/?
iii) Power Options for North of
MS; BB proposal; Poles must be moved/cost evaluation of underground v.
moving poles - has to be done
e) Zenon:
i) Last septic
connection
from MS/done (?)
ii) Punch List completion
date/still
some items hanging
f) Hurlbutt:
i) Status update of
parking
lot light installation/we left
Change
Orders & Invoice
Approval:
a) HS as submitted to the SBC
b) 3-5 School as submitted to the
SBC
c) Invoices as submitted to the
SBC CRG
Any
other business that may
properly
come before the meeting:
Next
Meeting(s):
Wednesday
6/8/05 @ 7:30 PM All
WESTON
SCHOOL BUILDING
COMMITTEE,
Wednesday,
May 11, 2005, 7:30pm, Commission Room at Town Hall
1) Approve Minutes of Previous
meetings:
a) Meeting Minutes of 4/27/05 approval/done
2) New Items:
a) Presentation &
Discussion
of O&G Revised Schedule/presented and discussed - will continue to
be discussed
b) Tree replacement @ Maki /
Revson/to
be done (we think three big fir trees and some vegetation or another
tree
in lieu of the vegetation [there is sod there now])
c) FT letter regarding
architectural
service reduction @ the MS / MS Aud./to be discussed next week after
some
more careful review of detail
d) Play Area at the 3-5
School/need
engineer to report on possible drainage required (?) - MacDonald-Sharp
to be asked for immediate recommendation;
e) Stone Wall site List/Town of
Weston has no answer yet (June 1 deadline);
f) O&G Landscape bids for
the
3-5 School/will handle this as a small project
g) Silverstein Property line
items/playground
may impinge on previous planting, etc.
h) O&G Schedule update/?
3) O&G Schedule / Progress /
Review:
a) 3-5 School:
i)
Metal Panel Installation schedule/behind (our opinion)
b) HS: i) Locker room
abuse-resistant
GWB/revision to spec for damage-resistant ceiling because only 8ft high
c) Site: ?
d) MS:
i) Pool Backwash
schedule/it
was expressed that this item needs doing!
ii) Power Options for North of
MS/may
be a problem unless landscape architect comes up with something creative
e) Zenon:?
i) Last septic
connection
ii) Punch List completion date
f) Hurlbutt:
i) Installation of parking lot
lighting/parking
lot lightinh poles in (?) - not yet working
4) Change Orders & Invoice
Approval:
"About Town" left
a) HS as submitted to
the
SBC
b) 3-5 School as submitted to
the
SBC
c) Invoices as submitted to the
SBC
5) Any other business that may
properly
come before the meeting:
6) Next Meeting(s):
Wednesday
5/25/05 @ 7:30 PM
WESTON
SCHOOL BUILDING
COMMITTEE,
Wednesday, May 4, 2005, 7:30pm, Commission Room
AGENDA
Call the Meeting to order;
motion to go into executive session (executive session with architect
on
Contract issues); adjournment (after coming out of executive
session).
SPECIAL WESTON SCHOOL BUILDING
COMMITTEE, April 27, 2005, 7:30pm, Commission Room at Town Hall
AGENDA
1) Approve Minutes of previous
meetings:
Meeting Minutes of 4/12/05 approval/done
2) New Items:
a) Discussion of
O&G
March Cost Report/done
b) Discussion of O&G Revised
Schedule/some questions, done
c) Power Options for North Power
Service Feeder to the Middle School/least expensive solution selected
3) O&G Schedule / Progress /
Review:
a) 3-5 School
i) Metal Panel
Installation/on
going
ii) Other items by
O&G/discussion
b) High School
i) Metal Panel
Installation/on
going
ii) Other Items by
O&G/discussion
c) Site/brief report
d) Middle School Pool Backwash
Schedule/?
e) Zenon - on going
i) Last Septic
Connection
ii) Punch List Completion
f) Installation of Hurlbutt
Parking
Lot Lighting Schedule/behind schedule but to be completed in week or two
4) Change Orders & Invoice
Approval:
discussion
a) High School as
required
b) 3-5 School as required
c) Invoices/we left at this point
5) Any other business that may
properly
come before the meeting:
6) Next Meetings:
a) Wednesday
5/4/05
@ 7:30pm, Executive Session
b) Wednesday 5/11/05
@ 7:30pm, Regular Scheduled Meeting
SPECIAL WESTON SCHOOL BUILDING
COMMITTEE, April 12, 2005, 7:30pm, Weston Public Library
AGENDA
Approve Minutes: Meeting
Minutes
of 3/30/05/done
New Items:
a) Presentation of
O&G
March Cost Report/not done
b) Commemorative Plaques
for
Intermediate School and High School/discussed
c) Review of Pool Wall
Proposal/Marneke
proposal $3,200 for contract drawings
d) Power options for north of
the
Middle School/discussions to continue (i.e. alternatives of underground
v. moving poles)
O&G Schedule / Progress /
Review:
O&G not present at this special meeting - Owner's Rep reported.
a) 3-5 School
i) Metal Panel
Installation/on-going
ii) Waterproof membrane
status/viability/on-going
b) High School
i) Metal Panel
Installation/on-going
ii) Waterproof membrane
status/viability/on-going
c) Site/discussion of planting
plan
but no decisions under neighbors review it with Blades&Goven;
discussion of vandalism
d) Middle School Pool Backwash
schedule/?
e) Zenon
i) Last septic
connection/in
progress
ii) Punch List completion/in
progress
f) Installation of Hurlbutt,
parking
lot lighting schedule/to be done over vacation.
Change Orders & Invoice
Approval:
a) High School and 3-5
School
as required/brick, fencing and fixtures dicussed.
b) Invoices/we left @9:40pm,
before
the end of the meeting.
6) Any other business that may
properly
come before the meeting:
7) Next Meetings: Tuesday
4/19/05
@ 7:00pm, Special Executive Session; Regularly scheduled meeting:
Wednesday 4/27/05 @ 7:30pm
WESTON
SCHOOL BUILDING
COMMITTEE,
Wednesday,
March 30, 2005, 7:30pm, Commission Room at Town Hall
Approve Minutes of 3/16/05
Meeting/done
New Items:
a) Review of O&G
February
Cost Report/some further adjustments to be made
b) Use of school track between
3:30
and 5:30pm for practice/?
c) Blades & Goven additional
services proposal for tree donation/OK'd
d) Tackboard bids/accepted
e) Culverts Rte. 57 (2)/one OK'd
by DEP, the other needs redesign for major improvement the State of CT
wants us to do of their road!
f) Revson field drainage/frozen
conditions caused overflow during torrential rains recently
O&G Schedule / Progress /
Review:
a) High School &
3-5
School
i) Metal panel
installation
(HS & 3-5 School)/to be done (finished) in foreseeable future
ii) Waterproof membrane
status/viability
(HS & 3-5 School)/?
b) 3-5 School Update - Tackboard
review/decision
made to go ahead with wrap, etc.
c) High School Update/going well
and new schedule has music and art wing to be finished by December -
but
perhaps sooner!
d) Site/neighbors of 3-4-5
present
to ask about plantings - se above, Blades and Goven contract
e) Middle School pool backwash
and
pool wall (design, cost, schedule, const.)/Richard Marneke on the case
f) Zenon - last items to be
checked
i) Last septic
connection
ii) Punchlist completion
g) Installation of Hurlbutt
parking
lot lighting/to be done during Spring vacation #2
Change Orders & Invoice
Approval:
done (but we left in the middle)
a) High School as
required
b) 3-5 School as required
c) Invoices
Any other business that may
properly
come before the meeting: Next Meeting: Wednesday 4/13/05 @ 7:30
PM
WESTON SCHOOL BUILDING
COMMITTEE,
Wednesday, March 16, 2005, 7:30pm, Commission Room at Town Hall
REVISED
AGENDA
1) Approve Minutes of Previous
meetings:
Meeting Minutes of 3/2/05 approval/done
2) New Items:
a) Cost review of
Referendum
Question #1/$650-$750k to come from WMS work (in Item#1--NOT #3, the
Auditorium)
for high school to get to 10% contingency
b) Use of school property during
the spring break and summer/revision to need, no final word on track
use
by teams yet
c) Review date, schedule,
format,
procedure, locations and announcement for “Spring Site Walk”/"virtual"
walk to be done(not safe or feasible at this point any other way)
3) O&G Schedule / Progress /
Review:
a) Finishes: walls /
floors/sub-committee
worked on this during the early part of the meeting
b) 3-5 School
i) Waterproof
membrane status/viability
(HS & 3-5 School)/to be redone where needed
ii) Lighting approvals/(?)
c) High School/some not so
terrific,
in Committee's opinion
d) Site
i) Security/loose
fence
issue resolved
ii) Fire Department meeting /
request
update/in progress and looking to be worked out to everyone's
satisfaction
(we hope)
e) Middle School Pool Backwash:
cost,
schedule/WWHD on top of this now
f) Zenon last septic
connection/soon
all frozen situations will be thawed (we hope)
g) Zenon punch list review/in
progress
(close to being OK'd!)
4) Change Orders & Invoice
Approval:
a) High School as
required/done
b) 3-5 School as required/done
c) Invoices; Applications for
Payment/we
left before this item was finished
5) Any other business that may
properly
come before the meeting: resident in the audience who may have had a
question
here, but as noted above, we left - FORUM reporter had left previously
6) Next Meeting: Wednesday
3/30/05 @ 7:30 PM
WESTON SCHOOL BUILDING
COMMITTEE,
Wednesday,
March 2, 2005, 7:30pm, Commission Room at Town Hall
REVISED
AGENDA:
The
meeting will begin at
7:00pm
with a motion to move the meeting into Executive Session for about 45
minutes/discussion
of pending lawsuit.
1)
Approve Minutes of Previous
meetings:
Meeting Minutes of 1/26/05 & 2/15/05/OK
2) New Items:
a) High School
schedule
revision/acceleration for HS fall semester/all but what can be
encapsulated
and kept away from students and teachers will be completed by September
2005 ("fast track" designed by staff/administration/O&G, etc.)
b) HS Football Field Access this
Spring/discussion about potential lawsuits re: accidents, damage, etc.
- more to come before a decision is made to permit early access to new
track.
3) O&G Monthly Progress Report
#8
& TOW Soft Cost Review:
a) O&G Report
review/getting
closer to Town expectation.
b) SBC / TOW Soft Cost Review -
room for movement among projects, with permission of appropriate body
(Town
Meeting).
4) O&G Schedule / Progress /
Review:
F,F & E plan to go to State Department of Education Facilities Unit
- need Board of Education formal vote and SBC OK/School Building
Committee
voted to authorize Chairman to act in their behalf to sign off on
FF&E
Plan.
a) 3-5 School/weather
tight
(roof, windows and now interior walls done)
b) High School/accent colors
still
not determined
c) Site/high school stone wall
to
be undertaken outside the project.
d) Middle School Pool Backwash
cost
and schedule/on hold (weather)
e) Zenon last septic
connection/on
hold (weather)
f) Installation of Hurlbutt,
parking
lot lighting (on hold (weather?)
5) Any other business that may
properly
come before the meeting/bills reviewed - next meeting: Wednesday
3/16/05 @ 7:30 PM
WESTON
SCHOOL BUILDING
COMMITTEE,
Special Meeting Tuesday, February 15, 2005 at 7:30pm, Commission Room
at
Town Hall
New
items:
a) Schedule for High
School
Asbestos abatement/to be done sooner, in sections.
b) Revised Schedule for High
School
as requested by Bd. of Ed./working on it - Media Center and
administration
area to be attempted to be done sooner.
c) Use of football field during
the spring training period/to be negotiated with O&G, Town -
presentation
made by W.H.S. Principal of two alternatives, as proposed by Athletic
Director
(plus detail on what process would be to assure student safety plus no
damage to work and assuring no contact with workers [thus, no
interruption
of work])
d) Landscape bid; “Memorial
Trees”
and “Memory Patio”/going out, coordination taking place with
interested
parties.
e) Middle School fire tank &
pool dry hydrant connection for fire pumper/still more discussion to
come
from WVFD.
f) Review & approve of
Oliver’s
IT Proposal/OK'd to go.
O&G
Monthly Progress Report
#8
& TOW Soft Costs Review:
a) O&G Report
review/most
recent report not completed yet (available at next meeting).
b) SBC / TOW Soft Costs
Review/still
fluid - as project moves into final phase, adjustment and fine tuning
are
made.
Pending Approvals: a)
MS
Pool backwash approval status/WWHD OK'd it over the 'phone--we think
that
is what we heard.
O&G
Schedule / Progress
Review:
a) TOW vs. O&G
schedule
dates/extra column added to show original dates and new, closer-in
times
(project moving more quickly than official schedule);
b) 3-5 School/going well!
(NOTE: School Building Committee to recommend an April [after
holidays]
"Community [Visit] Day" to escort interested Westonites through the
project
on School Road, in much the same way the Fields were viewed last Fall.)
c) HS/finding some and expecting
more things (not on the drawings) in old sections, and since these
items
(i.e. existing fixtures, electrical connections) not included in
drawings,
change orders needed to install new design treatment (i.e. dropped
ceiling).
d) Site
i) MS Pool Backwash,
status;
cost; leachfield/see above "Pending Approvals."
ii) Zenon last septic
connection/working
great--no noise, no odor - one more connection to go and the whole
campus
will be on line.
e) Installation of Hurlbutt,
parking
lot lighting/?
Change Orders: (OKd)
a) High School as
required
b) 3-5 School as required
c) Others as required
Approve Minutes of previous
meetings:
a) Meeting Minutes of 1/26/05 and 2/2/05/one set approved.
Bd. of Ed. Presentation of
Reallocation
of School Funds/sounds like a big deal, but it was a presentation
of
work to be completed, already begun, by staff to modify and update some
rooms at WMS using "in-house" supervision.
Invoice Approvals -
Consultants
& others/we left before previous topic completed (10:30pm or so)
Next
Meeting:
Wednesday
3/2/05 @ 7:30 PM
WESTON SCHOOL BUILDING COMMITTEE,
Feb. 2, 2005, 7:30pm, Commission Room at Town Hall
Approval of minutes: 1-19
& 1-26/1-19 OK'd
O&G Monthly Progress Report
#7 & Town of Weston Soft Cost review:
- O&G Report
review/recommendation
that the School Building Committee meet every other week for the next
month
or so...
- SBC/Town of Weston Soft
Cost
review/at
next meeting O&G and Town of Weston soft cost assessment will be
reconciled
Pending Approvals:
- CL&P Easement &
2/6-2-12, installation
schedule/Easesment filed, CL&P out there doing the work right now!
- Middle School pool
backwash
approval
status/no action from WWHD yet, but they are working on it
O&G Schedule/ProgressReview:
- Town v. O&G Schedule
dates/this
is being discussed with both parties to reconcile dates by est. end of
February
- 3-5 school/going great
guns--looks great!
- high school/as mentioned
in
previous
meeting (below), work moving along in counter-clockwise direction--next
up is media center and library, next week (?)
- site
- Middle School pool
backwash,
status;
cost; leachfield; frozen waste pipe/WWHD submission in limbo, frozen
pipe
unfreezes (we are not sure this is the unfrozen pipe--could be on H.S.)
- Zenon last septic
connection/very close...
- Hurlbutt parking lot
lighting/after
all, this will not be a significant expense because it was found that
there
are conduits already in place--just need new wire (?)
Invoice approvals:
consultants
and others if applicable/meetings (with Owner's Rep) will be held
before
next Committee meeting with those doing the work for a number of
projects, including site work drawings for plantings, replacement of
special
trees and outdoor furniture.
["About Town" left at this point
in the meeting.]
Change Orders:
- high school as required
- 3-5 as required
- others as required
Any other business/Speak Up will
be
attended by SBC; (next meeting 2-16-05)
WESTON SCHOOL BUILDING COMMITTEE,
Jan. 26, 2005, 7:30pm, Commission Room at Town Hall
1) Approve Minutes of previous
meetings:
Meeting 1/19/05
2) O&G Monthly Progress Report
#7 & Town of Weston Soft Cost Review:
a) O&G Report
review/done
b) SBC / TOW Soft Cost
Review/first
draft shows overall positive picture
3) Pending Approvals:
a) CL&P Easement
&
Installation/short-staffed CL&P doing their best to get both new
3-4-5
and W.H.S., etc. connected to permanent power ASAP
b) MS Pool backwash
approval/pending--redesign
required, and that is underway.
4) O&G Schedule / Progress
Review:
a) 3-5 School/going
well,
academic wing(s) to be finished first
b) High School/looking great
(work
progressing in a counter-clockwise direction, starting where the first
shovel hit the ground in Feb. '04)
c) Site/?
i) Middle School
pool backwash
status, cost; leachfield/(see above)
ii) Zenon last septic
connection/"
d) Hurlbutt, parking lot
lighting/?
5) Invoice Approvals:
Consultants
& others if applicable
6) Change Orders:
a) High School as
required
b) 3-5 School as required
c) Others as required
7) Any other business that may
properly
come before the meeting: discussion of latest monthly report, and
inquiry
as to whether "worst case" estimates should trigger changes in final
delivery
of completion--sooner the better (and cheaper)? NOTE:
Please
remember, this Web report is only "About Town's" opinion of what was
discussed.
8) Next Meeting:
Wednesday
2/02/05 @ 7:30 PM
WESTON SCHOOL BUILDING COMMITTEE,
Wednesday, January 19, 2005, 6:30pm, Commission Room at Town Hall
1) Call Meeting to Order:
(About Town did not attend this meeting)
2) Motion to move meeting into
executive
session:
3) Executive Session
4) Approve Minutes of previous
meetings:
Meeting 1/12/05
5) O&G Monthly Schedule Review:
a) 3-5 School
b) High School
c) Site
6) O&G Progress Reports:
a) 3-5 School
b) High School
c) Middle School pool backwash
status;
cost; leachfield
d) Hurlbutt parking lot lighting
7) Soft Cost Presentation / Review
all
projects / phases
8) Invoice Approvals:
Consultants
& others
9) Change Orders:
a) High School
b) 3-5 School
c) Revson/Zenon
d) Others as required
10) Any other business that may
properly
come before the meeting:
11) Next Meeting:
Wednesday
01/26/05 @ 7:30 PM
WESTON SCHOOL BUILDING COMMITTEE,
Wednesday, January 12, 2005, 7:30pm, Commission Room at Town Hall
Approve Minutes of Previous
meetings:
Meeting 1/05/05/done
O&G Monthly Schedule
Review:
O&G presentation & SBC Review
a) 3-5 School/more
brick
going up
b) HS/outline of what is yet to
be done and when
c) Site/progress being made on
power
issue
O&G Progress Reports:
NOTE:
All
reports on this meeting are without benefit of written, final versions
of documentation.
a) 3-5 School/although
behind
earlier schedule, now on track for turnover of building before the
summer
(our interpretation, not an official statement)
b) High School/lots of progress
on science wing (to open @same time as above other building - our
interpretation)
c) Middle School pool backwash
status;
cost; leach field/getting closer to completion
d) Hurlbutt, parking lot
lighting/this
is a topic we will not comment upon.
FF&E; IT:
a) 3-5 School/as of
later
this week, plans to be drawn up for needed replacement furniture and
new
where needed.
b) HS/in particular, IT
important
on this facility.
Invoice Approvals:
Consultants
& others ("About Town" left at this point)
Change Orders:
a) High School
b) 3-5 School
c) Revson/Zenon
d) Others as required
Any other business that may
properly
come before the meeting:
Next Meeting:
Wednesday
01/19/05 @ 6:30 PM with SBC & F-T
a) Wednesday
01/19/05
@ 6:30 PM with SBC & F-T (separate agenda)
b) Wednesday
01/19/05
@ 7:30 PM
WESTON
SCHOOL BUILDING
COMMITTEE,
Wednesday, January 5, 2005, 7:30pm, Commission Room at Town Hall
Approve
Minutes of Previous
meetings:
a) Meeting 12/08/04/OK
-
with a change
b) Meeting 12/15/04/OK
Temporary and permanent power at
the
High School and 3-5 School/working on generating it.
Pending Approvals/Installations:
a)CL&P Power
b)Middle School Pool Backwash
O&G Monthly Progress
Report
#6: O&G presentation & SBC review/so far so good, but we
may be falling behind
O&G Progress Reports:
a) 3-5 School/closed
in,
brick work on the way (but not done inside)
b) High School - PVC piping in
plenum
ceiling /plenum ceiling/status update/?
c) Middle School pool backwash
status;
cost; leach field/redo on design for pool backwash needed
Invoice Approvals:
Consultants
& others
Change Orders: (discussion of how
many outstanding ones presently--there appears to be some comfort that
most have been identified)WE LEFT BEFORE IT BECAME ICEY.
a) High School
b) 3-5 School
c) Revson/Zenon
Any other business that may
properly
come before the meeting: Next Meeting: Wednesday
01/13/05
@ 7:30 PM
WESTON SCHOOL BUILDING COMMITTEE,
Wednesday, Dec. 15, 2004, 7:30pm, Commission Room at Town Hall
1) Approve Minutes of Previous
meetings:
meeting 12/08/04/not until next meeting.
2) O&G Monthly Progress
Report
#6: O&G presentation/more to come.
3) O&G Progress Reports:
a) 3-5 School/on
schedule
and 28 masons now at work
b) High School/on schedule and
major
milestones to be reached soon
i) PVC piping in
plenum
ceiling / status update/action needed soon.
c) Middle School pool backwash
status,
cost, alternates/WWHD on the case and we hope to move more effectively
with this local organization (that is so familiar with our
situation--and
someone whom we can trust to act promptly).
4) Invoice Approvals:
Consultants,
contractors, & others/we left
5) Change Orders:
a) High School
b) 3-5 School
c) Revson/Zenon
6) Any other business that may
properly
come before the meeting:
7) Election of SBC officers for
Year 2005.
8) Next Meeting: not next
Wednesday!
Merry Xmas (Santa Claus refused to pay a visit to the School Project
until
the plenum ceilings are done to code. And that goes for the
reindeer,
too) to O&G, SBC and all the contractors from at least one
Westonite!
WESTON SCHOOL BUILDING COMMITTEE,
Wednesday, Dec. 8, 2004, 7:30pm, Commission Room at Town Hall
- Approve Minutes of
Previous
meetings:
a) Meeting 11/17/04 b) Meeting 11/22/04/done with one change
- Review of Maki / Levi
property/School
Building Committee recognized that the construction project damaged the
Maki-Levi property (took down the trees and brush that formed a natural
buffer between Revson Field and the M-L property) although there should
have been not action taken within the natural buffer as shown on
plans.
Replacement foliage/trees will be installed at the opportune time for
best
growth possibility.Landscape budget review/amount identified for Army
Corps
required work, buffer for all neighbors affected who have come forward
so far and funds for stone wall in front of high school.
NOTE:
memorial trees included in this funding: total of @$250,000
obligated.
- Follow-up review of Fire
Dept
requested
upgrade/Fire Department and Fire Marshall's office present to discuss
the
range of options - no final numbers until O&G gets report on a
different
type of monitoring device.
- Site security, fencing and
gates/people
using artificial field (soccer) for other sports (how to police over
the
weekend?)
- O&G Progress Reports:
a) 3-5 School/"i" change order
OK'd,
About Town left before coilor selection decided
i) Metal panel
cavity wall
waterproof / status update Change Order
ii) Color selection for gym
b) Revson Field;/DEP says OK to
use
plant
i) DEP approval
status
c) Zenon Plant activation
schedule update/1200
gallons processed so far
d) High School/not resolved
i) PVC piping in
plenum
ceiling/ status update
e) Middle School backwash
status/not
resolved
Pending Approvals: CL&P
power
easements/in hands of Town Atty (CL&P OK'd it)
Change Orders:/About Town left
a) High School
b) 3-5 School
c) Revson; Zenon
WESTON
BUILDING COMMITTEE, Wednesday, Dec. 8, 2004, 7:30pm, Commission Room at
Town Hall (to be conducted at completion of School Building committee
business
agenda) - About Town was not present for this - but we will be at the
Lachat
Conservation-Education Center meeting tomorrow at 4:30pm in the
Commission
Room.
Attendance
Call
Meeting to Order
Design
of the Lachat
Conservation
Center at the Devils Den Preserve
- Discussion of the role of the
Building Committee
- Review of
architectural/engineering
consultants AIA agreement
Any
other business that may
properly
come before the meeting
Adjournment
WESTON SCHOOL
BUILDING
COMMITTEE, Wednesday, Dec. 1, 2004, 7:30pm, Commission Room at Town
Hall/
CANCELLED
WESTON BUILDING COMMITTEE,
Wednesday,
Dec. 1, 2004, 7:30pm, Commission Room at Town Hall (to be conducted at
completion of School Building committee business agenda)/CANCELLED.
SPECIAL WESTON SCHOOL BUILDING
COMMITTEE,
Monday, November 22, 2004 at 7:30pm, Commission Room at Town Hall
1) Approve Minutes of Previous
Meetings:
Meeting 11/17/04/not done
2) Review Fire Dept requested
upgrade/discussion--need
O&G input on high school detail (more next meeting)
3) Review O&G Monthly Report
#5, October/we rec'd a copy
4) O&G Progress Reports:
a) Metal panel cavity
wall
waterproof/ status update; C.O./more info needed--not yet a leading item
b) School security upgrade/no
report
c) 3-5 School
i) Color selection
for gym/in
progress
d) Revson Field;
i) DEP Approval
status/due
soon
ii) Fence along property
line/needs
remediation
e) Zenon Plant activation
schedule/see
above D.E.P.
f) High School
i) Review of HS
construction
schedule/falling behind, but if winterized in a timely fashion, should
not be a problem
ii) PVC piping in plenum
ceiling/
status update/can't have PVC in any part of building where gray
water/septic
is involved or where fire might be a threat (?)
g) Middle School pool backwash
status/?
5) Pending Approvals:
a) CL&P power
easements/?
b) DEP septic approval/see above
6) Change Orders:?
a) High School
b) 3-5 School
c) Revson; Zenon
7) Any other business that may
properly
come before the meeting:
8) Next Meeting: Monday 12/01/04
@ 7:30 PM
WESTON SCHOOL BUILDING COMMITTEE,
Wednesday, November 17, 2004, 7:30pm, Commission room at Town Hall
(rev.). Additionally, Fletcher-Thompson will address the issues
of
“Metal panel waterproof estimate / status” at 3-5 School and “PVC
piping
in plenum ceiling” at the High School.
- Approve Minutes of
Previous
meetings:
Meeting 11/10/04/done
- Review of Fire Dept
requested
upgrade/long
discussion--more on Monday, Nov. 22 special meeting
- Site security after
working
hours/repeat warning of do not trespass
- O&G Progress Reports:
a) 3-5 School
i) Metal panel
waterproof
estimate / status/long discussion with Fletcher-Thompson, more Monday,
Nov. 22
ii) Masonry contractors
schedule,
C.H. Nickerson, in writing & signed/action needed.
b) Revson Field; DEP Operation
status;
concrete dugout pads
i) DEP Operation
status/due
end of November.
ii) Concrete dugout pads/not
in
the plans as of now.
c) Zenon Plant; Operation
status; activation
schedule/see above--plant ready to go!
d) High School
i) Metal Panel
waterproof
estimate / status/see above
ii) Revised construction
schedule/not
handed out to public
iii) PVC piping in plenum
ceiling/a
no-no--iron used.
e) Middle School pool backwash - Status of Governmental
Approvals:
CL&P Power Easements for Schools/maybe getting closer
- Review of O&G Monthly
Report, September
2004; items not discussed 11/03
- Change Orders: LOTS!
a) High School
b) 3-5 School
c) Revson
d) Site - Invoices for
Payment -
LOTS...we
left
- Invoices for Application
- Any other business that
may
properly
come before the meeting:
Next Meeting: Monday 11/22/04 @
7:30
PM
WESTON
SCHOOL BUILDING
COMMITTEE,
Wednesday, November 10, 2004, 7:30pm, Commission Room at Town Hall
Approve
Minutes of
Previous meetings:
Meeting 11/03/04/done
3-5 School
- Metal panel waterproof
estimate / status/?.
- Masonry contractors
schedule,
C.H. Nickerson,
in writing & signed/not yet.
Revson
Field; DEP
operation status;
Sprinkler review; concrete dugout pads/not yet, not until Spring and
not
in contract.
Zenon
Plant; operation
status;
activation schedule/must wait until WMS effluent feed ready.
High School
- Metal Panel waterproof
estimate / status/same
- Revised construction
schedule/waiting
on Nickerson.
Middle
School pool
backwash/can
be fixed easily.
Status
of Governmental
Approvals:
- CL&P power easements
for
Schools/not
cooperative
- CL&P power at
Morehouse
Farm Park/"
"
Review
of O&G Monthly
Report;
September 2004, items not discussed 11/03/some details not clear--still
money left, but getting less and less ("stop the bleeding")--my
observarion,
the that of the S.B.C.
Change
Orders:
("About
Town" left at this point)
- High School
- 3-5 School
- Revson
- Site
Invoices
-
Consultants
&
Others
WESTON SCHOOL BUILDING COMMITTEE,
Wednesday, November 3, 2004, 7:30pm, Commission Room at Town Hall
1)Approve Minutes of Previous
meetings:
a) Meeting 10/20/04, as revised b) Meeting 10/27/04/done
2)O&G Progress reports:
a)3-5 School
i)Masonry manpower
status,
C.H. Nickerson/promises to be ready with end of outdoor brick-work by
first
week in December.
ii)Bid review of tack boards,
marker
boards/further discussion.
b) Revson Field; Yard
Drains/moving
ahead.
c) Revson Field; DEP Sprinkler
approvals/not
to get this 'til other parts of project work.
d) Zenon Plant/the other
part--next
week DEP down, we think.
e) High School
i) Weekend
supervision/need
some.
3) Status of Governmental
Approvals:
CL&P Easements for Schools/still in the works.
4) Fletcher Thompson presentation:
a) Metal panel
installation
for HS & 3-5 School/long discussion - decision made, we think.
b) Color presentation/samples to
be provided on-site.
c) Signage/selection indoors
made
(type face still to be chosen from 3)
d) Contract issues/discussed in
open session - regarding assistance with FF&E for Board of
Education.
5) Review of O&G Monthly
Report;
September 2004
6) Change Orders: ("About
Town" left at this point--wondering about the relation ship of item
above
to this one).
a) High School
b) 3-5 School
c) Revson
d) Site
7) Invoices
a) Consultants & Others
8) Any other business that may
properly
come before the meeting...
WESTON SCHOOL
BUILDING
COMMITTEE, Wednesday, October 27, 2004, 7:30pm, Commission Room at Town
Hall
AGENDA (minutes, other
regular
items excluded from this version of posted "agenda")
- Status of Governmental
Approvals:
CL&P Easements for Schools/nothing new
- Review of O&G Monthly
Report, September
2004/draft to Committee for review at next meeting
- O&G Progress
reports: discusion,
no voting on these items (no quorum)
Change Order work and approvals
Revson Field, Yard Drains
Revson Field, DEP Sprinkler
approvals
Zenon Plant
High School
3-5 School and "bid results for
marking boards & tackboards"
Masonry manpower status - Next
Meeting: Wednesday
11/3/04 @ 7:30
PM
WESTON
SCHOOL BUILDING
COMMITTEE,
Wednesday, October 20, 2004, 7:30pm, Commission Room at Town Hall
AGENDA
- Site
safety/members
of the Committee and members of the public MUST register with the
O&G
trailer, get signed in and get a hard hat prior to taking an escorted
'walk'--all
other walks are unapproved and are in violation of safety rules (our
interpretation
of this policy); Tree Donation/after ONE HOUR of discussion and first a
negative vote to recommend donation as proposed, another motion passed
5-2 approving the gift but remaining silent on location of trees and
sizes.
- Approve
Minutes
of Previous meetings: Meeting 10/13/04 OK'd with amendment (added name
of member);
- O&G
work progress
reports: briefly noted...
a) Revson
Field; Yard Drains; in progress
b) Revson
Field; DEP Sprinkler approvals - in progress
c) Zenon
Plant/Nov.
1 finished (C,L&P gave quick OK!)-then start up testing to be done
BY THANKSGIVING (perhaps?);
d) High
School
- brick going up, timing of installing new pipng and taking off line
the
old system;
e) 3-5
School/brick
chugging along - to be "tight" for winter work by 12-15.
i) Masonry
manpower status/better
f)
Morehouse
Farm Park permanent power/? - Presentation
of
Change Orders by O&G: ("About town" didn't stay for this);
a) High
School
Power
b) 3-5
School
c) Site
d) Revson
Field - Status
of Governmental
Approvals:
a) DOT 3’
x 6’ culvert
b) DEP,
Revson
Field
c)
CL&P
Easements for Schools - High
School Water
Infiltration: Revised roof drainage proposal
- Invoices
for payment:
Consultants
Next
Meeting:
Wednesday 10/2704 @ 7:30 PM
WESTON SCHOOL BUILDING COMMITTEE,
Wednesday, October 13, 2004, 7:30pm, Commission Room at Town Hall
- Executive Session/no
decision
made after;
- Status of Government
Approvals
(DOT,
DEP and CL&P "easement")/yes, don't know, don't know;
- High School Water
Infiltration
- revised
roof drainage/discussion, drawing needed to explain it (my
interpretation);
- O&G: progress on
Revson (last
week of October next progress point), Zenon (two weeks after CLP OK, on
line), High School additions (moving along--critical item:
permanent
power), 3,4,5 school (close in by Dec. 15), masonry manpower status (19
masons now), sprinkler requirements for Revson (will need watering
alot),
Morehouse Farm Park permanent power (on); discussion of trees
(where
to locate gift--there is a plan suggested by anonymous donor to be
reviewed
to see that it fits in with rest of plan--thanks to donor!
(NOTE:
"About Town" left at this point.)
- PRESENTATION OF CHANGE
ORDERS
by O&G:
high school power, 3,4,5 school, site.
- INVOICES FOR
PAYMENT:
consultants
& others.
WESTON SCHOOL BUILDING COMMITTEE,
Wednesday October 6, 2004, 7:30pm Commission Room at Town Hall
AGENDA
- Tree Donation SBC/BB
- O&G work progress
reports:
- Revson Field; Yard
Drains; Stu
F/ BB/ CRG
- Revson Field; DEP
Sprinkler
approvals
Stu F/ BB/ CRG
- Zenon Plant O&G/MS
- High School O&G/RM
- 3-5 School
O&G/MS:
Masonry
manpower status O&G/MS
- Morehouse Farm Park
permanent power
O&G/DP
- Presentation of Change
Orders
by O&G:
- High School Power
O&G/RM
- 3-5 School
O&G/MS
- Site O&G/RM
- Revson Field O&G/RM
- Status of Governmental
Approvals:
- DOT 3’ x 6’ culvert Stu
F/CRG
- DEP, Revson Field Stu
F/CRG
- CL&P Easements for
Schools CRG
- High School Water
Infiltration:
Revised roof drainage proposal Dan C/CRG
- Invoices for payment:
Consultants CRG/SBC
- Next Meeting: Wednesday
10/2704 @ 7:30
PM
WESTON SCHOOL BUILDING COMMITTEE,
Wednesday October 6, 2004, 7:30pm Commission Room at Town Hall
• Approve
minutes of 09-22-04 and 09-29-04 meetings/done
• High
School
water infiltration/still OK, but not sure until next big rain if
problem
solved (perhaps a more finished repair could be put in place, too).
• Status of
approvals - DOT/one DOT rec'd, another coming; DEP in progress.
• O&G
to report on progress of work
o Revson
Field/moving
along OK
o Zenon
Plant
completion schedule/testing of equipment other than patented items can
be done with temporary power--need steady power for Zenon specific
items.
• Sprinkler
system
for Revson Field/may not be needed depending on which grass chosen.
• Tree
removal/three
trees have to go near Zenon-retention pond--may be too late to plant
grasses,
so mulch or something else to be used to protect slope.
o
Hurlbutt/tree
trimming only over parking lots
o High
School
track/similar overhanging issue
• CL&P
easement
o Power
for
schools/will be there when we need it
• Building
envelope
schedule
o High
School/will
be closed in sufficiently and in a timely fashion to proceed with
interior
finishes
o 3-5
School/same
• Any other
business
that may properly come before the Committee
•
Presentation
of Change Orders by O&G/discussion of how it is vital at this point
to have a clear vision of where we are vis a vis budgets before more
decisions
about "change orders" overwhelm budget. "About Town" left at this
point.
• Invoices
for payment
• Executive
Session
• Adjournment
WESTON SCHOOL BUILDING COMMITTEE,
September 29, 2004, 7:30pm, Commission Room at Town Hall
AGENDA (major items):
- High School water
infiltration/DRY!!!
- Status of approvals -
D.O.T./nothing
new--any minute for OKs.
- O&G to report on work
in
progress:
- Revson Field/getting
done,
although
rain interferes;
- Zenon Plant completion
schedule/CL&P
easement issue may be avoided by use of generator w/o permanent
settings--last
week in October is a date to aim for completion and use (?)
- Cost Review/high school
28%
complete,
$900,000 contingency remains; April 2005 occupancy of science
wing;
- Change Orders:
ZENON PLANT
- Change to frosted
glass/we
left, but
they might have OKd this later...
3-4-5 SCHOOL
- Pipe&Power HVAC
upgrade
control
- Spectrum floors tile to
epoxy
- Merritt Contractors
coil/fire door finish
- MJ Daly vestibule
sprinkler
line
- Richards Corp site
drainage
& Fire
Department request (water tank level alarm)
- Losito electric - Fire
Department request
(water tank flow alarm)
- CL&P Easement:
- power for schools/Town
Attorney working
on it--may be a leading edge issue soon enough!
- power for Zenon
Plant/see
above
- Building Envelope
- High School and 3-4-5
school
update/discussion,
need to secure things against inclement winter weather.
WESTON SCHOOL BUILDING COMMITTEE,
September 22, 2004, 7:30pm, Commission Room at Town Hall
AGENDA:
- Minutes OK/done
- Carl Charles to
discuss
sod at
Revson
Field/done - vote to move ahead with sod from a new locally connected
contractor.
- Status of approvals -
DOT/coming - work
to be divided between two contractors;
- O&G to report on
progress
of work:
- Revson Field/DEP
"warning of
intention
to issue violation" if problem not fixed...response and remediation
report
submitted - no "violation" yet;
- Zenon Plant/to be ready
on
schedule.
- Building Envelope (we are
not
sure of
these dates--the point is to enclose buildings from weather before
winter
sets in):
- High School/mid December
- 3-5 School/we think
sooner.
- *High School Water
Infiltration/report
from Facilities Manager Bd of Ed - third flood in parts of same area -
cleaning out under drains continues and is debilitating and a test for
staff to keep shifting from room to room, cleaning and recleaning
carpet,
swabbing down the decks against mold infiltration. This problem
appears
is a forceful FLOOD condition during periods of extreme rainfall
(that's
the way we heard it).
- Applications for
payment/not
done while
"About Town" was present;
- Invoices for payment/same
- Vote to add to the agenda
an
executive
session on personnel matters/we left.
*= Taken first after minutes OK.
WESTON SCHOOL BUILDING COMMITTEE/(NOT
BUILDING COMMITTEE*)
Wednesday, September 8, 2004,
7:30pm,
Commission Room at Town Hall
AGENDA INCLUDES (previous listing
here was as of 3pm - this is 4pm version - item added):
- Approve minutes of
08-25-04
meeting/done
- introduction of new member of the Building Committee;
- Carl Charles to discuss
bleachers
and scoreboards at high school football field/after long and
detailed
discussion of history of how the football field's attendant facilities
have been designed and redesigned over the past few years, no decision
was made; discussion of whether 2 baseball fields at Revson would
be ready for Spring '05--if all sod in budget is used on one field and
not on the other, there can be suitable facilities for high school play
(will make do).
- Detailed project schedule
by
O&G/carpenters
in short supply, holding up other trades? Construction Manager
reported
on septic fill delay, decision made to keep pumping out tanks and
letting
fields dry and/or stay dry until septic fill for new fields is
installed
(that's what we got out of the discussion);
- Applications for
payment/"About Town"
left @9:20pm.
- Invoices for payment
WESTON SCHOOL
BUILDING
COMMITTEE/BUILDING COMMITTEE
Wednesday, August 25, 2004,
7:30pm,
Commission Room at Town Hall
AGENDA INCLUDES:
- Detailed project update by
O&G:
where ahead of schedule and where behind/Owner's Rep reported flooded
rooms
at high school after heavy rains--engineering solutions being proposed
to keep water out of foundation and interior rooms, guided to drainage
system (we think);
- Review of dugout design at
Bisceglie
Park/suggested minor detail changes to improve circulation and
construction
details.
- Review of scoreboards at
Bisceglie Park/not
an issue for Building Committee, other than construction - OK.
- Status of cable repair
work on
School
Road/other than closing it in, working great now!
WESTON SCHOOL BUILDING
COMMITTEE/BUILDING
COMMITTEE
Wednesday, August 18, 2004,
7:30pm,
Commission Room
- Detailed project update by
O&G:
where it is ahead and where it is behind/ehind because of weather, but
ahead where projects have been consolidated;
- Discuss July 2004 project
cost
reports/still
have goodly size contingency left;
- Status of cable repair
work on
School
Road/up and running - CABLEVISION and SNET not finished;
- First Selectman discusses
limited use
of new fields this Fall - Bisceglie for kids weekend games and, after
"punch
list" finished next week, Parks and Recreation Commission can make
decision
to use some (artificial ones) this Fall, perhaps. Use after
second
or third week in September. Ribbon cutting "play ball" at
Bisceglie
second week in September, weather permitting.
- Invoices and applications
for
payment/did
not stay for this.
WESTON SCHOOL BUILDING
COMMITTEE/BUILDING
COMMITTEE
Wednesday, August 11, 2004,
7:30pm,
Commission Room
- Detailed project update by
O&G and
F-T/things moving along on schedule (more details given, but so many
different
projects and parts of projects ("trades") that it is too much detail
for
observer not privy to all of these;
- Status of cable repair
work on
School
Road/moving along somewhat ahead of schedule;
- Status of claim
submitted/work
proceeding.
WESTON SCHOOL BUILDING
COMMITTEE/BUILDING
COMMITTEE
Wednesday, August 4, 2004, 7:30pm,
Commission Room at Town Hall.
- August 4, 2004, 7:30pm,
Commission Room
at Town Hall Status of cable repair work on School Road and Hurlbutt
septic
field vis à vis the schedule/on schedule--School Road to be
paved
with binder course the week of August 20 (#1 "pavement plan"); #2
parking
plans and #3 egress plans available at Board of Education offices as
well
as construction trailer.
NOTE: copies of the first
two - parking and paving - are now on our unofficial school
construction webpage. - Detailed
construction
schedule update
on a project by project basis/time made up--moving ahead of schedule in
some arts, lagging a week on others...
- Description of site
conditions
when
teachers return on August 24/August 18th new staff training (off site
or
at Hurlbutt); returning staff comes back on August 23--old and
and
new staff participate in teacher session at Temple Israel August
25-26-27;
School opens for students August 30; auditorium will not be
usable
for performances 2004-2005 school year, so plays will be performed
elsewhere.
- Report by Alan Swerdlowe
on
Tuesday
morning’s proposed Change Order review meeting/motion made and seconded
to deny claim by contractor working on high school gym walls.
- Executive Session
WESTON SCHOOL BUILDING
COMMITTEE/BUILDING
COMMITTEE
July 28, 2004, 7:30pm, Commission
Room at Town Hall
- Report on cable repair
work on
School
Road and Hurlbutt septic field vis-a-vis schedule/new fibre opticlines
in place and working, August 10...septic system at Hurlbutt under
repair
now...to use stronger (concrete rather than plastic) piping;
- Review of June 2004
project
cost reports/
- project generally on
time
and on budget--no
surprises,
- SBC will save $2.26
million
in reserve:
- Zenon tank coming by
August
10, plant
operational September 19--in the meanwhile septic at WMS to be used
with
pumping as needed (twice already this summer);
- School Road to be paved
August 16-20
with first course;
- Hurlbutt driveway paving
finished by
August 28
- State of Connecticut
wants
different
pipe size under Route 53 (?) - will not stand in the way of school
opening
on time.
- Invoices/"About Town"
didn't
stay for
this item.
WESTON SCHOOL BUILDING
COMMITTEE/BUILDING
COMMITTEE
Wedneday, July 21, 2004, 7:30pm,
Commission Room at Town Hall
- Architect's Report/window
treatments
unified (for lower cost!!!)
- Discussion of repair work
on
School
Road and Hurlbutt parking lot/$125,000 OK'd, moving some later stage
improvements
ahead of schedule;
- Presentation of change
orders
by O&G
(please note that only the subject of change orders as this WEBPAGE
supposes
them to be are noted on line):
- Zenon Plant/we were out
of
the room,
(but we think things are going OK since the discussion did not take
long);
- mechanical value
engineering
- 3-4-5 School - all OK
- gym floor
- courtyard
- kitchen
- telecomm
conduit/sleeves
- add site communication
conduit
- high school - OK
- well abandonment
- flashing in existing
wall
- Application for payment
for
Zenon Plant/F-T
signed off, payment should go forward. NOTE: We asked how
the
whole project was progressing overall, and reports show progress and
surprisingly,
we are UNDER BUDGET (unless someone was pulling my leg)!
WESTON SCHOOL
BUILDING
COMMITTEE/BUILDING COMMITTEE
Wednesday, July 14, 2004, 7:30pm,
Commission Room at Town Hall
•
Construction progress
update/computer
wiring under School Road breached;
•
Schedule issues/some ahead,
some
behind by two weeks;
•
Applications for
Payment/submitted
and most to be addressed next week when Construction Manager and
Architect
are present at the same
time;
•
Invoices for
Payment/same
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
Wednesday,
June 30, 2004, 7:30pm, Commission Room at Town Hall
• Barry
Blades
presentation of the campus landscaping plans/neighbors present from
various
abutting points - new planting to go in no earlier than next Spring;
• Board of
Education request for approval:
Architect
for North House windows and South and East House doors/OK received
•
Construction
progress update/schedule/actual building going well, but septic system
existing at Revson not able to function during construction of new
"white
water" septic system, so it would seem as of this moment. Pumping
existing system - cutting off before effluent gets to fields - using
the
tank only (20,000 gal. tank when empty) and pumping twice a month until
new tertiary treatment plant and "white water" fields ready seemed the
best solution at the moment. Other ideas: portajohns,
bottled
water, handiwipes; W.M.S. to open for teachers to return (under
contract)
August 23rd (?).
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
Wednesday,
June 23, 2004, 7:30pm, Commission Room at Town Hall
- Report
results
of Town Meeting regarding Revson Field/back to original plan.
- Board
of
Education
requests for approval:
a.
Architect
for North House windows and South and East House doors/copies to be
reviewed
and voted upon next week
b.
Plans
and specs - asbestos abatement at Hurlbutt and Middle School/approved
as
per wording the Board of Education suggested, to be included in
the
minutes of this meeting of the Building Committee
- Construction
progress
update/schedule:
- 2
weeks behind
on some parts, 4 weeks ahead on others;
- School
Road "reclaimed"
for construction project;
- Bisceglie
going
well;
- School
Building
Committee voted to keep Zenon roofing material as the originally
specified
($3400 more that "value engineering" type);
- Morehouse
Farm
Park Public Hearing at Conservation reported not going well - Town of
Weston
trucking in water to keep sod and seed alive.
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
Wednesday,
June 9, 2004, 7:30pm, Commission Room at Town Hall (not the actual
agenda):
- North
House work
review by Building Committee (of items provided by Board of Education
staff
for construction SOON)/more detail to come in future meetings;
discussion
of Cina tree relocation - may happen at Town expense (this is a bad
time
to relocate a mature tree--but if it is not too long a trip, shock to
tree
roots may not be fatal...).
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
Wednesday,
June 2, 2004, 7:30pm, Commission Room at Town Hall
- Options,
Revson
Field Layout/discussion of plan C-1 (executive session to discuss
contract
for Revson Fields revisions to keep big trees);
- School
campus
construction progress update/moving along - discussion of capital work
non-Referendum: process of review of design and bidding on, in
particular,
the bus garage roof and North House windows.
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
Wednesday,
May 26, 2004, 7:30pm, Commission Room at Town Hall
- Options,
Revson
Field Layout/alternatives shown to save big trees by reorienting 2
fields,
soccer field, adding fill and retaining wall - next Tuesday these trees
might have been removed, but School Building Committee orders O&G
to
mark them not to be cut.
- High
School Soccer
Field Lighting/price escalates by more than half what was estimated.
- School
Campus
construction progress update/steel up on two more sections of high
school;
change order proposals next meeting; Zenon plant location moved
closer
to School Road to avoid C,L&P pole...and mid-June completion on
Morehouse
Farm Park; Bisceglie to be finished by end of June 9 - fields
with
sod finished but not usable until Fall.
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
Wednesday,
May 19, 2004, 7:30pm, Commission Room at Town Hall
AGENDA
includes:
- High
School Field
Lighting/(this is the soccer field, not football field) still debated
as
to when and exactly what is entailed, process.
- Recommended
award
of fencing contract/done, review by neighbor and staff as to details of
fence upcoming.
- School
campus
construction progress update/on schedule
- Fletcher-Thompson
and O&G exterior and interior finishes review/more to come (matrix
as to precisely which choices have been made where);
- Invoices
for payment/discussion
as to how meetings are run and should be run to be most effective.
WESTON
SCHOOL BUILDING COMMITTEE/BUILDING COMMITTEE
Wednesday,
May 12, 2004, 7:30pm, Commission Room at Town Hall
AGENDA
includes:
- Parks
and Recreation
Commission: High School Soccer Field Lighting/advised to get full
budget picture
- Discussion
of
High School stone wall/brief
- Raked
joints on
the brick at high school and 3-4-5 School/not discussed
- Zenon
Plant update/site
readied
- Invoices
and any
other business/we left.
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
Wednesday,
May 5, 2004, 7:30pm, Commission Room at Town Hall
AGENDA (not
a complete agena--nor is a this an official record)
- O&G
- Zenon
Plant progress report/revised design of interior simplified while still
providing "hiding" of building in site plan - estimated finishing date,
plant to be operational mid-September (high school and middle school to
use part of Revson septic system until then--as About Town recalls,
perhaps
correctly, the middle school septic system is divided and controlled so
that flows can be redirected to various parts, as engineers feel is
necessary).
- O&G
- recommendations
for award:/awards made to contractors for specific parts of projects
at...
- high
school
- school
campus
- Zenon
Building
- O&G
- summary
of work completed last week/concrete and some steel in progress...
- O&G
- "look-ahead"
for month of May/more steel, sitework, completing new road (?) crossing
- Executive
Session
- contracts, fees/About Town understands that no action was to be taken
after
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
Wednesday,
April 28, 2004, 7:30pm, Commission Room at Town Hall
AGENDA
(includes
approval of minutes of March 31 and April 14)
- Fire
Department
requests/discussion of change order for simplified fire hydrant system
in front of high school--if not satisfactory, revisions can be made to
access in the future; in the meanwhile, special sub-base and sod
covered
accessway will be clearly marked, differentiating it from regular lawn
areas.
- Fletcher
Thompson
and O&G present Zenon bids and recommendations/came in VERY high -
with award of contract to low bidder, revisions will be made by Chair.
and O&G and F-T that still satisfy needs.
- Performing
and
Creative Arts Center report by ARO/after additional study, too
expensive
to go forward at this time with modified competition winning design
($5.7
million instead of $4.2 million [level of funding not to be exceeded]);
- O&G
present
project status reports; ahead on some, slightly behind on others
(brick not yet ordered) of School Road projects;
- O&G
presents
proposed Change Orders/"About Town" left at this point (9:45pm).
- Rooftop
units
-3-5 school
- Rooftop
units,
high school
- Soil
and erosion
controls - Main Campus
- Fire
Alarm system,
Town Hall
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
NOTE: no
School
Building Committee meeting April 21st.
AGENDA for
April 14, 2004: REPORT ON SUMMER WORK AND CAMPS; status
updates,
invoices, any other business/CAMPS WILL GO ON! But it will
be necessary for everyone who participates to be carefull and be
prepared
to use portajohns, bottled water, wipes; ACCESS will be from
Lord's Highway only to the Middle School for camps. School
Road
will be closed between WMS and Hurlbutt (we think); pool
open
at WMS in July but not August (usual cleaning). IMPORTANT:
ACCESS ONLY FROM THE BACK OF WMS (where we go to vote each
November)...special
steps taken to make safe access and parking around the back to fields
and
school.
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
Wednesday,
April 7, 2004, 7:30pm, Commission Room at Town Hall
Revised
AGENDA
Insurance
Issues, O&G application for payment, invoices, any other
business/quorum
present. Town Insurance professional reviewed coverage for
construction
in all aspects. Steel payment discussed and confirmed with
project
management team, summer construction scheduled discussed as it relates
to other School Road activity.
WESTON SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
Wednesday,
March 31, 2004, 7:30pm, Commission Room at Town Hall
AGENDA items
of import:
Chair.
remarked
that additional items taken up, if known about in advance, should
appear
as specific items on the agenda, and not just "any other business."
Weston
Education
Foundation reported on their meeting with ARO and Superintendent,
Facilities
Committee Monday re: "PCAC - Performing and Creative Arts
Center."
An auditorium of the type "end stage theater" (no fly space) which has
wings, aisles, would be acceptable to drama and performance staff and
true
to Ed Spec. Foundation will get back in gear and continue fund
raising
to this level (not as expensive as "fly space" alternative).
O&G
reported on status of construction and preparation for rains now
coming
down--O&G wants to be proactive in the event any breaches to
S&E
controls take place at any of the 3 sites (Campus, Bisceglie or
Morehouse).
Jennifer Perry of DEP reviewing final drawings of Zenon
plant.
A month from now steel with begin; box culvert installed early
April,
then road to the 3-4-5 school to be built across wetland. There
are
@40 workers on site.
Artificial
Surface action of Selectmen discussed with First Selectman
re:
Special Board of Selectmen's Meeting of March 29- and the suggestion
that
funds from the referendum go to cover the immediate shortfall of
@$40,000
in the fundraising ($460,000+raised already). NOTE: fundraising
for
the football field continuing--but full amount needed to place the
order
with the contractor - had to be right now or there would not be
adequate
time to build it for Fall season.
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
Wednesday,
March 24, 2004 at 7:30pm, Commission Room at Town Hall
AGENDA
includes:
- O&G
update
of progress/on time;
- O&G
presentation
of change orders/unsuitable soil found at site of science wing
foundation
- crushed stone to be best solution to keep the schedule as well as be
bestchange to make ("change order" for 200 yds of it OK'd);
- Harold
Mindell
to present fencing modifications at Silverstein property/we left before
resolution of this request by closest neighbor to 3-4-5 school.
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
Wednesday,
March 17, 2004, 7:30-m, Commission Room at Town Hall
AGENDA
Report of
earlier meeting with Construction Manager O&G, Zenon Plant delivery
and construction report from Owner's Representative and discussion of
fund-raising
plans, now on hold until School Building Committee
completes
assessment of best Middle School Auditorium program choice for design
competition
winners to follow (i.e. number of seats, fly-space, wings [left and
right]).
(Weston Ed Foundation does not wish to misrepresent what funds are
being
raised for).
School
capital
projects OK'd by Building Committee.
WESTON SCHOOL BUILDING COMMITTEE/BUILDING COMMITTEE
Wednesday,
March 10, 2004, 7:30pm in the Commission Room at Town Hall
AGENDA
includes
report from Police Chief, Owner's Rep, O&G (on many projects).
- Chief
Land spoke
and indicated that the Police Department would be prepared to help out
and offer needed protection services when and if more were
needed.
Plans at this time are secure (as in posted, campus protected and
outlying
projects under control).
- Owner's
Rep proposes method for "on the spot" decisions on small changes ($$)
and
an increasing amount/increasing formality of process
additionally.
He will present this again next week in writing. School
Facilities
Director reported to the Building Committee on projects funded
in
the capital budget that are moving forward (North House work, bus
garage
roof, etc.);
- O&G
spoke
of considerable progress so far, but warned of several problems--noted
below are contingency plans to be available if needed:
- the
first was
getting C,L&P to turn off service at 16 Parade Ground Court;
- second
was Zenon
Plant overrunning completion timeframe, perhaps (April contract
signing?)--two
alternatives suggested to minimize this: 1)7 day work week is
one
2)gaining time by planning pumping of W.H.S. septic multiple times per
day for the few weeks it might be necessary;
- third
was the
fact that O&G reported there is no extra fill/soil on campus as of
today. Last week's School Building Committee had discussed the
"extra"
fill on campus--which was considered as available to make up the
shortfall
in the budget of the artificial turf football field. The Sports
Complex
group hoped this cost-cutting opportunity was real. (This week O&G
reported contractors working on School Road projects will not be able
to
determine what part or all of this "extra" fill they will need until @
May.)
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
Wednesday,
March 3, 2004, 7:30pm, Commission Room at Town Hall
- O&G
discussion
of temporary fencing, signs, and site security/policies to be
established
very soon to strongly "police" school campus site; weekdays
covered;
need more to fill in time weekends, after hours;
- O&G
presentation
of change order procedure/discussed, agreed on procedure requiring
multiple
signatures, two step process;
- Review
of football
field finances/on schedule, on budget (with some adjustment);
- CHANGE
ORDERS
FOR APPROVAL/done;
- Any
other business,
invoices for payment/discussion of next steps in PCAC process/"About
Town"
left before this last item completed.
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
Wednesday,
February 25, 2004, 7:30pm, Commission Room at Town Hall
(NOTE:
this WEBsite will upload the monthly schedule and other information
distributed
for the month of March when it is current.)
- O&G
recommendations
on contract awards/made and voted upon; some further
investigation
on fields.
- O&G
presentation
on temporary fencing, signs, and site security/Coimmittee sees need for
a more comprehensive approach to make certain EVERYONE can tell where
the
places you are not supposed to be are...O&G staff reported on
procedures:
registration at trailer, colored LARGE badges for workers;
Committee
will be meeting alternate weeks in the future in the form that has been
done--regular Town Hall meetings now to be twice a month--and regular
7am
"trailer" meetings, we think Wednesdays, for those who can make it the
other Wednesdays. Some on Committee not happy that they cannot
inspect
progress of construction independently on weekends.
- O&G
description
of action to be taken if site (soil?) and erosion controls fail/formal
procedures now in place.
- O&G
Morehouse
Farm and Bisceglie Park update/cerrain aspects of completion must wait
until later in spring when ground is receptive and less apt to break
away.
- Review
of O&G
construction schedule for the month of march/presented to committee.
- Invoices,
any
other business
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
Wednesday,
Feb. 11, 2004, 7:30pm, Commission Room at Town Hall
- Discussion
of
future evening and daytime (job site) meeting schedule/fewer Regular
meetings
now (perhaps 2 per month), but one of these should be full report on
projects'
status including financials, dates, with representative from O&G as
well as Fletcher-Thompson; on-site meetings once a week with
Owners
Rep, O&G and Schools person in trailer--beginning@8-8:30am--morning
review of high school project; afternoon, 3-4-5.
"Monitoring
on-site" discussed, with differing approaches. O&G "walk the site"
events at 7am prior to 8am meet.
- Community
and
school population participation during construction/Schools in the
process
of assessing demand for whatever type of info desired; weekly
article
in FORUM on progress on projects.
- Review
of costs
to date of Performing and Creative Arts Center/$18K to Director, $15k
to
each of three (3) finalists.
- Discussion
about
removal of PCAC Exhibits from Weston Library/will move from school to
school
initially.
- NEW
ITEM
ADDED:
First Selectman report: Capital Planning Committee interested in study
of Town structures (for scheduling regular maintenance program); #5 of
6 lawsuits dismissed (Bisceglie the last one); EXECUTIVE
SESSION:
Contract revisions. ("About Town" left at this point @9pm)
- Invoices
- Any
other business
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
February 4,
2004, Wednesday, 7:30pm, Commission Room at Town Hall
AGENDA
included
awarding of many construction contracts for both the High School and
the
new 3-4-5 School; site work (campus-wide) and Revson and
Hurltbutt
projects/site work awarded, too. Fletcher-Thompson efforts extra
beyond what had been contemplated for the Zenon Plant discussed. Report
on Final Phase of Design Competition presented.
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
January 21,
2004, Wednesday, 7:30pm, Commission Room at Town Hall
AGENDA
includes
the usual topics - soft costs, O&G presentation of project
costs;
Morehouse Farm Park and Bisceglie Park updates; Campus Water
Supply
System report from consulting engineers, we think.
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
January 14,
2004, Wednesday, 7:30pm, Commission Room at Town Hall
AGENDA:
- Tobacco Road
residents/agreement to
work pronto to redsign the sides of the building facing residential
neighborhood.
It started to snow, and "About Town" took off.
- Performing Arts Center
Sub-Committee
report
- O&G reports - bidding
activity,
project costs
- Review of soft costs
- Campus Water Supply System
update
- Morehouse and Bisceglie
updates
- Invoices for payment.
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
January 7,
2004, Wednesday, Commission Room, 7:30pm
AGENDA:
(Chair. not present, Chair. of Design Sub-Committee absent as well).
- Update
on high
school fire alarm system/discussed
- Update
on Zenon
plant/all matter of detail being reviewed by DEP re: design details;
- Presentation
from
Linda Guller, public relations expert, doing pro bono work for the
performing
arts center/discussion of what is needed for P.R. for Performing Arts
Center
project;
- Review
of proposals
for testing and inspection/three (3) firms in the running, no decision
made.
- O&G
report
on bidding and scope review activity/bids still comining in on various
parts of project;
- Invoices,
any
other business/taken care of by subcommittee.
WESTON
SCHOOL BUILDING COMMITTEE/BUILDING COMMITTEE
Wednesday,
December 17, 2003, Commission Room at Town Hall
More
discussion
of bids and three more let out--others have to wait until site work
re-bids
come back in mid-January. Discussion of Performing Arts Center
Competition,
arrangements for Saturday, Dec. 20 all-day affair (five firms selected
to make their pitch from 8:15am thru 3:45pm) at Weston Library
Community
Room - on Town TV Channel 79 LIVE. REPORT ON COMPETITION DEC. 20
EVENT HERE.
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
Wednesday,
December 10, 2003, 7:30pm, Commission Room
Agenda
included
reports from Construction Manager O&G on latest analysis of bids
received,
and both the 3-4-5 school and the high school additions seem to be back
under budget; however, a "soft costs" draft analysis, not released to
"About
Town," was discussed at the meeting and appeared to indicate that we
may
be over seriously for previous budgets and estimates in this part of
the
project (i.e. Court costs, additional hours of consultant time for
additional
meetings and hearings, over the budget for assistance by Town
employees,
aggravated by administrative hearing requests)
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
Wednesday,
December 3, 2003 at 7:30pm, agenda includes:
Update on 3-4-5 school bids to
date,
scope review with apparent low bidders - more to come next week.
Steel and concrete awards made (and news that Army Corps had given its
approval to Site Plan!!! Officers re-elected.
AGENDA for
Tuesday, December 2, 2003 Special School Building Committee
(Town Hall Meeting Room). Invitees: Board of Education, Board of
Selectmen, Weston Education Foundation; lasted from 7:30pm to 9:30pm.
DESIGN
COMPETITION PHOTOS:
- Introduction
of
Reed Kroloff (retained to organize and administer design competition) -
discussion of process, schedule/Dec. 16, Dec. 20 and Jan. 31 set aside
for: Selection Committee to narrow down list of firms to 5;
5 firms describe their ideas/experience (@30-40 minutes ea.); selection
down to 3 finalists anounced just after New Years Day - then in 4
weeks,
these firms produce 3 boards and a model of their concept (based on
program
Committee gives them).
- Identification
of the Competition Selection Committee members/some selected - need
additional
names to fill out this group.
- Summary
profile
of 14 firms selected to submit qualifications/done.
- Discussion
of
Fletcher Thompson's participation in the process/"Executive Architect"
for the project.
- Question
and answer
period for Committee and Town/"So how much is this supposed to cost
beyond
the Referendum $3.1?" to questions about coordinating public
information
(i.e.TV all meetings/presentations).
- Board
of
Education,
Fletcher Thompson and Building Committee supply Mr, Kroloff with CD
information,
discs of the program, autoCAD files and site photos for him to
distribute
to teams/not discussed at meeting.
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
Tuesday,
November
25, 2003 at 7:30pm in the Commission Room at Town Hall/posted on the
door--held
in Town Hall Meeting Room
AGENDA:
O&G
report and one from from Barry Blades and Fletcher Thompson showed
first
cut at reducing winning bids for site work by up to $1.3 million;
all bids are not in for 3-4-5 school. Owner's Rep reported that
Army
Corps of Engineers approval (last one needed in order to go out to bid)
is due November 26th. Please click
here
for "About Town's" notes on Middle School Auditorium schematic
design phase (in 2002). How this project has come to a design
competition
will be explained at Special Building Committee meeting Tuesday,
December
2, 2003 at 7:30pm in the Town Hall Meeting Room.
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
Wednesday,
November 19, 2003, 7:30pm, Commission Room at Town Hall
AGENDA
includes:
O&G
report
on Bid results on the high school (15 different contracts);
overall
bid result is $45,000 under budget, but concern for possible inadequate
contingency suggests some trades be negotiated vis a vis changes in
details.
O&G
recommendation
on sitework; send it out again or cut, cut,cut--very serious that this
part of project is so far out of compliance with what professional
estimators
(2 of them--one from O&G, one from F&T) valued work at last
April.
Update on
design competition; will be a speeded up process and will produce
excitement and ideas by the end of January. (Funded by excess in
design development budget for W.M.S. Auditorium - Item 3 on Referendum.)
Invoices for
payment (subcommittee).
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
November 12,
2003, 7:30pm, Commission Room at Town Hall
Agenda
includes
Morehouse Farm Park update/discussion of DEP letters, no conclusion;
O&G
report on results of High School bid (next week Monday, Tuesday and
Wednesday
bid openings); sitework (including 3-5 school)/high bids and only 3 of
them--discussions to come with lowest bidders; Design Competition re:
W.M.S.
Auditorium/Performing Arts Center proposed for end of January (F-T
contract
a consideration)--expert retained to organize this use of remaining
funds
in Auditorium budget-design development phase; bills reviewed by
subcommittee
("About Town" did not stay).
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
October 29,
2003, 7:30pm, Commission Room at Town Hall
AGENDA -
site
video proposal (for long range record of construction), Army Corps
update
- soccer field intrusion causes OK to be withdrawn until further
explanation
and proof allows Army Corps approval to be re-issued, tree removal of
ceremonial
trees a major effort and will be pursued; plus O&G report and
introduction
of main leadership team.
Weston
School
Building Committee/Building Committee, October 22, 2003 at 7:30pm,
Commission
Room
"Pros and
Cons" of Bisceglie start dates discussed as part of O&G
report/report
from secondary source indicates that this work will not move ahead at
this
time; Morehouse Farm Park, DEP visit to campus and "pre-bid
meetings"
discussed - "About Town" will be videotaping the Selectmen's debate
across
the parking lot, so we will not be present at the Building Committee
(to
be ready for broadcast Monday, October 27th).
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE, October 15, 2003 at &:30pm,
Commission Room at Town Hall
Present:
8 of 10 members of the School Building Committee (missing two members
of
the Building Committee); members of the School Board,
administration
staff, graduate student observer; Parks and Recreation;
public.
REPORTS:
Long report from O&G and Construction Manager on progress on all
matters;
introduction of High School team construction leaders--discussed at the
end of the meeting in public session re: qualifications of this
group
for managing the complex project. Discussion of bid alternates.
WESTON
BUILDING
COMMITTEE/SCHOOL BUILDING COMMITTEE, OCTOBER 8 AT 7:30PM, COMMISSION
ROOM
Link to
schedule
for bidding HERE. (Please note that precise
dates
may change, but the concept of sending everything out to bid in a timed
release for Thanksgiving (indeed, we are grateful that construction is
on the horizon (BANG, CLANG). November 12 - 25 is the window when
ALL bids are due (at this time).
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
Wednesday,
October 1, 2003, 7:30pm, Commission Room at Town Hall
AGENDA/what
happened - Ten (10) members of the School Building Committee were
present...The
most significant part of this meeting was a discussion of "Building
Award"
schedule, led by O&G. We were not aware that approval to go
to
bid is so very, very close at hand, with release of drawing to
Construction
Manager next week sometime, with estimates for when bids would be
returned
all after Election Day except for "site work" - due November 3.
Everything
else is later.
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
Wednesday,
September 17, 2003, 7:30pm, Commission Room at Town Hall
AGENDA
- Attendance
- Members
and Others/Owner's Rep has surgery and is resting in Yale New Haven
Hospital
- good luck and best wishes!!!
- Call
meeting to
order/all present but Superintendent of Schools (open school week on
the
campus); member of the Building Committee standing in for Owner's Rep
and
taking minutes;
- Approve
minutes
of September 10, 2003/done.
- Status
of Approvals:
- Army
Corps of
Engineers/waiting for DEP.
- CT
DEP
Inland
Wetlands/to have a date for decision by this Monday, September 22, 2003;
- CT
DEP
Flood Management
Certification/awaiting others.
- STC
-
DOT Application
Review/tentative OK, but on the October agenda (could be sufficient
material
in support to not prevent project from going out to bid;
- Fletcher-Thompson
Status Report/discussion of how bids will be structured...
- O&G
Status
Report/report on Morehouse Farm Park storm management protections;
- Review
of Invoices/"About
Town" left at this point (and thus does not know if Triton invoices
were
approved);
- Building
Committee
review of Triton invoices
- ADJOURNMENT
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
Wednesday,
September 10, 2003, 7:30pm, Commission Room
AGENDA
- Minutes
August
27, September 3/approved
- Status
of approvals:
Army Corps, CT DEP inland wetlands, CT DEP flood management, CT STC -
DOT
permit/no news - Hartford visit Thursday.
- Triton
environmental
invoices - meetiung with Triton President/payment to be made after
final
check off procedures
- O&G
- introduction
of proposed project manager, project engineer and project
superintendent
for 3 to 5 school/O&G staff (not AP - the partner organizarion) to
be assigned to work on the 3-5 school
- F-T
report/nothing
new so no report
- Discussion
of
proposal from Construction Consulting Group for "MEP" constructability
review services (?)/"About Town" did not stay for this item.
WESTON
SCHOOL
BUILDING COMMITTEE/BUILDING COMMITTEE
Wednesday,
September 3, 2003, 7:30pm, switched back to Commission Room (overflow
at
Conservation)
AGENDA
- Status
of Required
Approvals: a)SFU b)Army Corps c)CT DEP Inland
Wetlands
d)CT DEP Dam Safety e)CT DEP Flood Management Certificate
f)CT
STC-DOT/moving ahead--should know by end of the month
- Report
on Soccer
Field/moving ahead, no lights at this point
- Report
by Leggette,
Brashaeres & Graham on water supply/two new wells almost OK'd (pump
tests ending at midnight--further paper work, but should be OK)
- O&G
- Bid
results on Bisceglie Park and Update on Morehouse Farm Park/below
estimates
for project (original) - together, Parks and Rec projects under
Referendum
budget
- Fletcher-Thompson
- Architect's report/no news (relates to first item)
WESTON
BUILDING
COMMITTEE/SCHOOL BUILDING COMMITTEE
Wednesday,
August 27, 2003
AGENDA
- Item
added to
the agenda to discuss need for 30+ space pull-in angle parking on
School
Road for parking lot overflow during construction at High School
(temporary)/Police
Chief approves, superintendent, high school principal confirm need for
SENIORS only/School Building Committee votes 6-2 in favor of request.
- Status
of required
approvals:/nothing final on any of them...Army Corps, CT DEP Dam
safety,
CT DEP Flood Certification, CT DEP Inland Wetlands, CT STC - DOT
- Milone&MacBroom:
requested changes at Morehouse Farm Park, DOT request of bypass lane at
Bisceglie Park, Proposal from Milone&MacBroom for redesign of
Bisceglie-Scribner
Park/seeding hillsides underway, limit to ground disturbance proposed
and
approved by Building Committee on upper field (s); bypass land a
minor revision to widen travelway at entrance to Bisceglie Park
suggested
by State Traffic Commission.
- O&G
update
on Morehouse Farm Park/this report included construction scheduling for
different access points (Fire Chief present).
- Invoices
for payment/"About
Town" left at this point.
WESTON
BUILDING
COMMITTEE/SCHOOL BUILDING COMMITTEE
Wednesday,
August 20, 2003 7:30pm, Commission Room
AGENDA/no
action taken (not a quorum)
- Status
of Required
approvals (SFU, DEP [500 yr flood, Inland Wetlands, Dams, Sewage
Disposal],
DPH Water Supply, State Traffic Commission/DOT, Army Corps of
Enginers);/Army
Corps waiting for CT - looking to early September until all OK's are
buttoned
up.
- Report
on Morehouse
Farm Park and Bisceglie Park Projects: Schedule, Current and
projected
costs vs. budget, O&G recommendations
- Report
on Hurlbutt
windows and H.S. Fire Alarm/looking good for being completed on time.
- Site
Logistics
Plan/to be discussed next week.
- Soccer
Field Report/Tree
Hearing Tuesday re: trees to be removed for lights.
- Revson
Property
Line/survey shows Town owns land where neighbor built fence.
WESTON
BUILDING
COMMITTEE/SCHOOL BUILDING COMMITTEE
Wednesday,
August 13, 2003, 7:30pm, Commission Room
"About Town"
did not attend complete meeting (we left at 9:30pm) - however, opening
part of Building Committee public meeting Army Corps of Engineers
spokesman
spoke and indicated that he was awaiting CT DEP approval of flood
management
work OK (?) before he issued his findings. General disruption
caused
by CT budget crisis (retirements of those handling Weston's
application--also
in Department of Public Health--causing delay in schedule). We
are
now @30 days behind and in danger of running up against winter
construction
delays.
Wednesday,
August 6, 2003, 7:30pm - CANCELLED
Weston
Building
Committee/School Building Committee
July 30,
2003,
7:30pm, Commission Room
AGENDA:
Fletcher-Thompson
to present choice for "finishes" for 3-4-5 school and additions to
Weston
High School/done and approved, generally; Board of Education to
present
the program for the Middle School Auditorium/done, and then Weston
Education
Foundation proposed to fund-raise for balance of cost...renovations
at WMS revised; discussion of the Zenon plant.
WESTON
BUILDIUNG
COMMITTEE/SCHOOL BUILDING COMMITTEE
July 23,
2003,
7:30pm, Commission Room
AGENDA:
Lots of
discussion
of...final site plan for 3-4-5 school, for approval; O&G
report
a work in progress: 1)Morehouse Farm Park 2)Hurlbutt
windows
3)Bisceglie-Scribner Park 4)High School Fire Alarm 5)Campus
water supply; F-T reported on SFU comments, progress,
other;
Owner's Rep: 1)Soccer field 2)Zenon plant contract
3)recovery
of bid bond (Hurlbutt) - good news!
WESTON
BUILDING/SCHOOL
BUILDING COMMITTEE
July 16,
2003,
7:30pm, Commission Room
Project
manager
for Soccer Field introduced/experienced Weston resident; Zenon
plant
proposal/to be OK'd by next week by MacDonald-Sharpe; O&G
Report
- a)Morehouse including irrigation bids b)Hurlbutt c)High
School
Fire Alarm d)Bisceglie-Scribner Park/discussed and progress
reported
on all fronts!
WESTON
BUILDING
COMMITTEE/SCHOOL BUILDING COMMITTEE
July 9,
2003,
7:30pm Commission Room
AGENDA
Fletcher-Thompson
report/informal review with Army Corps, DEP, EPA, U.S. birds and fishes
people just completed; Review and discussion of high school final
cost estimate led by O&G and F-T/search for possible revisions to
material
selection; O&G report: a)Morehouse/moving ahead but
some
decisions to be made soon on completion dates b)Hurlbutt/in
progress
(window sample shown) c)Soccer field/report that contract awarded
for man-made material field d)Modular classrooms/moving along
(Board
of Education report) e)Morehouse irrigation out for bids
(hopefully)
7-15 f)Bisceglie fields out for bid (hopefully) 7-22.
Quorum
present, First Selectman - no votes taken.
Weston
Building
Committee/School Building Committee
Wednesday,
June 25, 2003, 7:30pm, Commission Room at Town Hall
Bills, (done
at the end--did not stay for this); COMPLETE membership of
Building
Committee and member of the School Building Committee take care of
several
important matters: Ok sending out Fire Alarm bids for High School
(existing). Board of Education to pay some of this cost
differential
(I think that is what I heard). Hurlbutt Window project moving
ahead
smartly; Morehouse Farm Park still behind; Artificial Turf
bids to be reviewed by Field Committee (not using School Bond
$$)--School
Building Committee authorizes Owner's Rep to move this forward;
long
discussion of final cost estimate for High School work. Construction
Manager
reporting that now 6% overage--however, some of this may be due to lag
in updating drawings prior to estimator looking at them--Building
Committee
sees the need to have "bid alternates" for several pieces of the detail
so that project can move ahead without delay. "About Town" left
the
meeting at 9pm.
Weston Building Committee/School
Building Committee
June 18, 2003, 7:30pm, Commission
Room at Town Hall
AGENDA (quorum only of Building
Committee--those items NOT involving Referendum projects voted upon)
Minutes, McDonald-Sharpe contract,
Milone&MacBroom contract, Triton (Parks and Rec) Bisceglie (3)
invoices,
McDonald-Sharpe (2) invoices.
WESTON
BUILDING
COMMITTEE AND SCHOOL BUILDING COMMITTEE
June 11,
2003,
7:30pm Library
AGENDA
Minutes;
Playing
Fields presentation (all weather proposal)/taken off agenda; OK's
sought for the following: change order Resun/more to come;
Special testing lab contract/OK'd; McDonald-Sharpe contract/more to
come;
Milone and MacBroom contract for additional services/more next
week;
Triton (P&R) 3 invoices/Parks and Rec to recheck prior to payment
(by
Town Administrator); McDonald-Sharpe invoices - 2/more to
come;
WHS phasing/discussion; Fletcher-Thompson report/good progres on
Xenon plant design--more to come; O&G report and review of final
3-4-5
cost estimate/over $1 million estimated on the high side--"add
alternates"
in bid to overcome any problems staying within budget.
Weston
Building
Committee/School Building Committee, Wednesday, May 28, 2003, 7:30pm,
Commission
Room at Town Hall
AGENDA
Minutes
approval/done,
invoices for payment/some OK; Owner's Rep report opens up discussion of
timing of construction of fields and Army Corps progress, status of
applications
with Conservation Commission; F-T reports on treatment plant design,
visual
tools to explain project to Westonites, and latest on landscaping;
O&G
reports on contract administration and planning for construction (soon,
we hope); continuation of environmental invoices from previous
meeting--"About
Town" left at 10pm before any decrision about this was made.
Weston
Building
Committee and School Building Committee May 21, 2003, 7:30pm,
Commission
Room at Town Hall
AGENDA
Approval of
minutes; discuss and approve two (2) proposals for additional services
from Milone & MacBroom; discuss and approve Triton
Environmental
invoices/Some of the work done by both consulting firms OK'd;
more
information asked from Parks and Rec. at next meeting...
School Building Committee, May 14,
2003, 7:30pm, Commission Room at Town Hall
AGENDA
Approve minutes/done; F-T
report on brick/on display on School Road; SFU - good news (OK's fpr
major
projects expected in mid-summer), stormwater management (in the works
for
School Road); Sub Committee on finishes, colors, materials/met
and
reported and will keep meeting as issues emerge; REVSON FIELD
LEACH
FIELDS/20' x 700' to DEP - waiting OK; request for School
Building
Committee approval of funds for assistance to the Fire Marshal and
Building
Official/done; O&G report on Hurlbutt windows and Morehouse
Farm
Park/windows to get new contractor and Morehouse Farm Parl on hold
again;
invoices from Triton/to discuss next week.
School
Building
Committee meeting May 7, 2003 cancelled; item on Conservation
Commission
agenda Wednesday, May 7, 2003, Commission Room, "receipt of
application:
installation of leach fields within 100 feet of regulated area at
Revson
Field (Town of Weston)."
Building
Committee/School
Building Committee, Wednesday, April 30, 2003, 7:30pm, Commission Room
at Town Hall
AGENDA
- Minutes/ok
- Report
in Conservation
Commission OK for School Campus Site Plan/report of 5-0 approval,
thanks
given to Barry Blades for clear presentation
- Report
on High
School S.F.U. "completion test"/6 hours preliminary review - no major
complications...more
reviews to come
- Fletcher-Thompson
request for approval to go to S.F.U. on May 6, 2003 for Middle School
and
Hurlbutt site work/done.
- Progress
on construction:
a)Hurlbutt windows and b)Morehouse Farm Park/glass reviewed
(Hurlbutt), well tests discussed (Morehouse).
- Invoices
for approval/NOTE:
sub-committee work, conducted after rest of meeting completed.
Building
Committee/School
Building Committee, Wednesday, April 23, 2003, 7:30pm, Commission Room
AGENDA:
- Discuss
Referendum
results/done - question from audience (attorney for neighbor);
- Invoices
for payment/deferred;
- Correspondence
discussion (2 letter, F-T, Triton environmental, 1 e-mail);
- F-T
reported on
S.F.U. successful meeting on the 3-4-5 school (April 15);
- F-T
presents plans
and documents for S.F.U. review of the High School on April 29, 2003
for
signatures/done.
- Discussion
will
take place re: "TVing" future School Building Committee
meetings/regular
monthly meetings and special working meetings where significant matters
on the table considered OK - left to Chair. to decide when/which, etc.
SPECIAL MEETING SCHOOL BUILDING
COMMITTEE
Tuesday, April 15, 2003, 7:30pm,
Commission Room at Town Hall (no agenda posted 24 hours in advance)...
School Building Committee,
Wednesday,
April 16, 2003, 7:30pm, Commission Room at Town Hall (canelled).
Special Meeting of the School
Building
Committee/Building Committee Thursday, (April 10) on the Town Clerk's
calendar
Tuesday, 7:30pm, "CR"...cancelled.
School Building Committee and
Building
Committee, Wednesday, April 9, 2003 at 7:30pm (NOTE: "members may want
to attend the ATBM at 8:30pm in W.H.S."), Town Hall Commission Room
AGENDA
Approve minutes; sign plans for
3-4-5, sign forms for S.F.U. review; Presentation of Scenario
3 costs.
School
Building
Committee and Building Committee, April 2, 2003, 7pm, Town Hall
Commission
Room
AGENDA
- Minutes
approved.
- Ellen
Uzenoff's
questions - discussion/sobering discussion, upshot appears to be
Referendum
April 22 may very well call a halt to the entire project for a
considerable
time.
- Recommendations
re hiring water supply system engineering firm - Leggette, Braeshears
and
Graham retained.
- Recommendations
re hiring Construction firm to build Morehouse Farm Park project/done -
BIG savings because low bidder is @$1,000,000 under budget (???)
- At
8:30pm School
Building Committee ended meeting and went to the Meeting Room to attend
the Conservation Commission hearing on the school campus application.
Building
Committee and School Building Committee, Wednesday, March 26, 2003 at
7:30pm,
Commission Room at Town Hall:
AGENDA
1. Attendance
2. Call meeting to order
3. Approve minutes of March
12 and 18/done
4. Chief Land will discuss
security at Morehouse Farm Park - done, to be continued as matters
develop.
5. Discussion of proposals
from Engineering Firms for Campus Water Supply System - top two will be
invited for next week's meeting
6. Discuss suggested Forum
article - now the Referendum is set, how will this be done?
7. Discuss
Fletcher-Thompson/Blades
and Goven request for additional fees - put off for a bit
8. Request approval of
additional
services proposal from Triton Environmental - not sure what was done.
9. Request approval of
Fletcher-Thompson
invoices - not sure what was done
10. Present Morehouse Farm Park
bids-preliminary/"About Town" left at this point.
Tuesday,
March
18, 2003, 7:30pm, Commission Room at Town Hall - bills reviewed,
proposals
for water system briefly discussed and no decision made. After
this
meeting, Sub-committee on Finishes went over high school lighting again.
Conservation
Commission denies (March 15, 2003) for the second time ("without
prejudice")
application by the Town of Weston for septic and playing fields and
parking
area at Bisceglie Park. Previous denial July
2002--vote
on that denial taken at a Saturday special meeting, reasons supplied
later...reasons
this latest time:
- The
applicant
has not adequately responded to the concerns or reasons set forth in
the
original denial in two of the three reasons stated and the issue of
feasibility
and prudent alternative is not adequately addressed.
- The
applicant
has not presented evidence that there will be no significant impact as
a result of its proposed activity.
T
H E R EV S O
N F I E L D I S S U E N E V E
R S E E M S T O G
O A W A Y . . .





WHO WAS IN CHARGE OF REVSON FIELD REDO 2011?
WHO'S ACCOUNTABLE FOR ITS USE & CONDITION GOING FORWARD? ANSWER: BOARD OF EDUCATION
FROM "ABOUT TOWN"
NOTES
(unofficial
information) - one of the problems is that soils are compacted (and not
very porous soils to begin with) at Revson; 12-14-11 - Wrong angle?:
- First
word of STEAP
grant announced by First Selectperson at Selectmen 10-7-2010;
Parks&Rec contracts for work in 2011 and then the rains came (more
details to come);
- Heavy
rains another culprit? How about Native American artifacts
emerging as field is aerated?
- Speaking
of draining properly, "About Town" presents what might be the
explanation for Revson ponding as well as discussions of the artificial
turf football field...in addition to swales or whatever:
please read this from our notes from a previous Building Committee
meeting: "...and
ponding would only take place on the field after more than two inches
of
rain had fallen (in an hour?)".
- Reverse chronologic order from "About Town"
Building Committee/School Building Committee meeting notes...whenever
Revson
is mentioned (did not follow up on Maki-Levi issue, as
it did not seem to be
important to the issue of why Revson Field not draining properly):
Weston schools accept Revson Field
from town
Weston FORUM
Written by Kimberly Donnelly
Friday, 20 July 2012 06:50
Town and school officials walked the
entire Revson Baseball Field on Monday and, for a change, they were
very pleased.
"It rained almost three inches last
night, and Revson would be playable this afternoon," said Dave Ungar,
head of the Parks and Recreation Department. "It's incredible ... in
the past, the field would have been closed for three days... Even
Bisceglie [ballfields aren't] playable today."
Revson has been plagued with
drainage issues since it was built during the school construction
project nearly 10 years ago. Estimates to entirely reconstruct the
varsity and JV fields ran to well over $1 million, so that option was
never pursued.
After numerous failed attempts to
fix the field for less money, the town thought it finally had an
affordable solution last year when it hired Aqua-Turf of Orange for
about $145,000 to excavate, grade and replace the infield clay, sod,
and loam in the infield and install new drains and repair the
irrigation system in the outfield.
But Aqua-Turf, which was supposed to
finish the job in six weeks, still hadn't done the work to the town's
satisfaction after almost nine months. The town declared Aqua-Turf had
abandoned Revson.
It hired, instead, Sports Turf
Specialists to replace infield clay, National Irrigation to replace
damaged and incorrectly sized irrigation heads, and Peloso and Sons to
fix the sod. In addition, school maintenance crews helped get the field
in shape.
After the walk-through on Monday,
officials found that the field is finally draining properly and the
schools accepted the field from the town, Mr. Ungar said.
"The project wasn't without its
bumps and bruises, but it has really paid off," Mr. Ungar said.
Walking the field with Mr. Ungar
were First Selectman Gayle Weinstein; Town Administrator Tom Landry;
John Conte, town engineer; Joanne Keating, finance director for the
school district; Dan Clarke, the school district's director of
facilities; and Rocco Popoli, head of field maintenance for the schools.
Ms. Weinstein said last year, the
school district took over the responsibility of maintaining all the
school fields and grounds except for Revson. By accepting the field,
the district will now be responsible for its upkeep, as well.
"I think everyone is happy with
what's finally happened, keeping in mind that no field will ever be
perfect," Ms. Weinstein said.
When the Babe Ruth baseball league
finishes its season at the end of this week — it has been using the JV
field at Revson — the entire field area will be completely closed to
the public. School personnel will do work that is still needed on the
JV field, and both fields will be allowed to rest "so they should be
perfect for the fall," Ms. Weinstein said.
Executive Session
on July 5, 2012 goes for an hour- no action taken.
ON THE AGENDA AT SPECIAL 8:45AM BOARD OF SELECTMEN 7/5/12
FROM THE
C.G.S. Sec. 1-200:
(6) "Executive
sessions" means a meeting of a public agency at which the public is
excluded for one or more of the following purposes: (A) Discussion
concerning the appointment, employment, performance, evaluation, health
or dismissal of a public officer or employee, provided that such
individual may require that discussion be held at an open meeting;

Revson Field is 'beautiful' and 'amazing:' New contractors complete
work in record time
Weston FORUM
Written by Kimberly Donnelly
Wednesday, 27 June 2012 11:18
Revson Baseball Field has been
called a lot of things — many of which cannot appear in print — but
rarely has it been called "beautiful." But that's just what First
Selectman Gayle Weinstein called it when she got a look at it last week.
"I'm so excited. It's looking
beautiful!" she said. "The infield looks amazing" and "the irrigation
system actually works," Ms. Weinstein said.
By Monday of this week, much of the
varsity field at Revson was completed, with just some details left to
complete. This is no small matter for a project that has been ongoing —
and has faced ongoing hurdles — for more than seven years.
Ms. Weinstein said the infield was
"re-renovated" by Dennis Brolin of Sports Turf Specialists, who
replaced substandard clay; the irrigation system was "re-completed"
last week by National Irrigation, which replaced damaged pipes with
new, correctly sized ones; and Frank Peloso of Peloso and Sons fixed
the sod, after lifting a 40x40 section, removing rocks and replacing
topsoil, and leveling the area.
Ms. Weinstein said there are still
some small divots to be filled on the outfield and some hydroseeding to
be done, and the sod has to rest for several weeks to allow it to take
root before the field can be played on.
The remediation work took just a few
weeks, after nearly a year of missteps and inactivity by the
contractor, Aqua-Turf, at the problem-plagued field. But the latest
renovation efforts are just the latest in a long line of attempts to
make safely playable a field that most agree was never properly built
to begin with.
History
The baseball field was constructed
just north of Weston Middle School during the $80-million school
building project (which included building the intermediate school,
renovating and adding to the high school, and constructing Morehouse
Farm Park playing fields). A ribbon-cutting ceremony officially opening
Revson took place in 2005.
Flooding problems, like the ones
seen here in March 2010, have plagued Revson since it was built in
2005. —Vivian Simons photo
It has been plagued with drainage
problems ever since, problems that seemed to grow exponentially every
time the town tried to fix the field.
An initial study done in 2006 showed
drainage problems were caused primarily by compaction of the topsoil
and low permeability of the subsoil, likely caused by heavy equipment
on the field during the school construction. It was estimated at that
time it would cost anywhere from $500,000 to upward of $1.2 million to
completely tear up and replace the soil and the irrigation system and
to properly regrade Revson Field.
The town tried desperately to avoid
the cost of entirely re-engineering the field, as well as the
inconvenience of closing the field for a year or more.
Over the years, the town has tried
slowly mixing in new topsoil with the old; aerating and reseeding;
using "shatter penetration" to break up the topsoil and then reseeding
by injection; and adding more topsoil and clay.
Field of glass
At one point, in 2008, the town
discovered that some of the topsoil that had been dumped on the field
included dangerous shards of glass and other debris.
The soil was eventually raked to
remove debris, but the fracturing and aeration provided only temporary
improvements. Drainage problems remained.
The town tried for the next several
years to make improvements to the pitch of the field and to replace
some of the drains.
But the baseball community cried
foul and asked the town to come up with a long-term, realistic solution.
Glass shards were found mixed into
the topsoil at Revson in March 2008. —Patricia Gay photo
Last summer, it looked like the town
had finally devised that solution. With the help of a STEAP (Small Town
Economic Assistance Program) grant, the town devised a plan to renovate
the infield, replace sod, clay, and loam, improve drainage and
irrigation in the outfield, and repitch the field — for both the
varsity and junior varsity fields.
The latest project got off to a
bumpy start. The original project overseer withdrew and initial bids
were scrapped so the project could be rebid to include a topographical
elevation plan in the bid specifications.
Engineering consultants Milone and
MacBroom were hired to oversee the project and Aqua-Turf of Orange,
headed by Marc D'Andrea, was hired last July to do the work.
But heavy rains in the summer
delayed the start of the project — which was originally expected to
take four weeks — until late August. Then Tropical Storm Irene hit.
There were sunny stretches in the fall, but they were interspersed with
heavy downpours that often made it inadvisable to drive equipment on
the already compacted field.
But the mild winter made town
officials question why work wasn't progressing more quickly. At one
point, the lack of activity had the Board of Selectmen considering
replacing Aqua-Turf with a new contractor. It stuck with Mr. D'Andrea,
however, citing concerns about accountability.
But the project continued to stall,
with little progress being made throughout the spring. Problems with
the irrigation system were not fixed to the town's satisfaction and it
was discovered the contractor had installed the wrong kind of clay.
Abandoned
Earlier this month, after Mr.
D'Andrea and Aqua-Turf failed to meet a deadline to complete punch list
items, the town declared the contractor had "abandoned" the project.
This allowed the town to hire
several new people to come in and replace the clay, reinstall an
adequate irrigation system, and properly resod the field.
Most of this work was essentially
completed last week, with just some "nitty gritty details" still to be
done on the varsity field, according to First Selectman Weinstein.
After being updated about the
positive changes at last Thursday's Board of Selectmen meeting,
Selectman Dennis Tracey praised the first selectman and the town
administrator. "It's been a lot of effort, and you and Tom [Landry]
have done a great job pulling it back together from the brink of
disaster," Mr. Tracey said.
"At the end of the day, once
Aqua-Turf was off the project, we were able to make significant
progress," Ms. Weinstein said earlier this week.

According to Weston First Selectman: Contractor has abandoned Revson
project
Weston FORUM
Written by Kimberly Donnelly
Wednesday, 06 June 2012 12:55
The town has claimed the contractor
used the incorrect clay on the infields at Revson and that problems
with a sinking outfield and a faulty irrigation system are his
responsibility. —Kimberly Donnelly photo
Nearly a year after it was started,
the town has declared the Revson Baseball Fields renovation project
abandoned by the contractor, Marc D'Andrea of Aqua-Turf.
"This has been a painful process and
it's been difficult for all of us. It's a shame," said First Selectman
Gayle Weinstein on Monday. But plans are in place to resolve the
problems on the field as soon as possible. "We are getting people we
trust to come in and do the job correctly. Unfortunately, this guy held
us up for the past month," Ms. Weinstein said of Mr. D'Andrea.
"That's a complete lie," Mr.
D'Andrea said when contacted by phone on Tuesday. "I did not abandon
this... I met or exceeded all deadlines. I worked with them very
diligently. This is not right on their part."
The first selectman said the good
news is the town withheld a final payment of $46,000 from Mr. D'Andrea,
and that should be enough to do the necessary repairs to the fields.
"These people are unruly and nothing
is ever good enough... Their intent is not to pay me," Mr. D'Andrea
said.
The project
Aqua-Turf of Orange was hired by the
town in July 2011 for $144,900 to do excavation, grading and
replacement of infield sod, clay and loam, and to install drains in the
outfield to try to improve the drainage problems that have plagued
Revson for years.
Work progressed so slowly, however,
that the town looked into hiring a new contractor in November 2011.
Aqua-Turf stepped up its efforts — until the winter weather made it
impossible to keep working — and the town agreed to continue with
Aqua-Turf.
Ms. Weinstein said at that time that
one of the biggest concerns with regard to changing contractors was
that if there is a problem later with the field not draining properly —
Revson's chronic problem — a switch in contractors part way through
construction would give too many people the opportunity to point
fingers, ultimately making it impossible to determine responsibility.
"We had to take that into
consideration, especially given the history with Revson," Ms. Weinstein
said at the beginning of December 2011.
During the course of digging up the
outfield in the fall and then later in the spring, several things
happened. Some irrigation pipes were damaged by Aqua-Turf's equipment.
But, everyone was aware that would likely happen, and replacing those
pipes and irrigation heads was included in the project. Ms. Weinstein
said the contractor claimed he did, in fact, replace the broken
irrigation lines, but later, after sod was put on the outfield and died
in portions, the town suspected there were still damaged lines.
Mr. D'Andrea confirmed this week he
did replace the irrigation system. The field was dropped by two feet
and the irrigation system was six to eight inches underground, so he
knew ahead of time it would have to be replaced.
Before construction began, he marked
with stakes where the sprinkler heads were located, Mr. D'Andrea said.
When he reinstalled the new system, he did so using the original
measurements, even adding a few additional ones, he said.
"They still think it's not done
right. They inspected it and said it was OK, then they said later it
wasn't," Mr. D'Andrea said. "There's no problem with it. It's done."
Removing debris
The other thing that happened this
spring was the town's public works department helped to remove some
boulders, rocks and debris from the outfield when Mr. D'Andrea claimed
it would cost more money for him to do it because he didn't have the
necessary equipment. Now, with portions of both the varsity and junior
varsity outfields "sinking," Ms. Weinstein said Mr. D'Andrea is claming
the outfield is not his responsibility because the DPW worked on the
field.
Mr. D'Andrea said he was not aware
when he began the project the extent of the debris he would find under
the surface.
"We've uncovered cement fence posts,
an iron catch basin, gates, a swimming pool, part of a house, tree
roots — a lot of crap and nobody told me about this. This was built
incorrectly originally... The entire site — the conditions were
horrid," he said.
Mr. D'Andrea said he has "documented
proof" that it was the DPW that caused the damage to the outfield. He
said he had graded the field to the proper specifications and the town
engineer OK'd it. "It was pitched perfectly and ready to go," Mr.
D'Andrea said.
The very next day, he continued, the
town brought the DPW in to clear the rocks and debris. "They made their
mess," he said.
Mr. D'Andrea also said the town
workers wasted time and effort because they "dug everything up" instead
of simply breaking up smaller rocks, which would have been OK.
"But whatever I said or suggested
was questioned," he said.
Clay
Over the last few weeks, it's the
infield that has been a bigger problem than the outfield.
The contract with Aqua-Turf
specified DuraEdge Classic, an infield clay used on professional
baseball fields, be put at Revson.
When clay was brought in to Revson,
several parents pointed out that the clay at the junior varsity field
and the varsity field looked different — and neither looked quite
right. Mr. D'Andrea insisted he used the DuraEdge Classic, and that he
installed the specified 180 tons, as per the contract, Ms. Weinstein
said, but the town sent the material out to be analysed.
In the meantime, the town wanted to
order more clay but was unsure how much was needed. A representative
from DuraEdge came to look at the field, and he said not only was the
clay that had been installed not theirs, but it contained large
aggregate that was "not suitable for play," Ms. Weinstein said.
The material on the field now is a
mix of red clay, red infield mix, and red stone dust. "We were told it
is more appropriate for a warning edge than an infield," Ms. Weinstein
said.
She said DuraEdge confirmed that Mr.
D'Andrea ordered the correct clay from them, but he never picked it up.
The contractor told town officials he found it elsewhere for less
money, but the town has not seen confirmation of that, the first
selectman said.
On Tuesday, Mr. D'Andrea said of the
town's claim that he used the incorrect clay, "They are incorrect." He
said he followed the specifications in the contract. He believes the
problem has more to do with a sales representative who was "bitter
about not getting the sale."
Mr D'Andrea said he had the clay
tested and told the town what needed to be done to fix the problem, but
they "just kept forcefully making these deadlines."
Ms. Weinstein said legally, the town
had to give Aqua-Turf time to make good on the contract. She said Mr.
D'Andrea was given until noon last Thursday, May 31, to address the
outfield, clay, and several other "punchlist" items. When the town
didn't hear from him, it was determined Aqua-Turf had abandoned the
project.
The town has ordered clay directly
from DuraEdge — DuraEdge Recreational, which is slightly less expensive
and easier to maintain than the originally specified DuraEdge Classic,
but still acceptable and "far superior" to what is there now, Ms.
Weinstein said.
Irrigation
Dennis Brolin of Sports Turf
Specialties is scheduled to install the clay on the varsity field on
June 13 or 14, depending on the weather. At that time, he will give the
town a quote to replace the clay on the JV field, but he told the first
selectman finding a time he is available to do it might prove difficult.
An inspector from National
Irrigation came to the field on Friday, June 1. The inspector "feels
strongly that the outfield issues are due to cracked irrigation lines,"
Ms. Weinstein said in an email update sent Saturday, June 2, to some
members of the baseball community and several town officials, including
the selectmen and the finance board chairman.
National Irrigation has agreed to
come at the end of this week or the beginning of next (depending on
weather) to do a full inspection of the irrigation system, blowing all
the lines and locating cracks on any of the sprinkler heads, Ms.
Weinstein said. The inspection alone is expected to take about three
days, and then any necessary repairs would need to be scheduled.
Ms. Weinstein said repairs to the
sinking outfield were supposed to sart this week, but they will be
postponed until the irrigation work is completed, since that might
entail having to dig up the field in places.
"We have hired Frank Peloso to do
the outfield work, and he is ready to begin as soon as National is
finished with the irrigation system," Ms. Weinstein said in her email.
Ms. Weinstein said, depending on the
extent of the irrigation system damage, she is hopeful the town has
enough money from the original project budget to cover the cost of
replacing the clay on both the varsity and JV fields and fixing both
outfields.
The first selectman acknowledged
that Mr. D'Andrea might try to sue the town for the $46,000 he was not
paid, but she is not overly concerned. "We have documented all that he
has done wrong, including having letters from Dura Edge proving that he
installed the wrong material. He'd be stupid to sue us," she said in
her email.
Mr. D'Andrea said he, too, has
documented proof that he did the job properly and he is not responsible
for the problems that exist at Revson now.
"I completed to spec everything. I
went over and above what I had to do," he said.
Mr. D'Andrea claims the town
"forced" him to work when he shouldn't have — when the field was too
wet — which caused more damage. He said he met often with officials who
were "unruly" and unreasonable. "It was like talking to a brick wall.
They don't understand."
Mr. D'Andrea believes he has been
caught in the middle of a political mess. "I was put through a
nightmare... There have been so many irrational people on this project
that couldn't come to grips. It's severely affected my health" both
physically and mentally, Mr. D'Andrea said.
Selectmen
discuss Revson on Dec. 14, 2011
Revson contractor almost strikes out
Weston FORUM
Written by Kimberly Donnelly
Thursday, 01 December 2011 00:00
The town almost put in a pinch
hitter at Revson baseball field this week, but decided at the last
minute to stick with its starting line-up.
First Selectman Gayle Weinstein said
on Monday the town had solicited bids last week from contractors
interested in taking over construction at the ball fields just north of
Weston Middle School. She had called a special meeting of the Board of
Selectmen to determine whether to switch contractors on the project
because she and other officials — as well as many residents — were so
unhappy with the lack of progress at Revson.
“We were incredibly concerned by the
lack of activity we were seeing,” Ms. Weinstein said. While weather has
certainly been an issue this fall, “we had plenty of nice days we felt
the contractor should have been working, but he wasn’t,” she said.
This past summer, the town hired
Aqua-Turf of Orange for $144,900 to do excavation, grading and
replacement of infield sod, clay and loam, and the installation of
drains in the outfield to try to improve the drainage problems that
have plagued Revson for years.
Much of the field was dug up, but
then work seemed to reach a standstill. Piles of dirt that were there
since early October were still untouched last week.
Ms. Weinstein said town officials
met with Marc D’Andrea, principal with Aqua-Turf, a week ago Saturday
to express their concern at the lack of progress. He said he would be
done in two weeks, Ms. Weinstein said, but then over the next three
days, only one small pile of dirt was moved.
The equipment and manpower allocated
for the job “was completely insufficient,” the first selectman said.
Wet weather has definitely played a
role in the delays. Ms. Weinstein said Mr. D’Andrea said he was being
cautious about driving heavy equipment on the wet soil because of past
problems with compaction on the field.
However, Ms. Weinstein said Town
Engineer John Conte, Town Administrator Tom Landry, Parks and
Recreation Director Dave Ungar, and engineering consultant Tom Shiel
from Millone and MacBroom agreed there had been many days when the
weather was good and the ground was dry enough, but Aqua-Turf was
nowhere to be found.
“Moisture has been miserable this
year,” Mr. Landry said. “But in terms of temperatures, we’ve had good
luck.”
[Workers roll out sod at Revson
Field on Tuesday, Nov. 29. —Patricia Gaty photo]
Workers roll out sod at Revson Field
on Tuesday, Nov. 29. —Patricia Gaty photo
That’s important when it comes to
laying sod on the field, Mr. Landry said. Once there is an extended
period of cold and frost, sod companies stop cutting sod, and once it’s
cut, there is only about a one-week window to install it, he said.
Even though temperatures were
predicted to remain mild this week, the weather window is bound to
close. “There is a real sense we are living on borrowed time,” Mr.
Landry said.
Plan B
Last week, town officials did not
feel as if Aqua-Turf shared their sense of urgency. “We had to come up
with a Plan B,” Ms. Weinstein said. But, she added, they knew if they
were going to change contractors, it had to happen soon.
The goal is to have Revson ready for
the start of the Weston High School Baseball season on March 19, Ms.
Weinstein said.
And so, the day before Thanksgiving,
the first selectman posted notice of a special meeting to be held
Monday, Nov. 28, to determine whether a new contractor should be hired.
Several contractors walked the field last Friday and submitted bids.
But over the weekend, Ms. Weinstein
said Aqua-Turf workers were at Revson and were “able to get a
significant amount of work done... We had a conversation with [Mr.
D’Andrea on Monday] about his need to continue to make that kind of
progress and to meet the deadline,” Ms. Weinstein said.
She said the town did receive two
new bids on Monday, but ultimately decided to “continue the course”
with Aqua-Turf.
Mr. Landry said, “We looked at all
our options... We think this is our best option.”
Ms. Weinstein said the biggest
concern with regard to changing contractors was that if there is a
problem later with the field not draining properly — Revson’s chronic
problem — a switch in contractors part way through construction would
give too many people the opportunity to point fingers, ultimately
making it impossible to determine responsibility.
“We had to take that into
consideration, especially given the history with Revson,” Ms. Weinstein
said.
Weston tries to delay wetlands remediation until next year
Weston FORUM
Written by Kimberly Donnelly
Thursday, 18 August 2011 00:00
Students beginning the new school
year at Weston Middle School and Weston High School may be heading into
the midst of a major construction zone.
Town and school officials are hoping
a letter from Weston Superintendent Colleen Palmer to the Army Corps of
Engineers will allow the town to delay the start of wetlands
remediation work required on the school campus — but the work has
already been delayed for several years.
The Army Corps of Engineers notified
the town last Friday, Aug. 12, that it must begin the first phase of
remediation work this fall so that the second phase can take place in
October.
Tom Landry, town administrator, said
the first phase consists of removing “thousands and thousands of cubic
yards” of dirt and other material from the field between the middle and
high school. The second phase involves crafting a new wetlands area;
the plants required to create the wetlands need to be planted in
October in order for them to “take” properly, Mr. Landry said.
Building project
The requirement to remediate the
wetlands is a result of the school building project that began almost a
decade ago and included building the new intermediate school, and an
addition and renovations at the high school. Mr. Landry explained that
during construction, some of the wetlands were filled in. In order to
be able to do that, the town agreed to construct wetlands elsewhere, he
said.
The town did that in five different
locations, “but they didn’t take,” Mr. Landry said.
A resident complained to the Army
Corps of Engineers, which in turn told the town not to worry about four
of the smaller areas. As far back as 2009, “They said, ‘If you try to
reestablish the wetlands there, it will be a waste of time, so we won’t
make you do it,’” Mr. Landry said.
However, the corps did want the town
to try to remediate the larger area between the middle and high schools.
So the town hired an engineer,
Triton Environmental, to do bid specifications and the project went out
to bid last summer. Mr. Landry said the engineer estimated the work
would cost about $120,000 to $150,000; $120,000 was budgeted to cover
the cost.
When the bids came back, the low bid
was $280,000, and the second lowest was $350,000.
Mr. Landry went back the engineer,
who agreed to go back and talk to the bidders about what was driving
the costs so high and to see if there were any specs that could be
changed to make the cost more reasonable.
The town asked the Army Corps of
Engineers if it could put off the work until the following summer —
this summer. The corps agreed to an extension.
“The engineer finishes his
conversation with the bidders and some things were changed in the
specs,” Mr. Landry said. There was a plan to have those items done by
town employees or separate contractors in order to save money.
This spring, a town meeting approved
an additional $120,000 — to be added to the already approved $120,000 —
for the work, and a second bid package went out.
But when those bids came back, the
low bid was $329,000.
Why so high
“The engineers still don’t know why
they are coming in so high,” Mr. Landry said, although one possibility
is the fact that contractors have to get all their equipment to the
site two different times — once for phase one, when material is
removed, then again in October to plant, he said. “But we’re going to
have to do the work regardless.”
Because the town has already delayed
the project for a year, Mr. Landry was concerned the Army Corps of
Engineers would not simply grant another extension. The town instead
asked the corps if it could “contract for the work now so they know we
are doing it, but not actually do the work until next summer,” he said.
The corps of enginners said it would
like a letter from the schools explaining why the work would be so
intrusive, Mr. Landry said. Dr. Palmer agreed to write the letter,
which Mr. Landry will mail this week. “They will decide if they will
permit us to do the work next summer or not. It’s up to them,” he said.
Dr. Palmer said there are several
reasons why the phase one work would be extremely disruptive while
school is in session. Some of the buildings are not fully air
conditioned, so at the beginning of the school year, many windows are
normally open, exacerbating what would be a noise problem regardless,
she said.
Also, students would not have access
to the field; heavy machinery on site would pose a danger to students
and staff; and it would limit outdoor access for all middle school
students, she said.
“We have to remediate ... but with
appropriate planning, we might be able to better prepare for this,” Dr.
Palmer said.
In any event, phase two work will be
done in October: The question is whether it will be this October or
next.
“Our intention,” Mr. Landry said,
“is to try to do the heavy excavation when school is closed, but we
can’t plant the plants until October,” and that is no small job,
either. “It’s not just a couple of guys with shovels. It will be pretty
disruptive, too.”
Rain delays plague Revson Field
work
Weston FORUM
Written by Kimberly Donnelly
Thursday, 18 August 2011 00:00
Construction work to try to fix the
flood-prone Revson Baseball Fields has been delayed — due to flooding.
“There’s about seven inches of rain
on Revson right now,” said First Selectman Gayle Weinstein Monday
morning.
Aquaturf of Orange had been expected
to start work last week on the $145,000 project, that incudes
excavation, grading and replacement of infield sod, clay and loam, and
the installation of drains in the outfield of the high school’s varsity
and junior varsity baseball fields, located just north of Weston Middle
School.
Heavy rains last week and over the
weekend continued at the beginning of this week, drenching the field
and making work impossible to begin, said Tom Landry, town
administrator.
Once it does begin, work is expected
to take about four weeks.
According to the bid specifications
for the job, contractors were required to finish the work at Revson by
Aug. 26. However, Mr. Landry said because the delay is not the fault of
the contractor, the town will likely grant an extension if needed.
How could low bid be less than half the
high bid?
Low bid for Revson Field in Weston comes in at $144,900
Weston FORUM
Written by Kimberly Donnelly
Thursday, 07 July 2011 00:00
After reviewing the three bids
submitted for drainage work at the Revson Baseball Fields, the town has
identified the low bidder. Aquaturf of Orange submitted a bid total
of $144,873 for the excavation, grading and replacement of infield sod,
clay and loam, and the installation of drains in the outfield. Tom Landry, town administrator, said the
work will be done on both the varsity and the junior varsity fields,
which are located on School Road to the north of Weston Middle School.
The other two bids received were
from Kuwalksy Brothers of Westport ($198,369) and BDE Sports Turf of
Monroe ($314,970).
“There was a pretty good range,” Mr.
Landry said. He explained that the bid specifications asked bidders to
provide costs for five individual items, and there was “quite a
variance” on some of those.
The items included:
A base bid on the
infield replacement and drainage work at the varsity field;
An add alternate
to laser grade the right and center field high elevation points;
An add alternate
to install sod on the newly graded outfield area;
A base bid on the
infield replacement and drainage work at the junior varsity field; and
An add alternate
of additional drainage work at the junior varsity field.
Mr. Landry said it looks like the
town does have enough money put aside for the project to do the work on
both the varsity and JV fields. Half of the cost of the project is
coming from an $86,000 state STEAP (Small Town Economic Assistance
Program) grant. The grant requires the town to match the funds given to
it; those matching funds have already been approved by the town.
All three bidders did a mandatory
walk-through of the site with Milone and MacBroom, the engineering
consultants hired by the town to oversee the Revson project. Before
recommending Aquaturf, however, Milone and MacBroom will talk to
Aquaturf to make sure it fully understands the scope of the project,
Mr. Landry said, and Dave Ungar, director of Parks and Recreation, will
check Aquaturf’s references.
Mr. Landry said an application will
be reviewed by the Conservation Commission at its next meeting on
Tuesday, July 19. If approved, the Board of Selectmen will likely be
asked to award the bid at its regularly scheduled meeting later that
week on Thursday, July 21.
Contractors are required to complete
the work between July 25 and Aug. 26.
PARKS & REC MEETING MONDAY JUNE 13, 2011
Parks &
Rec has item on its agenda June 13, 2011 "Revson Field renovation
project status" so "About Town" attended. Besides the regular
review of operations (fields) and review of proposed gift to Little
League fields operations at Bisceglie, commissioners wanted to know
what the real story was behind Revson report in
the FORUM. And were reassured by knowledge that excellent
engineers will be observing.
Weston's
Revson Field project: Dr. Dest bows out
Weston FORUM
Written by Patricia Gay
Wednesday, 08 June 2011 11:12
William Dest, a soil scientist hired
by the town of Weston to provide
third party oversight on renovations to Revson Field, has withdrawn
from the project.
Dr. Dest, who is from Wethersfield,
has worked for the town on numerous
projects in the past, including an evaluation of Revson Field for
Milone and MacBroom engineering consultants. He was supposed to oversee
the current $186,000 drainage project to alleviate some of the flooding
issues on the Revson baseball field.
But, Dr. Dest said due to a number
of phone calls and e-mails from
people opposed to the project, he decided to withdraw from it.
“I am very unhappy,” said First
Selectman Gayle Weinstein. “I think
it’s a detriment to the town that Dr. Dest has decided not to work on
the project because he was getting inundated and peppered by phone
calls and e-mails from members of the community. Now we have seen what
happens when people try to micromanage projects to that level,” she
said.
“Several people called him again and
again. I think he didn’t need that
kind of aggravation in his life,” said Tom Landry, town administrator.
According to Dr. Dest, he received
calls and e-mails from three
Westonites. He wouldn’t name the callers specifically or what issues
they had, but said, “I could see there were some differences as to what
people thought about the project. I have always enjoyed a good working
relationship with the town and just don’t want to get involved in its
politics.”
On Tuesday, June 7, Selectman Dan
Gilbert and Weston residents Jim
Maggio and Robert Pritsker acknowledged they had contacted Dr. Dest.
Dr. Gilbert said he was disappointed
Dr. Dest had withdrawn. “He has an
excellent reputation and was going to act as an independent third party
to make sure we were on track,” he said.
In a recent e-mail to Dr. Dest, Dr.
Gilbert said he was happy to hear
he had been hired for the project and had been wanting the town to hire
him since November. Dr. Gilbert asked Dr. Dest to review the project’s
bid specifications to ensure the work would improve drainage on the
field.
“My goal was simply to get everyone
on the same page. I think this is unfortunate for the town,” Dr.
Gilbert said.
Dr. Maggio said he had no objections
to Dr. Dest. He contacted him to
find out if he had reviewed the plans for the drainage project because
he had concerns that the plan would be effective.
“My big issue with this project is,
where is the science behind the
plans to support that the piping system being proposed will work?” Dr.
Maggio said.
Mr. Pritsker said he, too, was in
Dr. Dest’s “corner.” As the parent of
a boy who plays baseball, he said he had concerns about whether the
proposed project would work.
“We’ve had a string of
embarrassments on work done to this field. The
original $1.2-million Milone and MacBroom proposal, which came from Dr.
Dest’s recommendations, would work if done to the infields. That is a
guaranteed home run,” he said.
He had doubts that the $186,000
project would do any good. “I think it
is an absolute waste of money and wanted to find out from Dr. Dest if
he thought the project would work in light of what he had proposed in
the Milone and MacBroom report,” Mr. Pritsker said.
Parks and Recreation Director Dave
Ungar said in light of Dr. Dest’s
withdrawal, the town has hired the other bidder for oversight of the
project, Milone and MacBroom. While Dr. Dest’s proposed fee was $5,400,
Milone and MacBroom’s fee is $6,000 plus direct expenses, which could
add up to a total of $6,750.
“We have a finite budget for
renovation to make the field better,” Mr.
Ungar said. “Is the field going to be perfect? It won’t be. We’re
trying to make the field safer and more playable and drain somewhat
better. Do we have the capital to rip the entire field out and start
over? No. We’ve talked to the finance board many times over and have
gotten clear marching orders to make the field better, and make it more
playable for a reasonable dollar amount that the town can swallow,” Mr.
Ungar said.
“No one expects the field to be
perfect. We are hoping for decently playable,” Ms. Weinstein said.
Weston gets STEAP grant
for Revson
Field
Weston FORUM
Written by Kimberly Donnelly
Wednesday, 06 October 2010 11:42
Weston received notice last week
that its application for an $86,000
grant to help repair the ailing Revson Field was approved by the state.
The town is receiving the money from
the Connecticut Small Town
Economic Assistance Program (STEAP). STEAP provides financial
assistance for projects that encourage economic development and
preserve the character of the state’s less-populated towns.
“I’m so excited!” said First
Selectman Gayle Weinstein earlier this
week. She credited Tom Landry, town administrator, and Dave Ungar,
parks and recreation director, for filing the grant application and
following through. “I’m very grateful for all their work,” she said.
The money will be used to make
improvements at the Revson baseball
fields next to Weston Middle School on School Road, primarily to repair
drainage in the outfield, fixing the pitch of the infield, and maybe
for aeration, Ms. Weinstein said.
The proposed infield renovations
include the removal and disposal of
7,500 square feet of current sod and all clay; the installation of 66
yards of screened topsoil, the addition of clay bricks to the pitcher’s
mounds and home plate areas, and grading to the turf and skin.
Drainage renovations include the
installation of two curtain drains on
each field running down the first and third base lines to catch infield
water runoff and channel it to storm drains on School Road; and the
installation of Hydraway drainage systems in the infields and outfields.
The total cost of the entire project
is estimated at $156,200.
Gov. M. Jodi Rell announced the
STEAP grant disbursement, and explained
why she feels the Revson project is deserving of the money. “These
funds will help alleviate the chronic problem of standing water at
Revson Fields,” Ms. Rell said. “Parents have sometimes been reduced to
using ‘kitty litter’ to dry the fields for ball games, even though
other fields in the region have been perfectly playable.”
Revson Field is used primarily by
the Weston High School baseball team
and several other leagues, and has a history of flooding and standing
ground water, making it often unusable for play. Past attempts to
remediate the field have failed.
The state-funded STEAP program
provides funds to eligible towns for
economic development, community conservation and quality of life
projects. To be eligible, a town must have a population of less than
30,000 residents, not be designated as a distressed municipality or a
public investment community and not have an urban center.
A total of $20 million in STEAP
funds for 115 towns was approved when
the state Bond Commission met Aug. 17. The funds will enable 134
projects across the state to move forward.
Ms. Weinstein pointed out that the
STEAP grant requires towns to match
the funds given to them. She had thought she might put the issue on
tonight’s Board of Selectmen agenda, but, while the town was told it
was approved for the grant money, it has not yet received the official
paperwork.
Ms. Weinstein said, as anxious as
she is to move forward, she is going
to hold off on starting the process of approving the matching funds
until that paperwork comes through.
The selectmen must first approve the
$86,000 in matching funds, and
then the finance board needs to approve it. The town must also decide
whether the money will come from a supplemental appropriation from this
year’s budget or if it should be put into next year’s budget, Ms.
Weinstein said.
The Parks and Recreation Department
has had three experts look at the
field in recent weeks, including the groundskeeper from the Bridgeport
Bluefish baseball team. The good news, Ms. Weinstein said, is they all
seem to be in agreement about what should be done to fix the fields,
short of complete replacement, which is estimated to cost upwards of
$1.2 million.
Revson Field's water woes: After
five years where do we go from here?
Weston FORUM
Written by Patricia Gay
Wednesday, 05 May 2010 11:42
When Revson Field on School Road in
Weston officially opened on May 14, 2005, there was a ribbon-cutting
ceremony and much excitement about the two new baseball diamonds that
were about to emerge.
But unlike real diamonds, any
sparkle and brilliance the ballfields had quickly faded. It is doubtful
there will be much of a fifth year anniversary celebration for Revson
next week.
Responding to complaints from
organizations that use Revson Field, First Selectman Gayle Weinstein
met last week with members of the Board of Education, Parks and
Recreation, and other town officials to come up with a strategy for
dealing with Revson’s future.
She plans to discuss the meeting
further with the other selectmen Thursday, May 6, at 7:30 at town hall.
“One thing that came out of the
meeting,” Ms. Weinstein said, “is that maintenance at Revson has not
been handled the best it can be.”
Plagued
In the past five years, Revson has
been systematically plagued by drainage problems, resulting in
continous standing water in the outfield and infield. Most noticeable
in the spring — when other town fields are open for business after a
rainstorm — Revson has had to occasionally close.
The high school varsity baseball
team, which uses Revson as its home field, has been especially affected
and has forfeited games because the field was deemed unfit for play.
Last year, parents resorted to putting kitty litter on the infield to
soak up some water and make it playable.
A report done by Milone &
MacBroom civil engineers in 2006 identified multiple deficiencies in
Revson’s design and construction, and offered solutions ranging in cost
from $500,000 to $1.2 million — all involving closing the field for at
least a year.
Parks and Recreation Director Dave
Ungar said at present the town is not planning a complete overhaul. “To
renovate the field entirely would cost a huge amount of money. We are
looking for cost effective ways to keep the field playable at this time
and avoid digging the field up completely. We are maintaining it the
best we possibly can to make sure the baseball teams have a facility
they can use,” he said.
Deficient conditions
Before being converted to two
baseball fields, Revson was a soccer field. It was re-constructed in
2005 at the same time as the sewage treatment plant across the street,
as part of the School Building Committee project for the intermediate
school and high school.
“Revson Field has deficient
conditions and that’s what everyone has inherited — a facility that
isn’t what it is supposed to be,” said Tom Landry, town administrator.
Septic leaching fields for the
treatment plant were installed beneath Revson. When the field was dug
up to install the septic fields, topsoil taken from the field was put
into mounds and eventually placed back on top of Revson.
Critics of the project claim that
after Revson was dug up, it was covered with heavy clay content and
impervious muck from other parts of the building project.
Mr. Landry said that wasn’t the
case. “The same stuff that was dug up while working on the leaching
fields was put back on top. There was also some stuff used from [what
is now] the turf field, but that wasn’t the reason for the problem. The
problem was the characteristics of the material were prone to
compacting. It became so compacted it was virtually like stone, and
water couldn’t penetrate it,” he said.
After the original soil was
re-added, an additional foot and a half of topsoil was spread over the
field. “The water goes through the topsoil just fine, but when it
reaches that hardpan, the water just sits there. Grass roots are just
floating in water and there isn’t healthy, vegetative growth on the
field,” Mr. Landry said.
When asked if re-shaping the slopes
on Revson turned it into a “bowl” shape that could have affected
drainage, Mr. Landry said that wasn’t the case and the fields did not
become “bowl shaped.”
He also said wetlands mitigation the
town was supposed to do on another part of the school property did not
contribute to Revson’s problems either.
Fracturing and aeration
In October 2007, the town approved a
supplemental appropriation of $65,000 to pay an outside company for the
fracturing and aeration of the field in order to try to improve
drainage.
The company that was awarded the
contract subsequently dumped topsoil that contained glass and other
debris on the field, requiring intensive raking to make it suitable for
play.
In the end, the fracturing and
aeration provided only temporary improvement.
“There were several fixes, and
anecdotally I was told the field was better for awhile, but it is back
to how it originally was with very slow water drainage. The problems
are worse and aren’t getting better,” Mr. Landry said.
In the upcoming fiscal year,
starting July 1, the town has budgeted $20,000 for repairs to Revson
Field. Sports organizations expressed concern that the $20,000 is just
a “Band-Aid” approach and will not satisfactorily fix the drainage
problems.
“We had a frank and earnest
discussion at the meeting this week. The goal this year is to improve
maintenance and keep the fields in a playable condition. Eventually a
more expensive solution that involves digging up the entire field may
be necessary. But with a price tag of $1 million plus, it is not
something we can put in the town’s capital budget right now,” Mr.
Landry said.
Teams overcome obstacles to make
use of Revson Field
FORUM
by Patricia Gay
May 29, 2008
Despite a rocky start this spring,
baseball teams have been able to utilize Revson Field.
“The high school baseball team
played games on the field, and the Babe Ruth League is using it. I’m
glad the seniors were able to have a home field,” said Dave Ungar,
Parks and Recreation director.
Use of the ballfield was in jeopardy
in March, when a large quantity of glass and debris was found embedded
in the outfield.
In November 2007, the town
contracted with Athletic Field Services of Westchester to aerate the
field in an effort to provide better drainage. The field has a history
of retaining a lot of water when it rains. The company also deposited
160 tons of topsoil in the outfield.
In April, after glass was discovered
in the outfield, the company came back twice to rake and remove the
debris.
During this same time period, St.
Joseph’s College on Long Island reported similar problems on a soccer
field that was also covered with debris-laden topsoil supplied by
Athletic Field Services.
Still found
After the raking, some shards of
glass and other foreign objects were still found on the field. So five
weeks ago, Tom Landry, town administrator, said he sent a follow-up
letter to the company’s owner, Flavio LaRocca, asking him to come back
and look at the field again — something Mr. LaRocca promised he would
do if the town still had issues after the second raking.
Mr. Landry said he received no
response to his letter, so he sent another one about a week ago. Still
getting no response, Mr. Landry said he started calling Mr. LaRocca.
“We’ve been playing telephone tag. I called again and implored his
secretary to have him call me,” Mr. Landry said.
Mr. Ungar said the raking helped
quite a bit, and the town’s groundskeepers pick up foreign objects when
they see them. “Our main concern was the liability of a field that had
debris on it,” Mr. Ungar said.
Positive note
On a positive note, Mr. Ungar said
he has received feedback from the high school athletic director and
varsity baseball coach that field playability was adequate this year
and the fields have drained better than in the past couple of years.
“It’s hard to say because there was
no rain for a long period of time, and then the rain seemed to come on
weekends,” Mr. Ungar said.
But he thought the aeration process
may have helped with drainage.
The field was scheduled to have more
aeration work done this spring, but after the debris was discovered,
the next phase was put on hold. “My hunch is the project may go out to
bid,” Mr. Ungar said.
The project did not go out to bid
when Athletic Field Services was hired by the town’s Building Committee
in November. Balking at a price tag of upwards of $1 million to
re-engineer the field, at the urging of the Building Committee, the
town instead opted to hire Athletic Field Services to use a much less
expensive “shatter penetration and aeration” method to try to remediate
the field.
Committee member Don Gary, who
worked on the Revson project, said he had no immediate comment about
next steps for the field.
Revson is not the only ‘Field of
Glass’ - Soccer field on Long Island
has the same problem
Weston FORUM
Mar 26, 2008
When mysterious shards of glass and
other debris were found embedded throughout the outfield at Revson
Baseball Field two weeks ago, the news was an unwelcome surprise to
town officials and the Weston community.
“It’s pretty unimaginable,” Tom
Landry, town administrator, said. Resident Bob Walpuck called Revson a
“field of screams.”
But when Don Lizak, the athletic
director of St. Joseph’s College in Long Island, heard about the
situation in Weston, it came as no surprise to him. Mr. Lizak has
had to contend with large quantities of glass on one of the playing
fields on his college campus, too.
“In December, one of our physical
plant workers was walking along the soccer field and discovered pieces
of glass all over it,” Mr. Lizak said.
His descriptions of the glass
fragments found there sounded just like those uncovered at Revson.
“There were all kinds of thick glass pieces, pottery, ceramics, and a
lot of other trash and debris. It was very dangerous,” Mr. Lizak said.
Common bond
As it turns out, Weston, Conn., and
St. Joseph’s College in Patchogue, Long Island, have a common
bond. Both utilized the services of Athletic Field Services Inc.
to supply their fields with topsoil. Athletic Field Services, a
company based in Larchmont, N.Y., bills itself on its letterhead as
“Specialists in athletic field construction, renovation, and
maintenance services.”
In early November 2007, the town of Weston hired Athletic Field
Services to remediate drainage problems on Revson Field utilizing a
“shatter penetration and aeration” method. The town also
contracted with the company to supply and spread 160 tons of topsoil
over the outfields at Revson and an adjoining ball field, and 40 tons
of clay over the two infields. The total cost of the project was around
$42,000.
Don Gary, a member of the town’s building committee, and Dave Ungar,
director of parks and recreation, said the company appeared to do the
work as requested.
But two weeks ago, a school maintenance worker noticed widespread glass
and debris on Revson as he was preparing the field for spring baseball
practice.
St. Joseph’s
In November 2007, Athletic Field
Services also performed aeration work at St. Joseph’s. The company also
supplied and spread topsoil over its soccer field, Mr. Lizak
said. A few weeks later, a large quantity of glass was discovered
on the field. “We immediately called the company and complained,” Mr.
Lizak said.
He said the company’s owner, Flavio
LaRocca, came out to inspect the soccer field and initially denied
responsibility for the glass. “He was uncooperative, defensive and not
very good to deal with. He was also rude to our staff,” Mr. Lizak said.
He said Mr. LaRocca tried to blame a
consultant, who was no longer working for the company, for ordering bad
topsoil, but Mr. Lizak didn’t believe him. According to Mr.
Lizak, eventually Mr. LaRocca did take responsibility and agreed to
rake the field to clear the glass. “He brought in a team of about six
workers and they combed the field,” Mr. Lizak said.
But as soon as it rained, more glass
surfaced.
Frustrated by the actions of
Athletic Field Services, Mr. Lizak brought in an outside company to
comb the field again. “They raked up a huge amount of glass,” Mr. Lizak
said. In February, after more rain, yet more glass surfaced. The
field was then closed. “It couldn’t be used for soccer,” Mr. Lizak said.
He said the school’s baseball team
walked the field and picked up pieces of glass to clear a small section
to be used in a limited capacity as part of the baseball team’s
outfield.
“We have had quite a few people on
the field cleaning it, but the glass is still there. We are playing
cautiously on a small part of the field, but we can’t use it for
soccer,” Mr. Lizak said.
Still dissatisfied with the
performance of Athletic Field Services, Mr. Lizak said the college is
not paying for work the company has done and is consulting with an
attorney about next steps.
“This is not a comforting feeling,
just waiting for someone to get hurt. From an administrative
standpoint, this is a nightmare,” Mr. Lizak said.
Closed
Back in Weston, Revson Field
was supposed to be open by now for use by the Weston High School
baseball team, but due to safety hazards posed by the glass, it has
been closed until further notice. At a meeting held Wednesday,
March 19, Mr. Landry and Mr. Gary were joined by town attorney Patricia
Sullivan, Selectman Gayle Weinstein, and others in an examination of
Revson Field.
“I was surprised. I didn’t expect to
see something like that on a ballfield,” Ms. Sullivan said.
Afterwards, Mr. Landry said he
directed Ms. Sullivan to draft a letter to Athletic Field Systems
saying the field was unusable and immediate attention was needed to
address the problem. Two days later, on Saturday, March 22, Joe
Fitzpatrick, chairman of the building committee, joined Mr. Landry, Mr.
Gary, and Mr. Ungar on Revson Field to discuss the problem first-hand
with Mr. LaRocca.
“We walked the entire field. Mr.
LaRocca said it was terrible and he had never seen anything like it
before. He said he would fix it,” Mr. Gary said.
According to both Mr. Gary and Mr.
Landry, Mr. LaRocca said he would bring a crew of 10 or 12 workers with
steel rakes, to intensely comb the field standing shoulder to shoulder.
“He said he would also do more aeration if necessary and would come
back again if there was any more glass,” Mr. Gary said.
Mr. LaRocca did not return repeated
phone calls this week asking for comment.
Focus
Mr. Landry said his first
focus in this matter was to get the contractor to act responsively.
“We’ll see how it goes from there,” he said. He also said the town was
having the soil tested to make sure there weren’t any chemical
contaminants in it.
According to the written agreement
with the town, the company was supposed to supply “160 tons of
specified topsoil mix,” and the materials were guaranteed by the
manufacturer/supplier.
“It certainly appears that
inappropriate fill was put on the fields,” Ms. Sullivan said.
Selectman Weinstein said she is
concerned for kids using Revson Field. “We want the kids to get onto
the field as soon as possible,” she said.
But she also wants to ensure the
field is safe. “We need to make sure that Athletic Field Services pays
for the repairs. What happens if frost or rain comes and more glass
comes to the surface? I want the problem fixed now so we don’t have to
go through this whole thing next year,” she said.
She has also asked members of the
Building Committee, which is overseeing Revson and other projects, to
come to the selectmen’s next meeting to report where the committee
stands on Revson and its other projects.
“With this kind of financial
environment, we need to know where every dollar is going to be spent,”
she said.
Mr. Berkowitz, the high school
athletic director, said he hopes the problems at Revson can be resolved
quickly for the sake of the baseball team’s schedule.
“We had to cancel a scrimmage we had
set for Saturday,” he said.
For now, the team is utilizing the
multi-purpose turf field and is practicing in the gym. “I would like to
believe the person who sees what his company did would fix it. That’s
what you would expect from someone who expects to get more business,”
Mr. Berkowitz said.
Weston
weighs ways to fix drainage woes at Revson
Weston FORUM
by KIMBERLY DONNELLY
Sep 13, 2007
Weston’s revamped Revson Field just
north of Weston Middle School has been plagued with difficulties since
its ribbon cutting more than two years ago.
Now the town is struggling with the
best and most economical way to remediate drainage problems there.
Last Thursday, Sept. 6, Don Gary of
the town Building Committee went before the Board of Selectmen to ask
for a supplemental appropriation of approximately $65,000 (spread out
over 15 months) for renovations to the two baseball fields at Revson.
The board made a motion to approve
the appropriation, but withdrew the motion after several concerns were
brought forward by members of the audience, Jim Maggio and William
McDonough.
Dr. Maggio, who is a petitioning
candidate for selectman, pointed to a report by Milone & MacBroom,
commissioned by the town in September 2006, that states the drainage
problems at Revson are caused primarily by “compaction of the topsoil
and the very low permeability of the subsoil.”
The report states, “The structure of
the topsoil at the site was found to be platy below three to five
inches from the surface, indicating that the fields had been compacted
with heavy equipment during the construction operation.”
The report indicates that William
Dest, a consulting agronomist and soil scientist who helped evaluate
the field, offered several alternatives for renovating the fields in
order to address the drainage problems.
One suggested solution involves
tearing up the entire field, removing all the old, over-compacted soil
and replacing it with new soil, regrading, and reseeding. It would also
mean replacing the irrigation lines.
Cost estimates for this range from
about $500,000 to $600,000, and using this approach the fields would be
out of service for about a year.
A second option would be to remove
topsoil and blend it with sand, making it more resistant to compaction.
A layer of gravel would be installed on top of the subsoil.
This alternative would also mean
having to replace irrigation lines, would necessitate regrading and
reseeding, and would put the fields out of commission for at least a
year.
Milone & MacBroom estimated the
cost for this plan to be $1 million to $1.2 million.
A third option is installing a slit
drain system, in which vertical trenches are dug into the topsoil
layer, a small pipe, connected to a header pipe to collect water, is
placed at the bottom, and the trench is filled with sand.
This alternative, estimated to cost
$750,000 to $850,000, would put the field out of commission for one
season.
The report notes, however, that this
option would “not relieve the compaction of the subsoil, nor will it
resolve the depressions in the playing surface,” which are also noted
as a contributing factor to the drainage problems.
Another option
The Building Committee is proposing
another option, however. About 160 tons of soil would be brought in and
mixed slowly with the existing soil. It involves reseeding, and also
making some repairs to the infield, First Selectman Woody Bliss said.
This would be done over time — in
the fall, the spring, and then again next fall, so as to minimally
interrupt the sports seasons of teams that use the fields.
“I think it’s a pretty interesting
alternative,” Mr. Bliss said earlier this week. “The fields would be
out of play a little bit, but I don’t think we would lose a whole
season.”
With an estimated price tag of about
$65,000, “it’s a heck of a lot less expensive than any of the other
options,” Mr. Bliss said. “My feeling is it is probably worth a try.”
He cautioned, however, that none of
the proposed alternatives can guarantee the drainage problems at Revson
will be entirely fixed.
What the Building Committee is
proposing, though, has worked in other places, Mr. Bliss said, and, he
added, “from an engineering standpoint, it appears it may well have a
chance of succeeding.”
At the meeting on Thursday, Dr.
Maggio said surface aeration techniques such as the one the Building
Committee is proposing, because they don’t address the subsoil
compaction, would not fix the underlying problem.
“It seemed foolhardy and a Band-Aid
fix that would not treat the underlying cause, while allowing the
responsible parties to disappear into the sunset,” Dr. Maggio said
after the Board of Selectmen meeting.
Mr. McDonough told the selectmen he
believes the drainage problem stems in part from a failure to create a
wetlands area between the middle school and the high school as agreed
upon with the Army Corps of Engineers before the field was constructed.
Mr. McDonough also cited the grading
of the field — from what used to be a gentle slope that drained
naturally to what is now “shaped like a dish” — as one of the reasons
for the drainage problems.
Mr. Bliss said the selectmen asked
Dr. Maggio and Mr. McDonough if they had discussed this with the
Building Committee and the board was told they had not.
The selectmen withdrew the motion to
approve the supplemental appropriation at this time, and asked that Dr.
Maggio and Mr. McDonough bring their concerns to the attention of the
Building Committee.
“The Building Committee is really
the proper place to have these discussions,” Mr. Bliss said.
WESTON
SCHOOL BUILDING COMMITTEE, Wednesday, November 29, 2006, 7:30pm,
Commission Room, Town Hall
2)
Revson Field Report: Selectman’s comments to letter of 11/16
meeting TL / SBC/nothing in writing
WESTON SCHOOL BUILDING
COMMITTEE, Wednesday, November 15,
2006, 7:30pm, Commission Room, Town Hall
2)
Revson Field Report: Selectman’s comments to letter of 11/7 if any/no
one present was able to make the next Board of Selectmen's meeting.
WESTON
SCHOOL BUILDING COMMITTEE, Wednesday, November 1, 2006, 7:30pm,
Commission Room, Town Hall
No quorum, no
actions. Discussion of all items: note item #2.
2) Revson Field
Report: SBC Review/ citizens involved in school athletics came to try
to find out why Revson Field doesn't drain properly.
WESTON
SCHOOL BUILDING COMMITTEE, Wednesday, March 1, 2006, 7:30pm, Commission
Room at Town Hall
c)
Site:
iv)
Revson Field ball field drainage/not draining rapidly or totally so
that fields are not dry in two days
WESTON
SCHOOL BUILDING COMMITTEE, Wednesday, November 30, 2005,
7:30pm, Commission Room at Town Hall
d)
Site:
i)
Fencing at Revson Field on Collin’s border; update/memo from Town (and
other correspondence) presented - vote 5-2 to recommend no action
(please remember that this is not the official record of this
meeting--we did not have copies of all of the items in the file to
review);
WESTON
SCHOOL BUILDING COMMITTEE, Wednesday, November
9, 2005,
7:30pm, Commission Room at Town Hall
c)
Site:i) Fencing at Revson Field on Collin’s
border/discussed and further information needed for full review as per
Selectmen's request.
WESTON SCHOOL
BUILDING COMMITTEE, Wednesday, August
31, 2005, 7:30pm,
Commission Room at Town Hall
New
Items:
a)
Revson Field sprinkler update/in progress
b)
Revson Field Silt Fencing Removal & Additional Drainage/must leave
silt fencing in place
WESTON
SCHOOL BUILDING COMMITTEE, Wednesday, August
24, 2005,
7:30pm, Commission Room at Town Hall
New Items:
a) Revson Field
Irrigation/Town and school project to share cost
WESTON
SCHOOL BUILDING COMMITTEE, Wednesday, Dec. 8, 2004,
7:30pm, Commission
Room at Town Hall
- Review
of Maki / Levi property/School Building Committee recognized that the
construction project damaged the Maki-Levi property (took down the
trees and brush that formed a natural buffer between Revson Field and
the M-L property) although there should have been not action taken
within the natural buffer as shown on plans. Replacement
foliage/trees will be installed at the opportune time for best growth
possibility.Landscape budget review/amount identified for Army Corps
required work, buffer for all neighbors affected who have come forward
so far and funds for stone wall in front of high school.
NOTE: memorial trees included in this funding: total of
@$250,000 obligated.
- b)
Revson Field;/DEP says OK to use plant i) DEP approval
status
SPECIAL WESTON SCHOOL BUILDING COMMITTEE, Monday,
November 22, 2004 at 7:30pm, Commission Room at Town Hall
d)
Revson Field;
i)
DEP Approval status/due soon
ii) Fence along property line/needs remediation
WESTON SCHOOL BUILDING COMMITTEE,
Wednesday,
November 17, 2004, 7:30pm, Commission room at Town Hall
b) Revson Field; DEP Operation
status; concrete
dugout pads
i) DEP Operation status/due end of
November.
ii) Concrete dugout pads/not in the plans as of now.
WESTON
SCHOOL BUILDING COMMITTEE, Wednesday, November 10, 2004, 7:30pm,
Commission Room at Town Hall
Revson
Field; DEP operation status; Sprinkler review; concrete dugout
pads/not yet, not until Spring and not in contract.
WESTON SCHOOL BUILDING COMMITTEE,
Wednesday, November 3, 2004, 7:30pm, Commission Room at Town Hall
b) Revson Field; Yard
Drains/moving ahead.
c) Revson Field; DEP Sprinkler approvals/not to get this 'til
other parts of project work.
WESTON SCHOOL BUILDING COMMITTEE,
Wednesday, October 20, 2004, 7:30pm, Commission Room at Town Hall
- O&G
work progress reports: briefly noted...
a) Revson Field; Yard Drains; in
progress
b) Revson Field; DEP Sprinkler
approvals - in progress
WESTON SCHOOL BUILDING COMMITTEE, Wednesday,
October 13,
2004, 7:30pm, Commission Room at Town Hall
O&G:
progress on Revson (last week of October
next progress point)...sprinkler requirements for Revson (will need
watering alot)
WESTON SCHOOL BUILDING COMMITTEE,
Wednesday October 6, 2004, 7:30pm Commission Room at Town Hall
- Revson
Field/moving along OK
WESTON SCHOOL BUILDING COMMITTEE,
September 29, 2004, 7:30pm, Commission Room at Town Hall
- O&G to report on work
in
progress: Revson Field/getting
done, although rain interferes;
WESTON
SCHOOL BUILDING COMMITTEE,
September 22, 2004, 7:30pm, Commission Room at Town Hall
Carl Charles to discuss sod at Revson Field/done - vote
to move ahead with sod from a new locally connected contractor.

Weston Family Fourth returned in 2006!
*It
turns out that, although agendas for School Building Committee meetings
thru August 25, 2004 were posted as "School Building Committee
/Building
Committee" - by a vote of 7-1 members (2 absent) of both groups voted
to
advise the Board of Selectmen to not to increase the size of the School
Building Committee (it is now 10--recent resignation of #11, long-time
representative on Building Committee). The future agendas for
both
bodies will be posted separately in the Town Clerk's
Office. For
link to "old" BUILDING COMMITTEE notes, click HERE.